Monthly State Let Construction Report For Yoakum District As Of Mar 13, 2024 Page 6 Of 8

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMATAGORDA
HighwayFM 521
FromAT TRES PALACIOS RIVER
ToSTR# 0846-03-004
CSJ0846-03-048
Proj IDBR 2B23(084)
Work TypeBRIDGE REPLACEMENT
 
0.2456283882.19137917.622.1
Work Order09-07-23
Work Began00-00-00
Work Completed
Time Computed12-06-23
Contract Working Days205
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0846-03-048
HIGHWAY BARRICADES AND SERVICES, LLC (0.22)
TEX OP CONSTRUCTION, LP (0.15)
A K FUQUAY CONSTRUCTION (0.47)
TRAFFIC SIGNS & LINES, LLC (0.61)
PRIMATE CONSTRUCTION, LP (0.08)
DARKHORSE INDUSTRIES, L.L.C. (0.57)
Contract #08233019
Totals6283882.190.00137917.622.1

CountyDEWITT
HighwayVA
FromVARIOUS LOCATIONS
To.
CSJ0913-00-114
Proj IDF 2021(772)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1652900.001563013.2894.5
Work Order11-16-21
Work Began10-16-23
Work Completed
Time Computed02-14-22
Contract Working Days120
Addl Days Granted0
Working Days Charged47
Percent Time Used39
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-00-114
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08213242
Totals1652900.0039781.201563013.2894.5

CountyDEWITT
HighwayVA
FromDISTRICTWIDE
To.
CSJ0913-00-116
Proj IDF 2024(051)
Work TypeTRAFFIC CONTROL DEVICES
 
1439926.580.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-05-24
Work Began00-00-00
Work Completed
Time Computed05-05-24
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HIGHWAY BARRICADES AND SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-00-116
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09233020
Totals1439926.580.000.000.0

CountyWHARTON
HighwayCR
FromAT BOSQUE SLOUGH CR 645
To(CR 467) STR # AA06-45-001
CSJ0913-09-070
Proj IDBR 2014(680)
Work TypeBRIDGE REPLACEMENT
 
0.062410624.90407985.6899.3
CountyWHARTON
HighwayCR
FromAT GUM TREE BRANCH #1
ToSTR # AA03-17-002 (CR 252)
CSJ0913-09-091
Proj IDBR 1702(589)
Work TypeBRIDGE REPLACEMENT
 
0.072517582.25617000.4799.9
CountyWHARTON
HighwayCR
FromAT MUD CREEK
ToSTR # AA04-25-001 (CR 430)
CSJ0913-09-098
Proj IDBR 1702(593)
Work TypeBRIDGE REPLACEMENT
 
568403.81509621.5189.6
Work Order07-27-20
Work Began11-05-20
Work Completed
Time Computed08-27-20
Contract Working Days210
Addl Days Granted0
Working Days Charged191
Percent Time Used90
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-070
LONESTAR TRAFFIC SAFETY, LLC (0.56)
LONE STAR PAVING COMPANY (3.53)
HEMPHILL WBE PILE DRIVING CO. (7.68)
Contract #06203224
Totals1496610.960.001534607.6699.9

CountyWHARTON ETC
HighwayCR
FromAT DRAW (CR 309)
ToSTR # AA04-53-001
CSJ0913-09-089
Proj IDBR 1702(587)
Work TypeBRIDGE REPLACEMENT
 
0.3663985642.303939511.4098.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-31-20
Work Began07-02-20
Work Completed
Time Computed00-00-00
Contract Working Days352
Addl Days Granted0
Working Days Charged344
Percent Time Used97
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-089
WEBER-BALKE FOUNDATION COMPANY, INC (5.76)
HEMPHILL WBE PILE DRIVING CO. (7.66)
LONE STAR PAVING COMPANY (1.82)
LONESTAR TRAFFIC SAFETY, LLC (0.35)
Contract #02203212
Totals3985642.300.003939511.4098.8

