| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | TAYLOR |
| Highway |
FM3438 |
| From |
TAYLOR HQ OFFICE |
| To |
TAYLOR HQ OFFICE |
| CSJ |
6242-21-001 |
| Proj ID |
RFC - 624221001 |
| Work Type |
CONCRETE APRON |
| |
|
0.001 |
21440.00 |
0.00 |
21440.00 |
99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
05-30-12 |
| Work Began |
05-30-12 |
| Work Completed |
|
| Time Computed |
05-30-12 |
| Contract Working Days |
35 |
| Addl Days Granted |
0 |
| Working Days Charged |
2 |
| Percent Time Used |
5 |
| Contractor(s) |
| 3-A GLASS & CONSTRUCTION |
SUBCONTRACTOR(S) FOR CCSJ: 6242-21-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04120832 |
|
Totals |
21440.00 |
0.00 |
21440.00 |
99.9 |
|
| County | STONEWALL |
| Highway |
US0083 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6242-44-001 |
| Proj ID |
SUP - 624244001 |
| Work Type |
LANDSCAPE MAINTENANCE |
| |
|
0.001 |
20000.00 |
5000.00 |
20000.00 |
100.0 |
| Work Order |
04-30-12 |
| Work Began |
05-01-12 |
| Work Completed |
04-29-13 |
| Time Computed |
05-01-12 |
| Contract Working Days |
365 |
| Addl Days Granted |
10 |
| Working Days Charged |
364 |
| Percent Time Used |
97 |
| Contractor(s) |
TIBH INDUSTRIES, INC. BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 6242-44-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
03120830 |
|
Totals |
20000.00 |
5000.00 |
20000.00 |
100.0 |
|
| County | TAYLOR |
| Highway |
US0083 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6242-64-001 |
| Proj ID |
SUP - 624264001 |
| Work Type |
JANITORIAL MAINTENANCE |
| |
|
0.001 |
78582.24 |
6125.00 |
70957.24 |
90.2 |
| Work Order |
06-01-12 |
| Work Began |
06-01-12 |
| Work Completed |
|
| Time Computed |
06-01-12 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
334 |
| Percent Time Used |
91 |
| Contractor(s) |
TIBH INDUSTRIES, INC. E.Q.U.I.P. ENTERPRISES |
SUBCONTRACTOR(S) FOR CCSJ: 6242-64-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04120830 |
|
Totals |
78582.24 |
6125.00 |
70957.24 |
90.2 |
|
| County | FISHER |
| Highway |
SH0070 |
| From |
SH 70 @ COTTONWOOD |
| To |
CREEK BRIDGE |
| CSJ |
6248-34-001 |
| Proj ID |
BPM - 624834001 |
| Work Type |
BRIDGE REPAIR |
| |
|
0.065 |
64795.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
36 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| L.C. JORDAN & SON |
SUBCONTRACTOR(S) FOR CCSJ: 6248-34-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04130803 |
|
Totals |
64795.00 |
0.00 |
0.00 |
0.0 |
|
| County | HOWARD |
| Highway |
IH0020 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6248-58-001 |
| Proj ID |
RMC - 624858001 |
| Work Type |
MOBILE RETROREFLECTIVITY DATA COLLECTION |
| |
|
0.010 |
37308.63 |
12031.59 |
12031.59 |
32.2 |
| Work Order |
04-01-13 |
| Work Began |
04-01-13 |
| Work Completed |
|
| Time Computed |
04-08-13 |
| Contract Working Days |
32 |
| Addl Days Granted |
0 |
| Working Days Charged |
18 |
| Percent Time Used |
56 |
| Contractor(s) |
| TRP CONSTRUCTION GROUP, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6248-58-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
02130801 |
|
Totals |
37308.63 |
12031.59 |
12031.59 |
32.2 |
|
| County | BORDEN |
| Highway |
US0180 |
| From |
VARIOUS LOCATIONS IN BORDEN CO. |
| To |
VARIOUS LOCATIONS IN MITCHELL CO. |
| CSJ |
6249-26-001 |
| Proj ID |
RMC - 624926001 |
| Work Type |
MOWING HIGHWAY RIGHT OF WAY |
| |
|
0.001 |
197512.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
58 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| 3JB CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6249-26-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11120801 |
|
Totals |
197512.00 |
0.00 |
0.00 |
0.0 |
|
| County | CALLAHAN |
| Highway |
IH0020 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6249-27-001 |
| Proj ID |
RMC - 624927001 |
| Work Type |
MOWING HIGHWAY RIGHT OF WAY |
| |
|
0.001 |
165348.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
