Monthly State Let Construction Report For San Antonio District As Of Feb 09, 2018 Page 5 Of 6

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN BEXAR COUNTY
To.
CSJ0915-00-178
Proj IDSTP 1702(555)
Work TypeCONSTRUCT CURB RAMPS
 
0.0013495290.12411449.4611.7
Work Order08-16-17
Work Began00-00-00
Work Completed
Time Computed09-06-17
Contract Working Days335
Addl Days Granted0
Working Days Charged63
Percent Time Used18
Contractor(s)
F. D. CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-178
F & W ELECTRICAL CONTRACTORS, INC. (5.94)
SHORT-LINE CORPORATION (2.71)
Contract #07173237
Totals3495290.1286822.92411449.4611.7

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2017
To.
CSJ0915-00-180
Proj IDSTP 2017(565)
Work TypeDISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.0011383517.97477005.0234.4
Work Order03-10-17
Work Began00-00-00
Work Completed
Time Computed04-09-17
Contract Working Days315
Addl Days Granted0
Working Days Charged53
Percent Time Used16
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-180
M & M STRIPING & POWER WASHING, LLC (1.37)
FLASHER EQUIPMENT COMPANY (0.89)
HEARN CO. (6.75)
Contract #02173213
Totals1383517.9737844.50477005.0234.4

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2018
To.
CSJ0915-00-181
Proj IDSTP 2018(318)
Work TypeDISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.0011424651.880.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days320
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-181
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183215
Totals1424651.880.000.000.0

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0915-00-186
Proj IDSTP 1702(556)
Work TypeTRAFFIC SIGNAL REHAB/UPGRADE
 
0.0012664496.9017041.500.6
Work Order08-11-17
Work Began00-00-00
Work Completed
Time Computed09-10-17
Contract Working Days319
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-186
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173035
Totals2664496.900.0017041.500.6

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2017
To.
CSJ0915-00-204
Proj IDSTP 2017(894)
Work TypeDISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.0011349187.00722801.4553.5
Work Order05-09-17
Work Began07-18-17
Work Completed
Time Computed07-03-17
Contract Working Days320
Addl Days Granted0
Working Days Charged112
Percent Time Used35
Contractor(s)
D&G ENERGY CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-204
L & R FOUNDATION DRILLING, INC. (1.03)
M & M STRIPING & POWER WASHING, LLC (4.15)
MINTCO GROUP LLC (1.60)
Contract #04173003
Totals1349187.0066283.00722801.4553.5

CountyKENDALL
HighwayCS
FromSEVENTH ST AT CYPRESS CREEK
To.
CSJ0915-11-028
Proj IDBR 1102(443)
Work TypeREHABILITATE BRIDGE AND APPROACHES
 
0.067514522.7068844.0513.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-13-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days86
Addl Days Granted0
Working Days Charged6
Percent Time Used6
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0915-11-028
BEAIRD DRILLING (11.56)
ENVIRONMENTAL SAFETY SERVICES, INC. (3.32)
BOWMAN ENGINEERING & CONSTRUCTION, INC. (2.89)
FLASHER EQUIPMENT COMPANY (0.97)
HOUSTON SAWING & DRILLING (0.54)
GEOSOURCE, INC. (0.40)
Contract #10173226
Totals514522.7068844.0568844.0513.3

CountyKENDALL
HighwayCR
FromMILL DAM ROAD, 0.6 MI S OF SH 27
ToAT GUADALUPE RIVER
CSJ0915-11-031
Proj IDBR 1602(228)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1581522927.911511534.4499.2
Work Order03-02-17
Work Began03-16-17
Work Completed
Time Computed02-04-17
Contract Working Days268
Addl Days Granted0
Working Days Charged180
Percent Time Used67
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0915-11-031
W. W. FOUNDATION DRILLING, LTD. (8.05)
(USE 07366)J.R. RAMON & SONS, INC (6.73)
ENVIRONMENTAL SAFETY SERVICES, INC. (5.52)
AUSTIN WOOD RECYCLING (2.40)
LONE STAR PAVING (1.33)
FLASHER EQUIPMENT COMPANY (0.94)
FUQUAY, INC. (0.70)
PENHALL COMPANY (0.41)
Contract #01173209
Totals1522927.91600.001511534.4499.2

CountyBEXAR
HighwayCS
FromMILLER RD AT MARTINEZ CREEK
To.
CSJ0915-12-533
Proj IDBR 2014(912)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.102882311.770.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days237
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-533
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183208
Totals882311.770.000.000.0

CountyBEXAR
HighwayVA
FromVARIOUS BRIDGES IN BEXAR COUNY
To.
CSJ0915-12-551
Proj IDBR 1502(471)
Work TypeUPGRADE BRIDGE AND APPROACH RAILING
 
