Monthly Local Let Maintenance Report For Abilene District As Of Apr 10, 2017 Page 2 Of 3

Last Update: Monday, April 10, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBORDEN
HighwayFM1054
FromFM 1054 BRIDGE @ COLORADO RIVER
ToFM 1054 BRIDGE @ COLORADO RIVER
CSJ6289-37-001
Proj IDRMC - 628937001
Work TypeROADWAY AND BRIDGE REPAIRS ON FM 1054
 
0.001647009.480.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6289-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07150801
Totals647009.480.000.000.0

CountyTAYLOR
HighwayIH0020
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6295-83-001
Proj IDRMC - 629583001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001287512.00190408.0066.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-26-16
Work Completed
Time Computed00-00-00
Contract Working Days128
Addl Days Granted0
Working Days Charged80
Percent Time Used62
Contractor(s)
GREG SCRUGGS
SUBCONTRACTOR(S) FOR CCSJ: 6295-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01160814
Totals287512.000.00190408.0066.2

CountyCALLAHAN
HighwayUS0283
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6295-85-001
Proj IDSUP - 629585001
Work TypePICNIC AREA MAINTENANCE
 
0.00116112.0018480.0099.9
Work Order12-24-15
Work Began01-01-16
Work Completed
Time Computed01-01-16
Contract Working Days365
Addl Days Granted375
Working Days Charged424
Percent Time Used57
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6295-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11150832
Totals16112.001452.0018480.0099.9

CountyTAYLOR
HighwayUS0277
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6295-86-001
Proj IDSUP - 629586001
Work TypePICNIC AREA MAINTENANCE
 
0.00116592.0018480.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-01-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted375
Working Days Charged455
Percent Time Used61
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6295-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11150833
Totals16592.000.0018480.0099.9

CountyTAYLOR
HighwayUS0083
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6295-95-001
Proj IDSUP - 629595001
Work TypeADDITIONAL LABOR ONSITE ATTENDANT
 
0.00124960.0029904.0099.9
Work Order12-24-15
Work Began01-01-16
Work Completed
Time Computed01-01-16
Contract Working Days365
Addl Days Granted365
Working Days Charged455
Percent Time Used62
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11150831
Totals24960.002160.0029904.0099.9

CountyHOWARD
HighwayMR0686
FromBIG SPRING STATE HOSPITAL
ToBIG SPRING STATE HOSPITAL
CSJ6296-92-001
Proj IDRMC - 629692001
Work TypeDRAINAGE AND DRIVEWAY IMPROVEMENTS
 
0.011105953.180.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days25
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6296-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03160804
Totals105953.180.000.000.0

CountyTAYLOR
HighwayBI0020R
FromVARIOUS LOCATIONS IN TAYLOR, CALLAHAN,
ToSHACKELFORD, JONES & HASKELL COUNTIES
CSJ6297-66-001
Proj IDRMC - 629766001
Work TypeINSTALLATION OF PAVEMENT MARKINGS
 
0.010210984.59256504.9999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-26-16
Work Completed
Time Computed08-26-16
Contract Working Days20
Addl Days Granted0
Working Days Charged11
Percent Time Used55
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6297-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160801
Totals210984.590.00256504.9999.9

CountyTAYLOR
HighwayIH0020
FromIH 20 @
ToUS 883
CSJ6299-15-001
Proj IDRMC - 629915001
Work TypeINSTALL OVERHEAD SIGN STRUCTURE
 
0.010116348.140.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-22-17
Work Began00-00-00
Work Completed
Time Computed06-01-17
Contract Working Days20
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6299-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01170801
Totals116348.140.000.000.0

CountyTAYLOR
HighwayUS0083
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6299-62-001
Proj IDSUP - 629962001
Work TypePREVENTATIVE MAINTENANE
 
0.001121585.0053355.7643.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged180
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6299-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160830
Totals121585.000.0053355.7643.8

CountyTAYLOR
HighwayUS0083
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6301-21-001
Proj IDSUP - 630121001
Work TypeJANITORIAL MAINTENANCE
 
0.00177010.0057693.0074.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged223
Percent Time Used61
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6301-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04160830
Totals77010.000.0057693.0074.9

