Monthly Local Let Maintenance Report For Abilene District As Of Jan 11, 2017 Page 2 Of 3

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySCURRY
HighwayUS0084
FromVARIOUS LOCATIONS IN SCURRY COUNTY
ToVARIOUS LOCATIONS IN SCURRY COUNTY
CSJ6288-74-001
Proj IDSUP - 628874001
Work TypePICNIC AREA MAINTENANCE
 
0.00116750.0022235.0099.9
Work Order08-19-15
Work Began09-01-15
Work Completed
Time Computed09-01-15
Contract Working Days365
Addl Days Granted365
Working Days Charged488
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
WEST TEXAS CENTERS/MHMR
SUBCONTRACTOR(S) FOR CCSJ: 6288-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07150832
Totals16750.001180.0022235.0099.9

CountyBORDEN
HighwayFM1054
FromFM 1054 BRIDGE @ COLORADO RIVER
ToFM 1054 BRIDGE @ COLORADO RIVER
CSJ6289-37-001
Proj IDRMC - 628937001
Work TypeROADWAY AND BRIDGE REPAIRS ON FM
 
0.001647009.480.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6289-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07150801
Totals647009.480.000.000.0

CountyBORDEN
HighwayUS0180
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6295-70-001
Proj IDRMC - 629570001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001110145.0065560.0059.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-31-16
Work Began05-31-16
Work Completed
Time Computed05-31-16
Contract Working Days25
Addl Days Granted0
Working Days Charged16
Percent Time Used64
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6295-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01160801
Totals110145.000.0065560.0059.5

CountyFISHER
HighwayUS0180
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6295-72-001
Proj IDRMC - 629572001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001170632.0099081.9858.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-01-16
Work Began00-00-00
Work Completed
Time Computed06-01-16
Contract Working Days47
Addl Days Granted0
Working Days Charged34
Percent Time Used72
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6295-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01160803
Totals170632.000.0099081.9858.0

CountyJONES
HighwayUS0180
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6295-75-001
Proj IDRMC - 629575001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001279500.00172345.0061.6
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed06-08-16
Contract Working Days97
Addl Days Granted0
Working Days Charged46
Percent Time Used47
Contractor(s)
KENNETH THOMASON
SUBCONTRACTOR(S) FOR CCSJ: 6295-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01160806
Totals279500.0064475.00172345.0061.6

CountyKENT
HighwayUS0380
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6295-76-001
Proj IDRMC - 629576001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001109399.5096831.0088.5
Work Order05-16-16
Work Began00-00-00
Work Completed
Time Computed06-08-16
Contract Working Days47
Addl Days Granted0
Working Days Charged43
Percent Time Used91
Contractor(s)
KENNETH THOMASON
SUBCONTRACTOR(S) FOR CCSJ: 6295-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01160807
Totals109399.5031678.5096831.0088.5

CountyMITCHELL
HighwayIH0020
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6295-77-001
Proj IDRMC - 629577001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001234640.00147070.0062.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-02-16
Work Completed
Time Computed06-02-16
Contract Working Days90
Addl Days Granted0
Working Days Charged47
Percent Time Used52
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6295-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01160808
Totals234640.000.00147070.0062.6

CountyNOLAN
HighwayIH0020
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6295-78-001
Proj IDRMC - 629578001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001220831.00139178.0063.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-01-16
Work Began00-00-00
Work Completed
Time Computed06-08-16
Contract Working Days92
Addl Days Granted0
Working Days Charged61
Percent Time Used66
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6295-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01160809
Totals220831.000.00139178.0063.0

CountySCURRY
HighwayUS0084
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6295-79-001
Proj IDRMC - 629579001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001208314.95124460.7059.7
Work Order06-02-16
Work Began06-27-16
Work Completed
Time Computed06-20-16
Contract Working Days84
Addl Days Granted0
Working Days Charged53
Percent Time Used63
Contractor(s)
GREG SCRUGGS
SUBCONTRACTOR(S) FOR CCSJ: 6295-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01160810
Totals208314.950.00124460.7059.7

CountySTONEWALL
HighwayUS0380
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6295-81-001
Proj IDRMC - 629581001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001124737.0080203.5064.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-16-16
Work Began06-13-16
Work Completed
Time Computed06-01-16
Contract Working Days57
Addl Days Granted0
Working Days Charged37
Percent Time Used64
Contractor(s)
KENNETH THOMASON
SUBCONTRACTOR(S) FOR CCSJ: 6295-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01160812
Totals124737.000.0080203.5064.2

