Monthly State Let Construction Report For Yoakum District As Of Feb 09, 2018 Page 6 Of 6

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyFAYETTE
HighwayFM 1115
From0.8 MI W OF FM 2762
ToGONZALES C/L
CSJ1262-01-014
Proj IDSTP 1602(482)
Work TypeRESTORE ROADWAY
 
5.6143558330.173334658.1393.7
Work Order10-05-16
Work Began12-28-16
Work Completed
Time Computed01-04-17
Contract Working Days150
Addl Days Granted0
Working Days Charged150
Percent Time Used100
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1262-01-014
EGGEMEYER LAND CLEARING, LLC (1.52)
FLASHER EQUIPMENT COMPANY (0.23)
LONE STAR EROSION CONTROL (1.52)
MURRAY CONSTRUCTION (0.50)
RELMCO, INC. (18.95)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.48)
ROADWAY SPECIALTIES, INC. (2.72)
NEWMAN & KENG PAVING COMPANY, INC. (2.67)
Contract #08163224
Totals3558330.171596.003334658.1393.7

CountyAUSTIN
HighwayFM 1457
FromFAYETTE C/L
ToSH 159
CSJ1411-02-011
Proj IDSTP 1702(489)
Work TypeRESTORE ROADWAY
 
5.8534469341.79345401.867.7
Work Order08-08-17
Work Began11-20-17
Work Completed
Time Computed11-06-17
Contract Working Days150
Addl Days Granted0
Working Days Charged16
Percent Time Used10
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1411-02-011
ROADWAY SPECIALTIES, INC. (4.36)
AREA WIDE PROTECTIVE, INC. (0.25)
J & M CONTRACTING COMPANY (17.81)
D.I.J. CONSTRUCTION, INC (1.85)
Contract #07173021
Totals4469341.7991401.86345401.867.7

CountyFAYETTE
HighwayFM 1457
FromAT ROCKY CREEK
ToSTR # 1441-01-001
CSJ1441-01-012
Proj IDBR 2016(062)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.2041089950.261173753.9099.9
Work Order11-16-15
Work Began01-14-16
Work Completed
Time Computed12-16-15
Contract Working Days120
Addl Days Granted0
Working Days Charged106
Percent Time Used88
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 1441-01-012
JJ KOONS, LLC. (17.29)
RICE ENVIRONMENTAL SERVICES (5.36)
N-LINE TRAFFIC MAINTENANCE, L.P. (9.62)
BEAIRD DRILLING (2.11)
LONE STAR PAVING (10.85)
ENVIRONMENTAL SAFETY SERVICES, INC. (8.10)
Contract #09153210
Totals1089950.261525.001173753.9099.9

CountyAUSTIN
HighwayFM 1094
From7.2 MI WEST OF SH 36(SCHLUENS RD)
To0.4 MI WEST OF SH 36(HOWARD ST)
CSJ1721-02-012
Proj IDSTP 1502(478)HES
Work TypeSAFETY TREAT FIXED OBJECTS,WIDEN SH
 
6.7493954433.253844565.0397.3
Work Order01-29-16
Work Began03-23-16
Work Completed
Time Computed05-29-16
Contract Working Days150
Addl Days Granted0
Working Days Charged155
Percent Time Used103
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1721-02-012
CEN TEX HYDROSEED, INC. (2.77)
J & M CONTRACTING, COMPANY (11.03)
D.I.J. CONSTRUCTION, INC (3.33)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.27)
ANGEL BROTHERS ENTERPRISES, LTD. (5.54)
Contract #11153009
Totals3954433.250.003844565.0397.3

CountyDEWITT
HighwayFM 966
FromAT DRAW
ToSTR # 130620216602001
CSJ2166-02-007
Proj IDBR 2018(509)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.064338050.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DALRYMPLE GRAVEL AND CONTRACTING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2166-02-007
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183019
Totals338050.000.000.000.0

CountyVICTORIA
HighwayUS 77
From0.52 MI. EAST OF FM 1685
To1.04 MI. WEST OF US 87
CSJ2350-01-041
Proj IDC 2350-1-41
Work TypeCONSTRUCTING TWO ADDITIONAL LANES
 
2.49321361349.8219866919.7593.0
Work Order11-24-15
Work Began01-18-16
Work Completed
Time Computed12-24-15
Contract Working Days450
Addl Days Granted0
Working Days Charged409
Percent Time Used90
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2350-01-041
CAT SKINNER, LLC. (0.78)
ROADWAY SPECIALTIES, INC. (1.33)
FLASHER EQUIPMENT COMPANY (0.48)
MCL CONTRACTING, LLC (0.50)
W. W. FOUNDATION DRILLING, LTD. (3.01)
WEBBER, LLC (12.42)
THE LEVY COMPANY, L.P. (0.23)
PRIMATE CONSTRUCTION, INC. (0.19)
ANDERSON COLUMBIA CO., INC. (22.71)
VALCO CONSTRUCTION (0.22)
PRIMATE CONSTRUCTION, INC. (0.05)
AARON CONCRETE CONTRACTORS, L.P. (0.62)
W. W. FOUNDATION DRILLING, LTD. (2.01)
SCOTT DERR PAINTING CO (0.02)
CERTIFIED PLACERS LLC (0.08)
MCL CONTRACTING, LLC (0.22)
CPAVE, INC. (0.19)
Contract #09153036
Totals21361349.82373512.3819866919.7593.0

CountyVICTORIA
HighwaySL 463
FromMOCKINGBIRD_LANE
ToBU 59T
CSJ2350-01-054
Proj IDNH 1702(188)
Work TypeCONSTRUCT FRONTAGE ROAD
 
2.0904467052.11292824.116.5
Work Order09-08-17
Work Began12-13-17
Work Completed
Time Computed12-07-17
Contract Working Days165
Addl Days Granted0
Working Days Charged11
Percent Time Used6
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2350-01-054
THE LEVY COMPANY, L.P. (2.47)
FLASHER EQUIPMENT COMPANY (1.09)
ROADWAY SPECIALTIES, INC. (1.05)
MURRAY CONSTRUCTION (0.33)
Contract #08173223
Totals4467052.11280546.65292824.116.5

CountyVICTORIA
HighwayUS 77
FromUS 77(FRONTAGE RD) AT MALLETTE DR
To.
CSJ2350-01-059
Proj IDNH 2018(567)
Work TypeCONSTRUCT TRAFFIC SIGNAL
 
0.010335632.920.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days49
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 2350-01-059
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183229
Totals335632.920.000.000.0

CountyMATAGORDA
HighwayFM 2668
FromFM 3057
ToFM 521
CSJ2697-01-034
Proj IDSTP 2017(975)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
10.4983844068.360.000.0
Work Order06-26-17
Work Began00-00-00
Work Completed
Time Computed09-24-17
Contract Working Days165
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2697-01-034
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173022
Totals3844068.360.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6