CountyTAYLOR
HighwayIH0020
FromVARIOUS LOCATIONS IN TAYLOR, CALLAHAN
ToJONES AND SHACKELFORD COUNTIES
CSJ6309-47-001
Proj IDRMC - 630947001
Work TypeCLEAN AND SEAL CRACKS AND JOINTS
 
0.001152961.64133065.0886.9
Work Order01-10-17
Work Began00-00-00
Work Completed
Time Computed02-01-17
Contract Working Days24
Addl Days Granted0
Working Days Charged23
Percent Time Used95
Contractor(s)
ARCC CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6309-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11160801
Totals152961.64114727.08133065.0886.9

CountySCURRY
HighwayUS0180
FromVARIOUS LOCATIONS IN SCURRY, FISHER
ToAND HASKELL COUNTIES
CSJ6309-49-001
Proj IDRMC - 630949001
Work TypeCRACK SEALING
 
0.010172304.00204995.76100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-30-16
Work Began11-30-16
Work Completed10-05-16
Time Computed12-01-16
Contract Working Days31
Addl Days Granted0
Working Days Charged12
Percent Time Used38
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6309-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11160803
Totals172304.000.00204995.76100.0

CountyNOLAN
HighwayIH0020
FromCR 126 @
ToIH 20
CSJ6310-00-001
Proj IDRMC - 631000001
Work TypeCONCRETE BEAM REPAIR
 
0.010273381.5054916.0920.0
Work Order03-20-17
Work Began02-20-17
Work Completed
Time Computed03-27-17
Contract Working Days20
Addl Days Granted0
Working Days Charged1
Percent Time Used5
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6310-00-001
DELTA STRUCTURAL TECHNOLOGY, LLC (22.88)
CONTRACTORS SERVICE COMPANY (6.15)
DOUBLE A CONTRACTING, L.P. (1.94)
Contract #01170802
Totals273381.5054916.0954916.0920.0

CountyBORDEN
HighwayUS0180
FromVARIOUS LOCATIONS
ToIN BORDEN COUNTY
CSJ6310-99-001
Proj IDRMC - 631099001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010133858.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days33
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MIJELUM
SUBCONTRACTOR(S) FOR CCSJ: 6310-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02170801
Totals133858.000.000.000.0

CountyFISHER
HighwayUS0180
FromVARIOUS LOCATIONS
ToIN FISHER COUNTY
CSJ6311-01-001
Proj IDRMC - 631101001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010217377.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days47
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GREG SCRUGGS
SUBCONTRACTOR(S) FOR CCSJ: 6311-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02170803
Totals217377.600.000.000.0

CountyHASKELL
HighwayUS0277
FromVARIOUS LOCATIONS
ToIN HASKELL COUNTY
CSJ6311-02-001
Proj IDRMC - 631102001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010286731.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days76
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FOUR R OILFIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6311-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02170804
Totals286731.000.000.000.0

CountyHOWARD
HighwayIH0020
FromVARIOUS LOCATIONS
ToIN HOWARD COUNTY
CSJ6311-03-001
Proj IDRMC - 631103001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010381168.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days125
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MIJELUM
SUBCONTRACTOR(S) FOR CCSJ: 6311-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02170805
Totals381168.000.000.000.0

CountyKENT
HighwayUS0380
FromVARIOUS LOCATION
ToIN KENT COUNTY
CSJ6311-05-001
Proj IDRMC - 631105001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010102211.650.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days33
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ABESCAPE LANDSCAPING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6311-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02170807
Totals102211.650.000.000.0

CountyMITCHELL
HighwayIH0020
FromVARIOUS LOCATIONS
ToIN MITCHELL COUNTY
CSJ6311-06-001
Proj IDRMC - 631106001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010322278.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days89
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MIJELUM
SUBCONTRACTOR(S) FOR CCSJ: 6311-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02170808
Totals322278.000.000.000.0

CountySCURRY
HighwayUS0084
FromVARIOUS LOCATIONS
ToIN SCURRY COUNTY
CSJ6311-07-001
Proj IDRMC - 631107001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010283758.250.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days85
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KENNETH THOMASON
SUBCONTRACTOR(S) FOR CCSJ: 6311-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02170810
Totals283758.250.000.000.0