Monthly State Let Construction Report For San Antonio District As Of Nov 22, 2017 Page 5 Of 6

Last Update: Wednesday, November 22, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBEXAR
HighwayVA
FromDISTRICTWIDE GUIDESIGNS FY16
To.
CSJ0915-00-159
Proj IDSTP 2016(902)
Work TypeDISTRICTWIDE GUIDESIGNS FY16
 
0.0012452827.792486567.1599.9
Work Order06-03-16
Work Began11-07-16
Work Completed
Time Computed07-03-16
Contract Working Days360
Addl Days Granted0
Working Days Charged227
Percent Time Used63
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-159
FLASHER EQUIPMENT COMPANY (1.14)
ENVIRONMENTAL SAFETY SERVICES, INC. (8.75)
JCD CONSTRUCTION, LLC (0.11)
AMERICAN TRAFFIC CONTROL (15.49)
Contract #04163232
Totals2452827.79181920.302486567.1599.9

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2016
To.
CSJ0915-00-166
Proj IDSTP 2016(669)
Work TypeDISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.0011355867.971069266.5578.8
Work Order03-28-16
Work Began06-09-16
Work Completed
Time Computed04-27-16
Contract Working Days320
Addl Days Granted0
Working Days Charged223
Percent Time Used69
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-166
FLASHER EQUIPMENT COMPANY (2.31)
HEARN CO. (6.88)
Contract #02163034
Totals1355867.971344.801069266.5578.8

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN BEXAR COUNTY
To.
CSJ0915-00-178
Proj IDSTP 1702(555)
Work TypeCONSTRUCT CURB RAMPS
 
0.0013495290.12111426.533.1
Work Order08-16-17
Work Began00-00-00
Work Completed
Time Computed09-06-17
Contract Working Days335
Addl Days Granted0
Working Days Charged19
Percent Time Used5
Contractor(s)
F. D. CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-178
F & W ELECTRICAL CONTRACTORS, INC. (5.94)
SHORT-LINE CORPORATION (2.71)
Contract #07173237
Totals3495290.1272576.53111426.533.1

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2017
To.
CSJ0915-00-180
Proj IDSTP 2017(565)
Work TypeDISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.0011383517.97269995.8419.5
Work Order03-10-17
Work Began00-00-00
Work Completed
Time Computed04-09-17
Contract Working Days315
Addl Days Granted0
Working Days Charged26
Percent Time Used8
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-180
M & M STRIPING & POWER WASHING, LLC (1.37)
FLASHER EQUIPMENT COMPANY (0.89)
Contract #02173213
Totals1383517.97158171.50269995.8419.5

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0915-00-186
Proj IDSTP 1702(556)
Work TypeTRAFFIC SIGNAL REHAB/UPGRADE
 
0.0012664496.900.000.0
Work Order08-11-17
Work Began00-00-00
Work Completed
Time Computed09-10-17
Contract Working Days319
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-186
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173035
Totals2664496.900.000.000.0

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2017
To.
CSJ0915-00-204
Proj IDSTP 2017(894)
Work TypeDISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.0011349187.00522791.6038.7
Work Order05-09-17
Work Began07-18-17
Work Completed
Time Computed07-03-17
Contract Working Days320
Addl Days Granted0
Working Days Charged67
Percent Time Used20
Contractor(s)
D&G ENERGY CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-204
L & R FOUNDATION DRILLING, INC. (1.03)
M & M STRIPING & POWER WASHING, LLC (4.15)
MINTCO GROUP LLC (1.60)
Contract #04173003
Totals1349187.00215131.50522791.6038.7

CountyKENDALL
HighwayCS
FromSEVENTH ST AT CYPRESS CREEK
To.
CSJ0915-11-028
Proj IDBR 1102(443)
Work TypeREHABILITATE BRIDGE AND APPROACHES
 
0.067514522.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-13-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days86
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0915-11-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10173226
Totals514522.700.000.000.0

CountyKENDALL
HighwayCR
FromMILL DAM ROAD, 0.6 MI S OF SH 27
ToAT GUADALUPE RIVER
CSJ0915-11-031
Proj IDBR 1602(228)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1581522927.911507936.3499.0
Work Order03-02-17
Work Began03-16-17
Work Completed
Time Computed02-04-17
Contract Working Days268
Addl Days Granted0
Working Days Charged180
Percent Time Used67
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0915-11-031
W. W. FOUNDATION DRILLING, LTD. (8.05)
(USE 07366)J.R. RAMON & SONS, INC (6.73)
ENVIRONMENTAL SAFETY SERVICES, INC. (5.52)
AUSTIN WOOD RECYCLING (2.40)
LONE STAR PAVING (1.33)
FLASHER EQUIPMENT COMPANY (0.94)
FUQUAY, INC. (0.70)
PENHALL COMPANY (0.41)
Contract #01173209
Totals1522927.9149631.501507936.3499.0