50 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| MANN ROBINSON & SON, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6249-27-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11120802 |
|
Totals |
165348.00 |
0.00 |
0.00 |
0.0 |
|
| County | NOLAN |
| Highway |
IH0020 |
| From |
VARIOUS LOCATIONS IN NOLAN CO. |
| To |
VARIOUS LOCATIONS IN FISHER CO. |
| CSJ |
6249-28-001 |
| Proj ID |
RMC - 624928001 |
| Work Type |
MOWING HIGHWAY RIGHT OF WAY |
| |
|
0.001 |
275580.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
74 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| GREG SCRUGGS |
SUBCONTRACTOR(S) FOR CCSJ: 6249-28-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11120803 |
|
Totals |
275580.00 |
0.00 |
0.00 |
0.0 |
|
| County | JONES |
| Highway |
US0083 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6249-29-001 |
| Proj ID |
RMC - 624929001 |
| Work Type |
MOWING HIGHWAY RIGHT OF WAY |
| |
|
0.001 |
176160.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
65 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| KENNETH THOMASON |
SUBCONTRACTOR(S) FOR CCSJ: 6249-29-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11120804 |
|
Totals |
176160.00 |
0.00 |
0.00 |
0.0 |
|
| County | STONEWALL |
| Highway |
US0380 |
| From |
VARIOUS LOCATIONS IN STONEWALL CO. |
| To |
VARIOUS LOCATIONS IN HASKELL CO. |
| CSJ |
6249-30-001 |
| Proj ID |
RMC - 624930001 |
| Work Type |
MOWING HIGHWAY RIGHT OF WAY |
| |
|
0.001 |
196936.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
66 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| HASKELL TRACTOR SERVICE |
SUBCONTRACTOR(S) FOR CCSJ: 6249-30-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11120805 |
|
Totals |
196936.00 |
0.00 |
0.00 |
0.0 |
|
| County | KENT |
| Highway |
US0380 |
| From |
VARIOUS LOCATIONS IN KENT CO. |
| To |
VARIOUS LOCATIONS IN SCURRY CO. |
| CSJ |
6249-31-001 |
| Proj ID |
RMC - 624931001 |
| Work Type |
MOWING HIGHWAY RIGHT OF WAY |
| |
|
0.001 |
172854.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
64 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| KENNETH THOMASON |
SUBCONTRACTOR(S) FOR CCSJ: 6249-31-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11120806 |
|
Totals |
172854.00 |
0.00 |
0.00 |
0.0 |
|
| County | SHACKELFORD |
| Highway |
US0180 |
| From |
VARIOUS LOCATIONS IN SHACKELFORD CO. |
| To |
VARIOUS LOCATIONS IN TAYLOR CO. |
| CSJ |
6249-32-001 |
| Proj ID |
RMC - 624932001 |
| Work Type |
MOWING HIGHWAY RIGHT OF WAY |
| |
|
0.001 |
157614.95 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
59 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| GREG SCRUGGS |
SUBCONTRACTOR(S) FOR CCSJ: 6249-32-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11120807 |
|
Totals |
157614.95 |
0.00 |
0.00 |
0.0 |
|
| County | TAYLOR |
| Highway |
US0083 |
| From |
VARIOUS LOCATIONS IN TAYLOR COUNTY |
| To |
VARIOUS LOCATIONS IN CALLAHAN COUNTY |
| CSJ |
6249-55-001 |
| Proj ID |
RMC - 624955001 |
| Work Type |
CLEAN AND SEAL CRACKS AND JOINTS |
| |
|
0.001 |
78936.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
02-25-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
03-04-13 |
| Contract Working Days |
13 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| AUSTIMPACTORS LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6249-55-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10120801 |
|
Totals |
78936.00 |
0.00 |
0.00 |
0.0 |
|
| County | NOLAN |
| Highway |
US0084 |
| From |
US 84 |
| To |
IH 20 |
| CSJ |
6249-62-001 |
| Proj ID |
EMC - 624962001 |
| Work Type |
US 84 EMERGENCY BRIDGE REPLACEMENT |
| |
|
0.040 |
1564229.50 |
264058.00 |
647570.00 |
41.3 |
| Work Order |
03-04-13 |
| Work Began |
03-11-13 |
| Work Completed |
|
| Time Computed |
03-11-13 |
| Contract Working Days |
74 |
| Addl Days Granted |
0 |
| Working Days Charged |
35 |
| Percent Time Used |
47 |
| Contractor(s) |
