Monthly Local Let Maintenance Report For Abilene District As Of Aug 12, 2014 Page 2 Of 2

Last Update: Tuesday, August 12, 2014
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyNOLAN
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6260-61-001
Proj ID SUP - 626061001
Work Type JANITORIAL MAINTENANCE
 
0.001 10205.00 815.00 9390.00 92.0
Work Order 09-01-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 365
Working Days Charged 334
Percent Time Used 45
Contractor(s)
TIBH INDUSTRIES, INC.
WEST TEXAS CENTERS/MHMR
SUBCONTRACTOR(S) FOR CCSJ: 6260-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06130831
Totals 10205.00 815.00 9390.00 92.0

CountyNOLAN
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6260-62-001
Proj ID SUP - 626062001
Work Type PICNIC AREA AND LANDSCAPE MAINTENANCE
 
0.001 17580.00 1671.50 15968.00 90.8
Work Order 09-01-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 365
Working Days Charged 334
Percent Time Used 45
Contractor(s)
TIBH INDUSTRIES, INC.
WEST TEXAS CENTERS/MHMR
SUBCONTRACTOR(S) FOR CCSJ: 6260-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06130832
Totals 17580.00 1671.50 15968.00 90.8

CountySCURRY
Highway US0084
From VARIOUS
To VARIOUS
CSJ 6260-63-001
Proj ID SUP - 626063001
Work Type PICNIC AREA MAINTENANCE
 
0.001 15434.00 1654.00 13644.00 88.4
Work Order 09-01-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 365
Working Days Charged 334
Percent Time Used 45
Contractor(s)
TIBH INDUSTRIES, INC.
WEST TEXAS CENTERS/MHMR
SUBCONTRACTOR(S) FOR CCSJ: 6260-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06130833
Totals 15434.00 1654.00 13644.00 88.4

CountyMITCHELL
Highway IH0020
From VARIOUS LOCATIONS IN MITCHELL COUNTY
To VARIOUS LOCATIONS IN HOWARD COUNTY
CSJ 6262-97-001
Proj ID RMC - 626297001
Work Type PICNIC AREA AND LANDSCAPE MAINTENANCE
 
0.001 27944.00 1332.00 12120.00 43.3
Work Order 11-12-13
Work Began 11-19-13
Work Completed  
Time Computed 11-19-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 255
Percent Time Used 69
Contractor(s)
RAIRE MANAGEMENT SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6262-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10130801
Totals 27944.00 1332.00 12120.00 43.3

CountyTAYLOR
Highway US0083
From VARIOUS
To VARIOUS
CSJ 6263-39-001
Proj ID SUP - 626339001
Work Type ADDITIONAL LABOR ONSITE ATTENDANT
 
0.001 24960.00 2196.00 19416.00 77.7
Work Order 10-01-13
Work Began 10-01-13
Work Completed  
Time Computed 10-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 304
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08130830
Totals 24960.00 2196.00 19416.00 77.7

CountyHOWARD
Highway IH0020
From VARIOUS LOCATIONS
To VARIOUS LOCATIONS
CSJ 6266-20-001
Proj ID SUP - 626620001
Work Type LITTER REMOVAL
 
0.001 48032.16 0.00 30299.55 63.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-25-13
Work Began 12-01-13
Work Completed  
Time Computed 12-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 243
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6266-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10130830
Totals 48032.16 0.00 30299.55 63.0

CountyHOWARD
Highway IH0020
From 1/4 MILE NORTH OF IH 20
To 1/4 MILE SOUTH OF IH 20
CSJ 6267-25-001
Proj ID EMC - 626725001
Work Type BRIDGE REPLACEMENT
 
0.213 2094360.80 25459.25 2073812.10 99.2
Work Order 01-20-14
Work Began 01-20-14
Work Completed  
Time Computed 01-27-14
Contract Working Days 97
Addl Days Granted 0
Working Days Charged 103
Percent Time Used 106
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-25-001
CONTRACTORS SERVICE COMPANY(0.93%)
ATS DRILLING, INC. (7.92%)
HJC FARMS, INC.(5.89%)
MCL CONTRACTING, LLC (0.27%)
Contract # 01140898
Totals 2094360.80 25459.25 2073812.10 99.2

CountyBORDEN
Highway US0180
From VARIOUS LOCATIONS IN BORDEN CO.
To VARIOUS LOCATIONS IN MITCHELL CO.
CSJ 6267-43-001
Proj ID RMC - 626743001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 204213.30 5703.15 5703.15 2.7
Work Order 07-01-14
Work Began 00-00-00
Work Completed  
Time Computed 07-14-14
Contract Working Days 58
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 24
Contractor(s)
GREG SCRUGGS
SUBCONTRACTOR(S) FOR CCSJ: 6267-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01140801
Totals 204213.30 5703.15 5703.15 2.7

