Monthly Local Let Maintenance Report For Abilene District As Of May 15, 2013 Page 1 Of 3

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHOWARD
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6087-99-001
Proj ID RMC - 608799001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.010 90244.48 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-28-10
Work Began 00-00-00
Work Completed  
Time Computed 07-05-10
Contract Working Days 44
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
OPEN RANGE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6087-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11090810
Totals 90244.48 0.00 0.00 0.0

CountyMITCHELL
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6091-68-001
Proj ID RMC - 609168001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.010 74365.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-13-10
Work Began 00-00-00
Work Completed  
Time Computed 07-06-10
Contract Working Days 38
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
OPEN RANGE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6091-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11090813
Totals 74365.20 0.00 0.00 0.0

CountyNOLAN
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6091-70-001
Proj ID RMC - 609170001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.010 75636.88 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-09-10
Work Began 00-00-00
Work Completed  
Time Computed 07-01-10
Contract Working Days 38
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
OPEN RANGE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6091-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11090814
Totals 75636.88 0.00 0.00 0.0

CountyCALLAHAN
Highway FM0018
From VARIOUS AREAS IN CALLAHAN COUNTY
To VARIOUS AREAS IN TAYLOR COUNTY
CSJ 6137-48-001
Proj ID RMC - 613748001
Work Type STREET SWEEPING
 
0.010 94400.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WILLIAM D. KNIGHT
SUBCONTRACTOR(S) FOR CCSJ: 6137-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05060801
Totals 94400.00 0.00 0.00 0.0

CountySTONEWALL
Highway US0380
From VARIOUS LOCATIONS IN STONEWALL,
To KENT AND SCURRY COUNTIES
CSJ 6215-59-001
Proj ID BPM - 621559001
Work Type MISCELLANEOUS BRIDGE WORK
 
0.669 171000.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS ROAD MAINTENANCE
SUBCONTRACTOR(S) FOR CCSJ: 6215-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04130802
Totals 171000.00 0.00 0.00 0.0

CountyCALLAHAN
Highway SH0036
From SH 36
To SH 206
CSJ 6215-60-001
Proj ID RMC - 621560001
Work Type CONCRETE INTERSECTION PAVING
 
0.070 307009.84 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6215-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01130802
Totals 307009.84 0.00 0.00 0.0

CountySHACKELFORD
Highway US0180
From VARIOUS LOCATIONS IN SHACKELFORD CO.
To VARIOUS LOCATIONS IN JONES & TAYLOR CO.
CSJ 6224-12-001
Proj ID RMC - 622412001
Work Type PICNIC AREA AND LANDSCAPE MAINTENANCE
 
0.001 136344.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS MOWING SERVICE
SUBCONTRACTOR(S) FOR CCSJ: 6224-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04110802
Totals 136344.00 0.00 0.00 0.0

CountySHACKELFORD
Highway US0180
From VARIOUS
To VARIOUS
CSJ 6227-26-001
Proj ID SUP - 622726001
Work Type PICNIC AREA & LANDSCAPE MAINTENANCE
 
0.001 96500.16 8475.34 183562.20 99.9
Work Order 06-01-11
Work Began 06-01-11
Work Completed  
Time Computed 06-01-11
Contract Working Days 365
Addl Days Granted 365
Working Days Charged 700
Percent Time Used 95
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6227-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05110830
Totals 96500.16 8475.34 183562.20 99.9

CountyHASKELL
Highway US0277
From VARIOUS LOCATIONS IN HASKELL CO.
To VARIOUS LOCATIONS IN STONEWALL CO.
CSJ 6229-00-001
Proj ID SUP - 622900001
Work Type PICNIC AREA MAINTENANCE
 
0.001 28580.00 2430.00 49660.00 99.9
Work Order 07-21-11
Work Began 08-01-11
Work Completed  
Time Computed 08-01-11
Contract Working Days 365
Addl Days Granted 365
Working Days Charged 639
Percent Time Used 87
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6229-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06110830
Totals 28580.00 2430.00 49660.00 99.9

CountyNOLAN
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6232-19-001
Proj ID SUP - 623219001
Work Type JANITORIAL FACILITY MAINTENANCE
 
0.001 9830.00 785.00 16520.00 99.9
Work Order 09-01-11
Work Began 09-01-11
Work Completed  
Time Computed 09-01-11
Contract Working Days 365
Addl Days Granted 365
Working Days Charged 608
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
WEST TEXAS CENTERS/MHMR
SUBCONTRACTOR(S) FOR CCSJ: 6232-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07110831
Totals 9830.00 785.00 16520.00 99.9

CountySCURRY
Highway US0084
From VARIOUS
To VARIOUS
CSJ 6232-20-001
Proj ID SUP - 623220001
Work Type PICNIC AREA MAINTENANCE
 
0.001 14756.00 1170.00 23108.00 99.9
Work Order 09-01-11
Work Began 09-01-11
Work Completed  
Time Computed 09-01-11
Contract Working Days 365
Addl Days Granted 365
Working Days Charged 608
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
WEST TEXAS CENTERS/MHMR
SUBCONTRACTOR(S) FOR CCSJ: 6232-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07110832
Totals 14756.00 1170.00 23108.00 99.9

CountyNOLAN
Highway SH0070
From VARIOUS
To VARIOUS
CSJ 6232-21-001
Proj ID SUP - 623221001
Work Type PICNIC AREA AND LANDSCAPE MAINTENANCE
 