CountyBEXAR
HighwayCR
FromGROSS LANE AT MEDINA RIVER
To.
CSJ0915-12-439
Proj IDBR 2007(638)
Work TypeREHABILITATE BRIDGE AND APPROACHES
 
0.001527480.77738106.55100.0
Work Order03-06-15
Work Began04-13-15
Work Completed09-25-17
Time Computed04-13-15
Contract Working Days69
Addl Days Granted91
Working Days Charged160
Percent Time Used100
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-439
MCL CONTRACTING, LLC (0.88)
DOUBLE S PAVING, INC. (2.26)
FLASHER EQUIPMENT COMPANY (1.81)
LONE STAR EROSION CONTROL (1.51)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.71)
ROADWAY SPECIALTIES, INC. (3.58)
ALTUS TRAFFIC MANAGEMENT LLC (0.58)
BEAIRD DRILLING (5.97)
FRANK JR REINFORCEMENT LLC (0.32)
JUST GROOVING, LTD. (0.35)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.39)
Contract #01153028
Totals527480.770.00738106.55100.0

CountyBEXAR
HighwayVA
FromVARIOUS BRIDGES IN BEXAR COUNY
To.
CSJ0915-12-551
Proj IDBR 1502(471)
Work TypeUPGRADE BRIDGE AND APPROACH RAILING
 
0.0011723801.411947939.6199.9
Work Order12-08-15
Work Began02-22-16
Work Completed
Time Computed02-06-16
Contract Working Days221
Addl Days Granted26
Working Days Charged250
Percent Time Used101
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-551
RICE ENVIRONMENTAL SERVICES (3.67)
FLASHER EQUIPMENT COMPANY (3.58)
RAMMING PAVING COMPANY (22.61)
CHEROKEE SERVICES (4.59)
Contract #10153005
Totals1723801.410.001947939.6199.9

CountyBEXAR
HighwayVA
FromIN SAN ANTONIO ON US 281, LOOP 345
ToFM 78 AND FM 1516 CORRIDORS
CSJ0915-12-555
Proj IDSTP 2016(870)TP
Work TypeGRD, BSE, SIDEWALKS, SIGN, PAVT MRK
 
0.0011771321.261315389.0474.2
CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN BEXAR COUNTY
To.
CSJ0915-12-559
Proj IDSTP 1602(380)
Work TypeSIDEWALK
 
0.0013515369.101870883.9353.2
Work Order10-06-16
Work Began11-10-16
Work Completed
Time Computed11-05-16
Contract Working Days309
Addl Days Granted0
Working Days Charged223
Percent Time Used72
Contractor(s)
J3 COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-555
ROADWAY SPECIALTIES, INC. (2.66)
AUSTIN MATERIALS, LLC (1.91)
JARCO TRANSPORT, LLC (1.76)
LONE STAR EROSION CONTROL (4.43)
SAECO ELECTRIC & UTILITY, LTD. (0.20)
WEBB & BEXAR CONSTRUCTION, LLC. (8.59)
M & M STRIPING & POWER WASHING, LLC (0.11)
FLASHER EQUIPMENT COMPANY (0.36)
C & C ALCOSER TRUCKING (1.04)
Contract #08163211
Totals5286690.36295721.793186272.9760.2

CountyBEXAR
HighwayCS
FromON INGRAM RD
ToAT RICHLAND HILLS
CSJ0915-12-570
Proj IDSTP 1702(042)HES
Work TypeINSTALL TRAFFIC SIGNAL
 
0.200188897.500.000.0
CountyBEXAR
HighwayFM 1976
FromAT MIDCROWN
To.
CSJ1890-01-048
Proj IDSTP 1702(043)HES
Work TypeTRAFFIC SIGNALS & ILLUMINATION
 
0.200217051.503736.001.7
Work Order06-14-17
Work Began00-00-00
Work Completed
Time Computed07-14-17
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-570
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173209
Totals405949.000.003736.000.9

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN BEXAR COUNTY
To.
CSJ0915-12-591
Proj IDNH 1702(678)
Work TypeLANDSCAPE DEVELOPMENT
 
0.001510193.000.000.0
Work Order09-14-17
Work Began00-00-00
Work Completed
Time Computed10-14-17
Contract Working Days95
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-591
FLASHER EQUIPMENT COMPANY (2.92)
Contract #08173010
Totals510193.000.000.000.0

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN BEXAR COUNTY
To.
CSJ0915-12-592
Proj IDNH 1702(679)
Work TypeLANDSCAPE DEVELOPMENT
 
0.001682419.000.000.0
Work Order09-14-17
Work Began00-00-00
Work Completed
Time Computed10-14-17
Contract Working Days82
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-592
FLASHER EQUIPMENT COMPANY (3.12)
Contract #08173230
Totals682419.000.000.000.0

CountyMEDINA
HighwayCR
From4.1 MI SW OF FM 471
To.
CSJ0915-45-052
Proj IDBR 1502(643)
Work TypeREPLACE BRIDGE & APPROACHES
 