CountyWHARTON
HighwayCR
FromAT WILLOW CREEK
ToSTR # AA04-14-003 (CR 403)
CSJ0913-09-102
Proj IDBR 2020(610)
Work TypeBRIDGE REPLACEMENT
 
0.072466308.45466185.7599.9
CountyWHARTON
HighwayCR
FromAT DRAW
ToSTR # AA04-33-001 (CR 407)
CSJ0913-09-103
Proj IDBR 2020(611)
Work TypeBRIDGE REPLACEMENT
 
0.046282290.22280590.6799.3
CountyWHARTON
HighwayCR
FromAT JONES CREEK
ToSTR # AA06-41-001 (CR 465)
CSJ0913-09-104
Proj IDBR 2020(613)
Work TypeBRIDGE REPLACEMENT
 
0.073495485.16486916.4998.2
Work Order05-14-21
Work Began06-14-21
Work Completed
Time Computed08-12-21
Contract Working Days238
Addl Days Granted0
Working Days Charged138
Percent Time Used57
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-102
A K FUQUAY CONSTRUCTION (1.17)
HEMPHILL WBE PILE DRIVING CO. (8.50)
HIGHWAY BARRICADES AND SERVICES, LLC (5.47)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.20)
SYLVA CONSTRUCTION, LLC (1.79)
TORO BRAVO CONSTRUCTION, LLC (0.40)
PRIMATE CONSTRUCTION, LP (0.63)
Contract #04213009
Totals1244083.830.001233692.9199.1

CountyWHARTON
HighwayCR
FromAT DRAW (CR 448)
ToSTR# 132410AA0142001
CSJ0913-09-106
Proj IDBR 2020(911)
Work TypeBRIDGE REPLACEMENT
 
0.058327485.00308827.3696.1
CountyWHARTON
HighwayCR
FromCOLORADO DRAW (CR 267)
ToSTR# 132410AA0306001
CSJ0913-09-108
Proj IDBR 2020(603)
Work TypeBRIDGE REPLACEMENT
 
0.062631174.00487276.9077.2
Work Order08-25-22
Work Began09-14-22
Work Completed
Time Computed09-24-22
Contract Working Days120
Addl Days Granted0
Working Days Charged114
Percent Time Used95
Contractor(s)
TEXAS STEEL INDUSTRIAL PLACING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-106
WEBER-BALKE FOUNDATION COMPANY, INC (6.23)
HOUSTON SAWING & DRILLING (0.38)
A K FUQUAY CONSTRUCTION (1.16)
Contract #06223026
Totals958659.0053180.25796104.2683.6

CountyWHARTON
HighwayCR
FromAT EAGLE BRANCH
ToSTR# AA03-56-001 (CR 268)
CSJ0913-09-109
Proj IDBR 2020(604)
Work TypeBRIDGE REPLACEMENT
 
0.075540294.75522888.0096.7
CountyWHARTON
HighwayCR
FromW BERNARD CREEK RELIEF
ToSTR# AA03-17-005
CSJ0913-09-110
Proj IDBR 2020(605)
Work TypeBRIDGE REPLACEMENT
 
0.057611359.25601355.0098.3
CountyWHARTON
HighwayCR
FromAT DRAW
ToSTR# AA03-17-006
CSJ0913-09-111
Proj IDBR 2020(606)
Work TypeBRIDGE REPLACEMENT
 
0.064475208.50461571.1097.1
Work Order05-18-22
Work Began07-11-22
Work Completed
Time Computed08-16-22
Contract Working Days184
Addl Days Granted0
Working Days Charged140
Percent Time Used76
Contractor(s)
TEXAS STEEL INDUSTRIAL PLACING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-109
SYLVA CONSTRUCTION, LLC (1.69)
WEBER-BALKE FOUNDATION COMPANY, INC (9.46)
A K FUQUAY CONSTRUCTION (1.15)
Contract #04223019
Totals1626862.500.001585814.1097.4