CountyHOWARD
Highway IH0020
From VARIOUS LOCATIONS
To VARIOUS LOCATIONS
CSJ 6267-44-001
Proj ID RMC - 626744001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 150590.00 39710.00 75295.00 50.0
Work Order 06-16-14
Work Began 06-23-14
Work Completed  
Time Computed 06-23-14
Contract Working Days 44
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 50
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6267-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01140802
Totals 150590.00 39710.00 75295.00 50.0

CountySHACKELFORD
Highway US0180
From VARIOUS LOCATIONS IN SHACKELFORD CO.
To VARIOUS LOCATIONS IN TAYLOR CO.
CSJ 6267-45-001
Proj ID RMC - 626745001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 184935.44 92231.84 92231.84 49.8
Work Order 00-00-00
Work Began 07-01-14
Work Completed  
Time Computed 07-08-14
Contract Working Days 59
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 30
Contractor(s)
GORMAN OUTDOOR, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01140803
Totals 184935.44 92231.84 92231.84 49.8

CountyCALLAHAN
Highway US0283
From VARIOUS
To VARIOUS
CSJ 6268-61-001
Proj ID SUP - 626861001
Work Type PICNIC AREA MAINTENANCE
 
0.001 16112.00 1600.00 9268.00 57.5
Work Order 12-30-13
Work Began 01-01-14
Work Completed  
Time Computed 01-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6268-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130830
Totals 16112.00 1600.00 9268.00 57.5

CountyTAYLOR
Highway US0277
From VARIOUS
To VARIOUS
CSJ 6268-62-001
Proj ID SUP - 626862001
Work Type PICNIC AREA MAINTENANCE
 
0.001 16592.00 0.00 9388.00 56.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-01-14
Work Began 01-01-14
Work Completed  
Time Computed 01-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6268-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12130831
Totals 16592.00 0.00 9388.00 56.5

CountyCALLAHAN
Highway US0283
From VARIOUS
To VARIOUS
CSJ 6268-87-001
Proj ID SUP - 626887001
Work Type LITTER REMOVAL IN CALLAHAN COUNTY
 
0.001 38873.78 4216.06 19043.05 48.9
Work Order 01-23-14
Work Began 02-01-14
Work Completed  
Time Computed 02-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 181
Percent Time Used 49
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6268-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01140830
Totals 38873.78 4216.06 19043.05 48.9

CountyTAYLOR
Highway US0083
From VARIOUS
To VARIOUS
CSJ 6268-88-001
Proj ID SUP - 626888001
Work Type LITTER REMOVAL
 
0.001 149176.24 0.00 73333.92 49.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-01-14
Work Began 02-13-14
Work Completed  
Time Computed 02-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 181
Percent Time Used 49
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6268-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01140831
Totals 149176.24 0.00 73333.92 49.1

CountyTAYLOR
Highway US0083
From VARIOUS LOCATIONS
To VARIOUS LOCATIONS
CSJ 6271-47-001
Proj ID SUP - 627147001
Work Type JANITORIAL MAINTENANCE
 
0.001 75498.00 5882.00 11764.00 15.5
Work Order 05-23-14
Work Began 06-01-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 16
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6271-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140830
Totals 75498.00 5882.00 11764.00 15.5

CountyHOWARD
Highway IH0020
From HOWARD AND BORDEN
To MITCHELL AND NOLAN COUNTIES
CSJ 6271-83-001
Proj ID RMC - 627183001
Work Type ON CALL MBGF CONTRACT
 
0.001 180609.56 47496.04 47496.04 26.2
Work Order 06-19-14
Work Began 07-09-14
Work Completed  
Time Computed 06-26-14
Contract Working Days 275
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 12
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6271-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05140801
Totals 180609.56 47496.04 47496.04 26.2

CountySCURRY
Highway US0084
From SCURRY AND KENT
To FISHER COUNTIES
CSJ 6271-84-001
Proj ID RMC - 627184001
Work Type ON CALL MBGF CONTRACT
 
0.001 90771.00 18165.00 18165.00 20.0
Work Order 00-00-00
Work Began 07-17-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 275
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 11
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6271-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05140802
Totals 90771.00 18165.00 18165.00 20.0

CountySHACKELFORD
Highway US0283
From VARIOUS LOCATIONS
To VARIOUS LOCATIONS
CSJ 6273-84-001
Proj ID RMC - 627384001
Work Type LANDSCAPE MAINTENANCE
 
0.001 102888.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 152
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06140801
Totals 102888.00 0.00 0.00 0.0

CountySTONEWALL
Highway US0083
From VARIOUS LOCATIONS IN STONEWALL
To VARIOUS LOCATIONS IN FISHER
CSJ 6273-85-001
Proj ID RMC - 627385001
Work Type LANDSCAPE MAINTENANCE
 
0.001 40000.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06140802
Totals 40000.00 0.00 0.00 0.0

CountyNOLAN
Highway BI0020M
From BI 20 @ IH 20
To EAST OF SWEETWATER
CSJ 6277-21-001
Proj ID EMC - 627721001
Work Type EMERGENCY FULL DEPTH BRIDGE DECK REPAIR
 
0.037 72700.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 08-04-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 10
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6277-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07140899
Totals 72700.00 0.00 0.00 0.0