CountyTAYLOR
HighwayUS0277
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6295-82-001
Proj IDRMC - 629582001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001159992.9099958.1462.4
Work Order06-15-16
Work Began00-00-00
Work Completed
Time Computed07-19-16
Contract Working Days44
Addl Days Granted0
Working Days Charged28
Percent Time Used63
Contractor(s)
GREG SCRUGGS
SUBCONTRACTOR(S) FOR CCSJ: 6295-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01160813
Totals159992.900.0099958.1462.4

CountyTAYLOR
HighwayIH0020
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6295-83-001
Proj IDRMC - 629583001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001287512.00190408.0066.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-26-16
Work Completed
Time Computed00-00-00
Contract Working Days128
Addl Days Granted0
Working Days Charged80
Percent Time Used62
Contractor(s)
GREG SCRUGGS
SUBCONTRACTOR(S) FOR CCSJ: 6295-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01160814
Totals287512.000.00190408.0066.2

CountyHOWARD
HighwayIH0020
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6295-84-001
Proj IDSUP - 629584001
Work TypeLITTER REMOVAL
 
0.00184732.8577399.1391.3
Work Order11-17-15
Work Began12-01-15
Work Completed
Time Computed12-01-15
Contract Working Days365
Addl Days Granted0
Working Days Charged361
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6295-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11150830
Totals84732.858324.9777399.1391.3

CountyCALLAHAN
HighwayUS0283
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6295-85-001
Proj IDSUP - 629585001
Work TypePICNIC AREA MAINTENANCE
 
0.00116112.0014660.0090.9
Work Order12-24-15
Work Began01-01-16
Work Completed
Time Computed01-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged335
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6295-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11150832
Totals16112.001452.0014660.0090.9

CountyTAYLOR
HighwayUS0277
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6295-86-001
Proj IDSUP - 629586001
Work TypePICNIC AREA MAINTENANCE
 
0.00116592.0015992.0096.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-01-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6295-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11150833
Totals16592.000.0015992.0096.3

CountyCALLAHAN
HighwayUS0283
FromVARIOUS LOCATIONS IN CALLAHAN
ToVARIOUS LOCATIONS_IN CALLAHAN
CSJ6295-87-001
Proj IDSUP - 629587001
Work TypeLITTER REMOVAL IN CALLAHAN COUNTY
 
0.00162240.3956678.8991.0
Work Order01-22-16
Work Began02-01-16
Work Completed
Time Computed02-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged335
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150830
Totals62240.394041.5256678.8991.0

CountyTAYLOR
HighwayUS0083
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6295-88-001
Proj IDSUP - 629588001
Work TypeLITTER REMOVAL
 
0.001133577.2299810.8974.7
Work Order01-22-16
Work Began02-01-16
Work Completed
Time Computed02-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged304
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6295-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150831
Totals133577.2211296.9199810.8974.7

CountyTAYLOR
HighwayUS0083
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6295-95-001
Proj IDSUP - 629595001
Work TypeADDITIONAL LABOR ONSITE ATTENDANT
 
0.00124960.0023856.0095.5
Work Order12-24-15
Work Began01-01-16
Work Completed
Time Computed01-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11150831
Totals24960.002040.0023856.0095.5

CountyHOWARD
HighwayMR0686
FromBIG SPRING STATE HOSPITAL
ToBIG SPRING STATE HOSPITAL
CSJ6296-92-001
Proj IDRMC - 629692001
Work TypeDRAINAGE AND DRIVEWAY IMPROVEMENTS
 
0.011105953.180.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days25
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6296-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03160804
Totals105953.180.000.000.0

CountyTAYLOR
HighwayBI0020R
FromVARIOUS LOCATIONS IN TAYLOR, CALLAHAN,
ToSHACKELFORD, JONES & HASKELL COUNTIES
CSJ6297-66-001
Proj IDRMC - 629766001
Work TypeINSTALLATION OF PAVEMENT MARKINGS
 
0.010210984.59256504.9999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-26-16
Work Completed
Time Computed08-26-16
Contract Working Days20
Addl Days Granted0
Working Days Charged11
Percent Time Used55
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6297-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160801
Totals210984.590.00256504.9999.9