CountyWHARTON
HighwayVA
FromALONG VARIOUS ROADWAYS FROM E. AHLDAG AV
ToEAST 3RD ST (CITY OF WHARTON)
CSJ0913-09-116
Proj IDSTP 2022(392)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1.620664041.50584707.7088.0
Work Order10-06-22
Work Began03-21-23
Work Completed
Time Computed01-04-23
Contract Working Days120
Addl Days Granted0
Working Days Charged115
Percent Time Used95
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-116
BUYERS BARRICADES HOUSTON, LLC (2.95)
Contract #09223023
Totals664041.500.00584707.7088.0

CountyWHARTON
HighwayCR
FromAT LCRA CANAL
ToSTR #AA01-86-001
CSJ0913-09-117
Proj IDBR 2023(033)
Work TypeBRIDGE REPLACEMENT
 
0.065535853.15511752.2095.5
Work Order09-07-23
Work Began11-14-23
Work Completed
Time Computed10-07-23
Contract Working Days59
Addl Days Granted0
Working Days Charged47
Percent Time Used79
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-117
LONESTAR TRAFFIC SAFETY, LLC (0.69)
Contract #08233059
Totals535853.15102967.40511752.2095.5

CountyDEWITT
HighwayVA
FromUS 183 @ US 77A
ToCLINTON RD
CSJ0913-17-044
Proj IDF 2023(173)
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
151104.00147309.0097.4
Work Order12-21-22
Work Began04-17-23
Work Completed
Time Computed03-21-23
Contract Working Days59
Addl Days Granted0
Working Days Charged50
Percent Time Used84
Contractor(s)
TEXAS ROAD CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-17-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11223023
Totals151104.000.00147309.0097.4

CountyDEWITT
HighwayCR
FromAT DEER CREEK
ToSTR # AA01-40-001 (MUELLER RD)
CSJ0913-17-045
Proj IDBR 2023(204)
Work TypeBRIDGE REPLACEMENT
 
0.074698733.00127566.7418.2
CountyGONZALES
HighwayCR
FromAT SANDIES CREEK(CR 210)
ToSTR AA02-10-001
CSJ0913-22-051
Proj IDBR 2019(253)
Work TypeBRIDGE REPLACEMENT
 
0.130563179.000.000.0
CountyVICTORIA
HighwayCR
FromAT ARENOSA CREEK
ToSTR # AA01-83-001 (BISCHOFF CEM RD)
CSJ0913-27-093
Proj IDBR 2023(208)
Work TypeBRIDGE REPLACEMENT
 
0.070586336.10145550.0024.8
Work Order08-03-23
Work Began12-12-23
Work Completed
Time Computed11-01-23
Contract Working Days225
Addl Days Granted0
Working Days Charged14
Percent Time Used6
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-17-045
JH CONTRACT FIELD SERVICES, LLC (8.15)
SYLVA CONSTRUCTION, LLC (5.44)
Contract #06233440
Totals1848248.10800.00273116.7414.7

CountyDEWITT
HighwayCR
FromAT SANDIES CREEK
ToSTR# AA01-66-001 (WESTOFF-CHEAPSIDE RD)
CSJ0913-17-046
Proj IDBR 2B22(011)
Work TypeBRIDGE REPLACEMENT
 
0.1251578840.250.000.0
CountyLAVACA
HighwayCR
FromAT MUSTANG CREEK
ToSTR # AA03-19-001 (CR 376)
CSJ0913-29-056
Proj IDBR 2023(684)
Work TypeBRIDGE REPLACEMENT
 
0.080673751.560.000.0
CountyLAVACA
HighwayCR
FromAT DRAW
ToSTR# AA02-31-001 (CR 245)
CSJ0913-29-057
Proj IDBR 2020(637)
Work TypeBRIDGE REPLACEMENT
 
0.077658409.090.000.0
CountyLAVACA
HighwayCR
FromKUENHS CREEK
ToSTR# AA01-89-001 (CR 291)
CSJ0913-29-063
Proj IDBR 2023(682)
Work TypeBRIDGE REPLACEMENT
 
0.078737032.120.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-02-24
Work Began00-00-00
Work Completed
Time Computed05-02-24
Contract Working Days360
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ACME BRIDGE COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-17-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01243224
Totals3648033.020.000.000.0