| J. H. STRAIN & SONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6249-62-001 CONTRACTORS SERVICE COMPANY(1.11%) D. I. J. CONSTRUCTION, INC.(1.53%) TEXAS SHAFTS, INC. (8.03%) MCL CONTRACTING, LLC (1.10%)
|
| Contract # |
02130899 |
|
Totals |
1564229.50 |
264058.00 |
647570.00 |
41.3 |
|
| County | HOWARD |
| Highway |
MR0686 |
| From |
BIG SPRING STATE HOSPITAL IN |
| To |
HOWARD COUNTY |
| CSJ |
6249-63-001 |
| Proj ID |
RMC - 624963001 |
| Work Type |
PARKING AREA - CURB AND GUTTER |
| |
|
0.010 |
327712.45 |
48144.26 |
48144.26 |
14.6 |
| Work Order |
04-01-13 |
| Work Began |
04-19-13 |
| Work Completed |
|
| Time Computed |
04-08-13 |
| Contract Working Days |
51 |
| Addl Days Granted |
0 |
| Working Days Charged |
17 |
| Percent Time Used |
33 |
| Contractor(s) |
| PRICE CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6249-63-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
02130803 |
|
Totals |
327712.45 |
48144.26 |
48144.26 |
14.6 |
|
| County | BORDEN |
| Highway |
US0180 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6249-65-001 |
| Proj ID |
RMC - 624965001 |
| Work Type |
PICNIC AREA AND LANDSCAPE MAINTENANCE |
| |
|
0.001 |
26967.87 |
2000.00 |
7269.97 |
26.9 |
| Work Order |
12-27-12 |
| Work Began |
01-03-13 |
| Work Completed |
|
| Time Computed |
01-03-13 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
118 |
| Percent Time Used |
32 |
| Contractor(s) |
| RAIRE MANAGEMENT SERVICES, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6249-65-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10120803 |
|
Totals |
26967.87 |
2000.00 |
7269.97 |
26.9 |
|
| County | TAYLOR |
| Highway |
IH0020 |
| From |
VARIOUS LOCATIONS |
| To |
VARIOUS LOCATIONS |
| CSJ |
6250-63-001 |
| Proj ID |
RMC - 625063001 |
| Work Type |
ILLUMINATION MAINTENANCE |
| |
|
0.001 |
183695.00 |
17119.00 |
29729.00 |
16.1 |
| Work Order |
02-22-13 |
| Work Began |
03-14-13 |
| Work Completed |
|
| Time Computed |
03-01-13 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
61 |
| Percent Time Used |
16 |
| Contractor(s) |
| WILLIS ELECTRIC CO., LP |
SUBCONTRACTOR(S) FOR CCSJ: 6250-63-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
01130801 |
|
Totals |
183695.00 |
17119.00 |
29729.00 |
16.1 |
|
| County | TAYLOR |
| Highway |
IH0020 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6250-87-001 |
| Proj ID |
RMC - 625087001 |
| Work Type |
MOWING HIGHWAY RIGHT OF WAY |
| |
|
0.001 |
156080.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
47 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| HJC FARMS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6250-87-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
01130803 |
|
Totals |
156080.00 |
0.00 |
0.00 |
0.0 |
|
| County | HOWARD |
| Highway |
IH0020 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6252-50-001 |
| Proj ID |
SUP - 625250001 |
| Work Type |
LITTER REMOVAL |
| |
|
0.001 |
35614.44 |
5942.20 |
11884.40 |
33.3 |
| Work Order |
12-01-12 |
| Work Began |
12-01-12 |
| Work Completed |
|
| Time Computed |
12-01-12 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
151 |
| Percent Time Used |
41 |
| Contractor(s) |
TIBH INDUSTRIES, INC. BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 6252-50-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11120830 |
|
Totals |
35614.44 |
5942.20 |
11884.40 |
33.3 |
|
| County | TAYLOR |
| Highway |
IH0020 |
| From |
VARIOUS LOCATIONS IN THE ABILENE DIST. |
| To |
VARIOUS LOCATIONS IN THE ABILENE DIST. |
| CSJ |
6254-48-001 |
| Proj ID |
RMC - 625448001 |
| Work Type |
INSTALL RAISED PAVEMENT MARKERS |
| |
|
0.010 |
181243.18 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
42 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| DOUBLE A CONTRACTING, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 6254-48-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04130801 |
|
Totals |
181243.18 |
0.00 |
0.00 |
0.0 |
|