0.0011723801.411947939.6199.9
Work Order12-08-15
Work Began02-22-16
Work Completed
Time Computed02-06-16
Contract Working Days221
Addl Days Granted26
Working Days Charged250
Percent Time Used101
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-551
RICE ENVIRONMENTAL SERVICES (3.67)
FLASHER EQUIPMENT COMPANY (3.58)
RAMMING PAVING COMPANY (22.61)
CHEROKEE SERVICES (4.59)
Contract #10153005
Totals1723801.410.001947939.6199.9

CountyBEXAR
HighwayVA
FromIN SAN ANTONIO ON US 281, LOOP 345
ToFM 78 AND FM 1516 CORRIDORS
CSJ0915-12-555
Proj IDSTP 2016(870)TP
Work TypeGRD, BSE, SIDEWALKS, SIGN, PAVT MRK
 
0.0011771321.261451400.3381.9
CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN BEXAR COUNTY
To.
CSJ0915-12-559
Proj IDSTP 1602(380)
Work TypeSIDEWALK
 
0.0013515369.102520921.3471.7
Work Order10-06-16
Work Began11-10-16
Work Completed
Time Computed11-05-16
Contract Working Days309
Addl Days Granted0
Working Days Charged274
Percent Time Used88
Contractor(s)
J3 COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-555
ROADWAY SPECIALTIES, INC. (2.66)
AUSTIN MATERIALS, LLC (1.91)
JARCO TRANSPORT, LLC (1.76)
LONE STAR EROSION CONTROL (4.43)
SAECO ELECTRIC & UTILITY, LTD. (0.20)
WEBB & BEXAR CONSTRUCTION, LLC. (8.59)
M & M STRIPING & POWER WASHING, LLC (0.11)
FLASHER EQUIPMENT COMPANY (0.36)
C & C ALCOSER TRUCKING (1.04)
Contract #08163211
Totals5286690.36354886.053972321.6775.1

CountyBEXAR
HighwayCS
FromON INGRAM RD
ToAT RICHLAND HILLS
CSJ0915-12-570
Proj IDSTP 1702(042)HES
Work TypeINSTALL TRAFFIC SIGNAL
 
0.200188897.500.000.0
CountyBEXAR
HighwayFM 1976
FromAT MIDCROWN
To.
CSJ1890-01-048
Proj IDSTP 1702(043)HES
Work TypeTRAFFIC SIGNALS & ILLUMINATION
 
0.200217051.5057744.0026.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-17
Work Began00-00-00
Work Completed
Time Computed07-14-17
Contract Working Days100
Addl Days Granted0
Working Days Charged12
Percent Time Used12
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-570
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173209
Totals405949.000.0057744.0014.2

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN BEXAR COUNTY
To.
CSJ0915-12-591
Proj IDNH 1702(678)
Work TypeLANDSCAPE DEVELOPMENT
 
0.001510193.0033500.006.5
Work Order09-14-17
Work Began00-00-00
Work Completed
Time Computed10-14-17
Contract Working Days95
Addl Days Granted0
Working Days Charged17
Percent Time Used17
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-591
FLASHER EQUIPMENT COMPANY (2.92)
Contract #08173010
Totals510193.0033500.0033500.006.5

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN BEXAR COUNTY
To.
CSJ0915-12-592
Proj IDNH 1702(679)
Work TypeLANDSCAPE DEVELOPMENT
 
0.001682419.00107750.0015.7
Work Order09-14-17
Work Began00-00-00
Work Completed
Time Computed10-14-17
Contract Working Days82
Addl Days Granted0
Working Days Charged10
Percent Time Used12
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-592
FLASHER EQUIPMENT COMPANY (3.12)
Contract #08173230
Totals682419.00107750.00107750.0015.7

CountyWILSON
HighwayCR
FromCR 348 AT DRY HOLLOW CREEK
To.
CSJ0915-14-031
Proj IDBR 1702(781)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.067315294.890.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days86
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-14-031
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183231
Totals315294.890.000.000.0

CountyMEDINA
HighwayCR
From4.1 MI SW OF FM 471
To.
CSJ0915-45-052
Proj IDBR 1502(643)
Work TypeREPLACE BRIDGE & APPROACHES
 
0.001422407.38160066.8537.8
Work Order08-23-17
Work Began00-00-00
Work Completed
Time Computed09-22-17
Contract Working Days64
Addl Days Granted0
Working Days Charged48
Percent Time Used75
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-45-052
BEAIRD DRILLING (6.07)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (0.70)
AZA BARRICADES (0.66)
ROADWAY SPECIALTIES, INC. (6.86)
Contract #07173238
Totals422407.3860643.00160066.8537.8

CountyKENDALL
HighwayRM 474
FromFM 473
ToKEMMER TRAIL
CSJ1042-01-032
Proj IDSTP 2013(720)
Work TypeGRAD, BSE, SURF, PAVMT MARKINGS
 