CountyJACKSON
HighwayCR
FromHICKS RD
ToAT LUNIS CREEK(STR# AA02-22-001)
CSJ0913-18-036
Proj IDBR 2021(255)
Work TypeBRIDGE REPLACEMENT
 
0.100491804.90499097.8699.9
CountyCALHOUN
HighwayCR
FromAT DRAW
ToSTR # AA01-33-001_(COLOMA RD)
CSJ0913-19-035
Proj IDBR 2018(331)
Work TypeBRIDGE REPLACEMENT
 
0.010316013.34314804.3499.6
CountyVICTORIA
HighwayCR
FromAT DRAW
ToSTR#AA02-85-001 (BLACK BAYOU RD #2)
CSJ0913-27-082
Proj IDBR 2B20(017)
Work TypeBRIDGE REPLACEMENT
 
0.010475226.50463184.0797.4
Work Order08-25-21
Work Began03-09-22
Work Completed
Time Computed11-23-21
Contract Working Days180
Addl Days Granted0
Working Days Charged169
Percent Time Used93
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-18-036
LONESTAR TRAFFIC SAFETY, LLC (0.57)
HEMPHILL WBE PILE DRIVING CO. (7.56)
SYLVA CONSTRUCTION, LLC (1.21)
Contract #07213233
Totals1283044.740.001277086.2799.5

CountyAUSTIN
HighwayCR
FromAT CANEY CREEK (130080AA0307001)
ToREESE ROAD (AA5074)
CSJ0913-20-089
Proj IDBR 2018(205)
Work TypeBRIDGE REPLACEMENT
 
0.080349533.50366175.1699.9
CountyAUSTIN
HighwayCR
FromAT IVES CREEK (130080AA0330002)
ToEAST EUCKERT RD (AA5049)
CSJ0913-20-091
Proj IDBR 2018(206)
Work TypeBRIDGE REPLACEMENT
 
0.080376385.40369133.4098.0
Work Order12-06-19
Work Began03-16-20
Work Completed
Time Computed03-05-20
Contract Working Days151
Addl Days Granted0
Working Days Charged121
Percent Time Used80
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-20-089
LONESTAR TRAFFIC SAFETY, LLC (0.81)
HEMPHILL WBE PILE DRIVING CO. (9.62)
Contract #11193010
Totals725918.900.00735308.5699.9

CountyAUSTIN
HighwayCR
FromAT MILL CREEK
ToSTR # AA03-66-003 (MILL CREEK RD)
CSJ0913-20-092
Proj IDBR 1802(834)
Work TypeBRIDGE REPLACEMENT
 
0.2003089325.200.000.0
CountyAUSTIN
HighwayCR
FromAT SANDY CREEK
ToSTR# AA03-66-007 (MILL CREEK RD)
CSJ0913-20-100
Proj IDBR 2B22(004)
Work TypeBRIDGE REPLACEMENT
 
0.072942595.300.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days221
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-20-092
A K FUQUAY CONSTRUCTION (0.39)
CEN-TREE SOLUTIONS LLC (0.68)
SUPERIOR TRAFFIC CONTROL, LLC (0.17)
Contract #02243045
Totals4031920.500.000.000.0

CountyAUSTIN
HighwayCR
FromAT DRAW
ToSTR# AA03-13-002 (KIEMSTEADT RD)
CSJ0913-20-093
Proj IDBR 2020(686)
Work TypeBRIDGE REPLACEMENT
 
0.100429070.67428968.5499.9
CountyAUSTIN
HighwayCR
FromAT DRAW
ToSTR# AA03-26-002 (NELIUS RD)
CSJ0913-20-095
Proj IDBR 2020(684)
Work TypeBRIDGE REPLACEMENT
 
0.100372220.92368507.3899.0
CountyAUSTIN
HighwayCR
FromAT DRAW
ToSTR# AA50-85-001 (WOODLEY RD)
CSJ0913-20-096
Proj IDBR 2020(683)
Work TypeBRIDGE REPLACEMENT
 