0.001422407.383120.000.7
Work Order08-23-17
Work Began00-00-00
Work Completed
Time Computed09-22-17
Contract Working Days64
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-45-052
BEAIRD DRILLING (6.07)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (0.70)
AZA BARRICADES (0.66)
ROADWAY SPECIALTIES, INC. (6.86)
Contract #07173238
Totals422407.383120.003120.000.7

CountyKENDALL
HighwayRM 474
FromFM 473
ToKEMMER TRAIL
CSJ1042-01-032
Proj IDSTP 2013(720)
Work TypeGRAD, BSE, SURF, PAVMT MARKINGS
 
6.6734456842.62718682.4816.1
Work Order07-20-17
Work Began00-00-00
Work Completed
Time Computed08-19-17
Contract Working Days261
Addl Days Granted0
Working Days Charged33
Percent Time Used12
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1042-01-032
RELMCO, INC. (23.70)
GEOSOURCE, INC. (3.41)
D.I.J. CONSTRUCTION, INC (2.59)
FLASHER EQUIPMENT COMPANY (1.89)
LONE STAR EROSION CONTROL (1.58)
Contract #06173027
Totals4456842.62427641.53718682.4816.1

CountyMEDINA
HighwayPR 37
FromSH 16
ToBANDERA C/L
CSJ1066-02-017
Proj IDSTP 2018(078)HESG
Work TypeGRAD, SURF, BASE, PAVEMENT MARKINGS
 
4.2861099115.250.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-16-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days153
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1066-02-017
ENVIRONMENTAL SAFETY SERVICES, INC. (18.67)
FLASHER EQUIPMENT COMPANY (6.51)
GEOSOURCE, INC. (6.46)
ROADWAY SPECIALTIES, INC. (5.55)
THE LEVY COMPANY, INC. (4.73)
Contract #09173010
Totals1099115.250.000.000.0

CountyCOMAL
HighwayFM 1101
FromSH 46
To0.5 MI N OF FM 306
CSJ1272-01-016
Proj IDSTP 2014(564)
Work TypeBASE, GR, STR, SIDEWALK
 
2.7976154722.504317713.9070.1
Work Order06-02-14
Work Began01-16-17
Work Completed
Time Computed12-01-14
Contract Working Days354
Addl Days Granted28
Working Days Charged185
Percent Time Used48
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1272-01-016
ENVIRONMENTAL SAFETY SERVICES, INC. (3.55)
E-Z BEL CONSTRUCTION, LLC (2.42)
INTERSTATE CONCRETE & STEEL SERVICES INCORPORATED (39.55)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.21)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.71)
AUSTIN WOOD RECYCLING (0.32)
INTERSTATE BARRICADES & MARKINGS, INC. (1.80)
FUQUAY, INC. (0.97)
Contract #04143002
Totals6154722.50251220.394317713.9070.1

CountyBEXAR
HighwayFM 1516
FromFM 78
ToFM 1976
CSJ1477-01-040
Proj IDSTP 2017(798)MM
Work TypeGRD, BSE, STR, SURF, PAV'T MRK
 
0.7625733862.95150230.362.6
CountyBEXAR
HighwayFM 1516
FromFM 78
ToFM 1976
CSJ1477-01-041
Proj IDSTP 1502(217)
Work TypeACQUISITION, RELOCATION ASSISTANCE
 
0.7621655042.650.000.0
Work Order06-26-17
Work Began00-00-00
Work Completed
Time Computed07-28-17
Contract Working Days586
Addl Days Granted0
Working Days Charged2
Percent Time Used0
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1477-01-040
DU-MOR ENTERPRISES_INC. (0.39)
FUQUAY, INC. (0.58)
AUSTIN WOOD RECYCLING (0.17)
LONE STAR PAVING (13.50)
E-Z BEL CONSTRUCTION, LLC (5.71)
FLASHER EQUIPMENT COMPANY (1.44)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.15)
ROADWAY SPECIALTIES, INC. (0.71)
Contract #03173203
Totals7388905.60125568.51150230.362.0

CountyCOMAL
HighwayFM 306
FromHOFFMANN LANE
To0.5 MI NORTH OF HUNTER ROAD
CSJ1728-02-058
Proj IDSTP 1502(615)MM
Work TypeGRAD, STR, BASE, SURF
 
3.2327936418.828270220.1599.9
Work Order10-21-15
Work Began12-01-15
Work Completed
Time Computed01-19-16
Contract Working Days364
Addl Days Granted0
Working Days Charged421
Percent Time Used115
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1728-02-058
E-Z BEL CONSTRUCTION, LLC (2.34)
CATO ELECTRIC COMPANY (0.00)
HEARN CO. (0.19)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.64)
FLASHER EQUIPMENT COMPANY (0.27)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.41)
R K STEPHENS CONSTRUCTION, LLC (5.07)
TRP CONSTRUCTION GROUP, LLC (1.39)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (3.04)
AUSTIN WOOD RECYCLING (0.61)
SCOTT DERR PAINTING CO, LLC (0.06)
Contract #08153016
Totals7936418.8281630.848270220.1599.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6