6.6734456842.62951461.2121.3
Work Order07-20-17
Work Began00-00-00
Work Completed
Time Computed08-19-17
Contract Working Days261
Addl Days Granted0
Working Days Charged89
Percent Time Used34
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1042-01-032
RELMCO, INC. (23.70)
GEOSOURCE, INC. (3.41)
D.I.J. CONSTRUCTION, INC (2.59)
FLASHER EQUIPMENT COMPANY (1.89)
LONE STAR EROSION CONTROL (1.58)
Contract #06173027
Totals4456842.62105168.51951461.2121.3

CountyMEDINA
HighwayPR 37
FromSH 16
ToBANDERA C/L
CSJ1066-02-017
Proj IDSTP 2018(078)HESG
Work TypeGRAD, SURF, BASE, PAVEMENT MARKINGS
 
4.2861099115.2578105.407.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-16-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days153
Addl Days Granted0
Working Days Charged22
Percent Time Used14
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1066-02-017
ENVIRONMENTAL SAFETY SERVICES, INC. (18.67)
FLASHER EQUIPMENT COMPANY (6.51)
GEOSOURCE, INC. (6.46)
ROADWAY SPECIALTIES, INC. (5.55)
THE LEVY COMPANY, INC. (4.73)
Contract #09173010
Totals1099115.2514624.1078105.407.1

CountyBEXAR
HighwayFM 1516
FromFM 78
ToFM 1976
CSJ1477-01-040
Proj IDSTP 2017(798)MM
Work TypeGRD, BSE, STR, SURF, PAV'T MRK
 
0.7625733862.95758821.3613.2
CountyBEXAR
HighwayFM 1516
FromFM 78
ToFM 1976
CSJ1477-01-041
Proj IDSTP 1502(217)
Work TypeACQUISITION, RELOCATION ASSISTANCE
 
0.7621655042.65718163.7243.3
Work Order06-26-17
Work Began00-00-00
Work Completed
Time Computed07-28-17
Contract Working Days586
Addl Days Granted0
Working Days Charged52
Percent Time Used8
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1477-01-040
DU-MOR ENTERPRISES_INC. (0.39)
FUQUAY, INC. (0.58)
AUSTIN WOOD RECYCLING (0.17)
LONE STAR PAVING (13.50)
E-Z BEL CONSTRUCTION, LLC (5.71)
FLASHER EQUIPMENT COMPANY (1.44)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.15)
ROADWAY SPECIALTIES, INC. (0.71)
Contract #03173203
Totals7388905.60777420.711476985.0819.9

CountyCOMAL
HighwayFM 306
FromHOFFMANN LANE
To0.5 MI NORTH OF HUNTER ROAD
CSJ1728-02-058
Proj IDSTP 1502(615)MM
Work TypeGRAD, STR, BASE, SURF
 
3.2327936418.828309246.4299.9
Work Order10-21-15
Work Began12-01-15
Work Completed
Time Computed01-19-16
Contract Working Days364
Addl Days Granted0
Working Days Charged421
Percent Time Used115
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1728-02-058
E-Z BEL CONSTRUCTION, LLC (2.34)
CATO ELECTRIC COMPANY (0.00)
HEARN CO. (0.19)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.64)
FLASHER EQUIPMENT COMPANY (0.27)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.41)
R K STEPHENS CONSTRUCTION, LLC (5.07)
TRP CONSTRUCTION GROUP, LLC (1.39)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (3.04)
AUSTIN WOOD RECYCLING (0.61)
SCOTT DERR PAINTING CO, LLC (0.06)
Contract #08153016
Totals7936418.8227.008309246.4299.9

CountyCOMAL
HighwayFM 306
FromRIVER CHASE WAY
ToHOFFMANN LANE
CSJ1728-02-059
Proj IDSTP 1602(300)MM
Work TypeGRAD, STR, BASE, SURF
 
1.3275996508.484654199.3377.6
Work Order09-06-16
Work Began10-06-16
Work Completed
Time Computed10-06-16
Contract Working Days364
Addl Days Granted0
Working Days Charged258
Percent Time Used70
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1728-02-059
OSCAR ORDUNO, INC. (10.30)
SOUTH TEXAS PAINTING COMPANY (0.32)
F & W ELECTRICAL CONTRACTORS, INC. (3.51)
FLASHER EQUIPMENT COMPANY (1.00)
ENVIRONMENTAL SAFETY SERVICES, INC. (7.37)
EGGEMEYER LAND CLEARING, LLC (0.55)
TEXAS LANDSCAPE & IRRIGATION (1.03)
FUQUAY, INC. (1.39)
GK CONSTRUCTION, LLC (0.19)
CENTURY ASPHALT MATERIALS (0.39)
Contract #07163211
Totals5996508.48382035.204654199.3377.6

page 1 | page 2 | page 3 | page 4 | page 5 | page 6