0.100456952.25453771.2799.3
Work Order06-16-22
Work Began01-17-23
Work Completed
Time Computed07-16-22
Contract Working Days172
Addl Days Granted0
Working Days Charged156
Percent Time Used90
Contractor(s)
FUQUA CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-20-093
AREA WIDE PROTECTIVE, INC. (0.51)
TRAFFIC SIGNS & LINES, LLC (4.57)
HEMPHILL WBE PILE DRIVING CO. (8.99)
RAY"S CRANE SERVICE (0.54)
CEN TEX HYDROSEED, INC. (1.82)
Contract #05223227
Totals1258243.8410370.721251247.1999.4

CountyAUSTIN
HighwayCR
FromAT DRAW
ToSTR# AA01-26-001 (CHEW RD)
CSJ0913-20-098
Proj IDBR 2023(134)
Work TypeBRIDGE REPLACEMENT
 
0.078814014.050.000.0
CountyCOLORADO
HighwayCR
FromAT WEST SANDY CREEK
ToSTR # AA02-22-001 (CR 221)
CSJ0913-26-064
Proj IDBR 2020(608)
Work TypeBRIDGE REPLACEMENT
 
0.066731034.600.000.0
CountyCOLORADO
HighwayCR
FromBUCKSNAG CREEK
ToSTR# AA02-83-001 (CR 112)
CSJ0913-26-066
Proj IDBR 2022(961)
Work TypeBRIDGE REPLACEMENT
 
0.0701207158.070.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days225
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-20-098
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243223
Totals2752206.720.000.000.0

CountyGONZALES
HighwayCR
FromAT SAN MARCOS RIVER CR 232
To#AA0232002
CSJ0913-22-016
Proj IDBR 2000(666)
Work TypeBRIDGE REPLACEMENT
 
0.1361278588.55212167.4316.5
Work Order05-17-23
Work Began12-18-23
Work Completed
Time Computed08-15-23
Contract Working Days165
Addl Days Granted0
Working Days Charged16
Percent Time Used9
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-22-016
EGGEMEYER LAND CLEARING, LLC (2.42)
LONE STAR EROSION CONTROL (4.05)
PENHALL COMPANY (0.37)
SYLVA CONSTRUCTION, LLC (2.70)
TEXAS SHAFTS, INC. (10.51)
TORO BRAVO CONSTRUCTION, LLC (1.53)
ZENITH SITE SERVICES (5.54)
J. R. (JOE) RAMON & SONS, INC. (4.24)
Contract #04233031
Totals1278588.55109554.33212167.4316.5

CountyGONZALES
HighwayCR
FromAT TINSLEY CREEK
ToSTR # AA03-84-001(CR 384)
CSJ0913-22-052
Proj IDBR 2020(609)
Work TypeBRIDGE REPLACEMENT
 
0.069417151.82149908.7599.9
CountyGONZALES
HighwayCR
FromAT DRAW
ToSTR # AA04-47-002 (CR 447)
CSJ0913-22-054
Proj IDBR 2020(919)
Work TypeBRIDGE REPLACEMENT
 
0.063194646.35169175.7286.9
CountyLAVACA
HighwayCR
FromAT MUSTANG CREEK
ToSTR # AA02-99-001 (CR 310)
CSJ0913-29-055
Proj IDBR 2020(920)
Work TypeBRIDGE REPLACEMENT
 
0.076437286.80416415.2695.2
Work Order05-27-21
Work Began02-23-22
Work Completed
Time Computed08-25-21
Contract Working Days185
Addl Days Granted0
Working Days Charged283
Percent Time Used152
Contractor(s)
SEFBO PIPELINE BRIDGE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0913-22-052
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.24)
J. R. (JOE) RAMON & SONS, INC. (3.00)
SYLVA CONSTRUCTION, LLC (5.71)
HEMPHILL WBE PILE DRIVING CO. (4.79)
ODUM SERVICES, LLC (0.68)
Contract #04213220
Totals1049084.970.00735499.7396.0