0.001 16876.00 1626.50 28059.00 99.9
Work Order 09-01-11
Work Began 09-01-11
Work Completed  
Time Computed 09-01-11
Contract Working Days 365
Addl Days Granted 365
Working Days Charged 608
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
WEST TEXAS CENTERS/MHMR
SUBCONTRACTOR(S) FOR CCSJ: 6232-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07110833
Totals 16876.00 1626.50 28059.00 99.9

CountyTAYLOR
Highway US0083
From VARIOUS
To VARIOUS
CSJ 6233-32-001
Proj ID SUP - 623332001
Work Type GROUNDS MAINTENANCE ONSITE ATTENDANT
 
0.001 22880.00 2136.00 35924.00 99.9
Work Order 10-01-11
Work Began 10-01-11
Work Completed  
Time Computed 10-01-11
Contract Working Days 365
Addl Days Granted 365
Working Days Charged 578
Percent Time Used 79
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6233-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08110830
Totals 22880.00 2136.00 35924.00 99.9

CountyHOWARD
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6234-16-001
Proj ID RMC - 623416001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 169756.00 0.00 168576.00 99.9
Work Order 06-25-12
Work Began 07-12-12
Work Completed  
Time Computed 07-02-12
Contract Working Days 44
Addl Days Granted 44
Working Days Charged 44
Percent Time Used 50
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6234-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11110801
Totals 169756.00 0.00 168576.00 99.9

CountyTAYLOR
Highway US0083
From VARIOUS LOCATIONS IN TAYLOR CO.
To VARIOUS LOCATIONS IN TAYLOR CO.
CSJ 6236-94-001
Proj ID RMC - 623694001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
0.001 103950.00 12095.00 36820.00 35.4
Work Order 12-03-12
Work Began 12-03-12
Work Completed  
Time Computed 12-10-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 142
Percent Time Used 38
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6236-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08120801
Totals 103950.00 12095.00 36820.00 35.4

CountyCALLAHAN
Highway US0283
From VARIOUS
To VARIOUS
CSJ 6239-84-001
Proj ID SUP - 623984001
Work Type JANITORIAL BUILDING MAINTENANCE
 
0.001 8410.24 646.52 9056.76 99.9
Work Order 04-01-12
Work Began 04-01-12
Work Completed  
Time Computed 04-01-12
Contract Working Days 365
Addl Days Granted 365
Working Days Charged 395
Percent Time Used 54
Contractor(s)
TIBH INDUSTRIES, INC.
ABILENE STATE SCHOOL VOCATIONAL SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6239-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01120830
Totals 8410.24 646.52 9056.76 99.9

CountyJONES
Highway US0180
From VARIOUS
To VARIOUS
CSJ 6239-85-001
Proj ID SUP - 623985001
Work Type JANITORIAL BUILDING MAINTENANCE
 
0.001 12828.44 1006.37 13834.81 99.9
Work Order 03-26-12
Work Began 04-01-12
Work Completed  
Time Computed 04-01-12
Contract Working Days 365
Addl Days Granted 365
Working Days Charged 395
Percent Time Used 54
Contractor(s)
TIBH INDUSTRIES, INC.
ABILENE STATE SCHOOL VOCATIONAL SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6239-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01120831
Totals 12828.44 1006.37 13834.81 99.9

CountySHACKELFORD
Highway US0283
From VARIOUS
To VARIOUS
CSJ 6239-86-001
Proj ID SUP - 623986001
Work Type JANITORIAL BUILDING MAINTENANCE
 
0.001 5673.44 438.62 6112.06 99.9
Work Order 03-28-12
Work Began 04-01-12
Work Completed  
Time Computed 04-01-12
Contract Working Days 365
Addl Days Granted 365
Working Days Charged 395
Percent Time Used 54
Contractor(s)
TIBH INDUSTRIES, INC.
ABILENE STATE SCHOOL VOCATIONAL SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6239-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01120832
Totals 5673.44 438.62 6112.06 99.9

CountyHOWARD
Highway IH0020
From HOWARD, MITCHELL, NOLAN, BORDEN,
To SCURRY, FISHER, KENT COUNTIES
CSJ 6240-07-001
Proj ID RMC - 624007001
Work Type ON CALL MBGF CONTRACT
 
0.010 290392.00 43682.08 320879.06 99.9
Work Order 05-03-12
Work Began 05-09-12
Work Completed  
Time Computed 05-10-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 350
Percent Time Used 95
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6240-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04120801
Totals 290392.00 43682.08 320879.06 99.9

CountyMITCHELL
Highway IH0020
From VARIOUS LOCATIONS IN MITCHELL COUNTY
To VARIOUS LOCATIONS IN HOWARD COUNTY
CSJ 6241-71-001
Proj ID RMC - 624171001
Work Type PICNIC AREA AND LANDSCAPE MAINTENANCE
 
0.010 17822.00 1530.00 13431.00 75.3
Work Order 07-19-12
Work Began 07-26-12
Work Completed  
Time Computed 07-26-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 279
Percent Time Used 76
Contractor(s)
POWER WASH SOLUTIONS
SUBCONTRACTOR(S) FOR CCSJ: 6241-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05120801
Totals 17822.00 1530.00 13431.00 75.3

page 1 | page 2 | page 3