Monthly State Let Construction Report For San Antonio District As Of Feb 09, 2018 Page 4 Of 6

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyATASCOSA
HighwaySH 97
From2.6 MILES NORTH OF MCMULLEN C/L
To9.0 MI NORTH OF MCMULLEN C/L
CSJ0328-06-029
Proj IDSTP 2016(072)
Work TypeGR, BASE, STRUC, PVMT MRKINGS
 
6.44110114302.985646787.5655.8
Work Order02-10-16
Work Began04-11-16
Work Completed
Time Computed04-10-16
Contract Working Days451
Addl Days Granted0
Working Days Charged448
Percent Time Used99
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0328-06-029
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.19)
CUATRO T CONSTRUCTION, INC. (5.04)
FLASHER EQUIPMENT COMPANY (2.43)
RELMCO, INC. (1.68)
(USE 25816)D & S TEXAS ICON CONSTRUCTION, LLC. (0.53)
FUQUAY, INC. (1.61)
CHEROKEE SERVICES (0.43)
LORENZ FIELD SERVICES, LLC (0.14)
ALTUS TRAFFIC MANAGEMENT LLC (0.43)
R & P CONSTRUCTION (5.70)
K-BAR SERVICES, INC. (0.01)
Contract #09153006
Totals10114302.98300674.875646787.5655.8

CountyATASCOSA
HighwaySH 97
FromMCMULLEN/ATASCOSA C/L
To2.6 MI N. OF MCMULLEN/ATASCOSA C/L
CSJ0328-06-030
Proj IDSTP 1702(814)
Work TypeGRADE, BASE, SC, SURF, PVMT MRK
 
2.5592924983.58656144.7922.4
Work Order09-20-17
Work Began11-27-17
Work Completed
Time Computed10-20-17
Contract Working Days185
Addl Days Granted1
Working Days Charged34
Percent Time Used18
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0328-06-030
D.I.J. CONSTRUCTION, INC (3.46)
FLASHER EQUIPMENT COMPANY (0.85)
INTERSTATE CONCRETE & STEEL SERVICES INCORPORATED (13.56)
LONE STAR EROSION CONTROL (4.22)
ROADWAY SPECIALTIES, INC. (3.92)
ALPHA PAVING INDUSTRIES LLC (0.19)
Contract #08173041
Totals2924983.58191880.80656144.7922.4

CountyMCMULLEN
HighwaySH 97
FromLASALLE COUNTY LINE
ToATASCOSA COUNTY LINE
CSJ0328-07-014
Proj IDSTP 1702(410)
Work TypeGRADE, BASE, SC, SURF, PAVMT MRK
 
5.0074336031.67739305.8317.0
Work Order07-20-17
Work Began09-18-17
Work Completed
Time Computed08-19-17
Contract Working Days312
Addl Days Granted2
Working Days Charged46
Percent Time Used14
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0328-07-014
MPB, INC. (2.31)
FLASHER EQUIPMENT COMPANY (6.85)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.22)
LONE STAR EROSION CONTROL (3.95)
THE LEVY COMPANY, L.P. (1.19)
CLARK CONSTRUCTION OF TEXAS, INC. (6.69)
ALPHA PAVING INDUSTRIES LLC (0.54)
Contract #06173218
Totals4336031.67292152.74739305.8317.0

CountyGUADALUPE
HighwaySH 123
FromAT BS 123
To.
CSJ0366-02-090
Proj IDNH 2017(562)
Work TypeGRAD,BASE,SURF,SIGNALS,SIGN,PVT MRK
 
0.330669005.338052.251.2
Work Order12-19-17
Work Began00-00-00
Work Completed
Time Computed01-18-17
Contract Working Days72
Addl Days Granted0
Working Days Charged2
Percent Time Used2
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0366-02-090
INTERSTATE BARRICADES & MARKINGS, INC. (3.59)
SAECO ELECTRIC & UTILITY, LTD. (24.87)
ENVIRONMENTAL SAFETY SERVICES, INC. (5.50)
Contract #11173211
Totals669005.338052.258052.251.2

CountyWILSON
HighwaySH 123
FromAT FM 537, FM 1347 AND FM 541
To.
CSJ0366-05-044
Proj IDSTP 2017(285)
Work TypeGRAD, BSE, SURF, PAVMT MRK
 
1.313611559.93577628.4194.4
Work Order12-12-16
Work Began05-08-17
Work Completed
Time Computed12-03-16
Contract Working Days33
Addl Days Granted5
Working Days Charged37
Percent Time Used97
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0366-05-044
DELGADO"S CONSTRUCTION (10.77)
FLASHER EQUIPMENT COMPANY (1.30)
D. I. J. CONSTRUCTION, INC. (7.45)
GEOSOURCE, INC. (0.29)
FUQUAY, INC. (1.99)
Contract #11163011
Totals611559.93102.30577628.4194.4

CountyGUADALUPE
HighwayBS 123B
From0.2 MI NORTH OF US 90
ToIH 10
CSJ0366-12-026
Proj IDSTP 2016(176)
Work TypeGR, BASE, STR, SURF, CURB,PAV'T MRK
 
1.0225283542.962111452.0439.9
CountyGUADALUPE
HighwayBS 123B
From0.2 MI NORTH OF US 90
ToIH 10
CSJ0366-12-027
Proj IDROW 366-12-27
Work TypeACQUISITION AND UTILITIES
 
1.0221805450.791014659.5356.1
Work Order01-29-16
Work Began05-29-16
Work Completed
Time Computed02-29-16
Contract Working Days375
Addl Days Granted0
Working Days Charged108
Percent Time Used28
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0366-12-026
ENVIRONMENTAL SAFETY SERVICES, INC. (2.69)
E-Z BEL CONSTRUCTION, LLC (0.94)
2 J RESOURCES COMPANY (3.19)
FLASHER EQUIPMENT COMPANY (0.71)
DC CIVIL CONSTRUCTION LLC (16.21)
CLAUDIA SERNA DBA SERNA"S TRUCKING (0.00)
MELENDREZ BROTHERS TRUCKING, INC. (0.06)
CUATRO T CONSTRUCTION, INC. (0.00)
Contract #10153217
Totals7088993.75373685.663126111.5744.0

CountyMCMULLEN
HighwaySH 72
FromSH 97
ToSH 16
CSJ0483-02-021
Proj IDSTP 2018(077)
Work TypeGR, BASE, SURF, PVMT MRKINGS
 
15.56328907909.730.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days586
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0483-02-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183003
Totals28907909.730.000.000.0

CountyBEXAR
HighwayIH 410
FromSH 151
ToINGRAM RD.
CSJ0521-04-274
Proj IDC 521-4-274
Work TypeGRAD, STR, BASE, SURF, PAV MARKINGS
 
2.71681778634.0475833717.1092.7
CountyBEXAR
HighwayIH 410
FromSH 151
ToINGRAM RD.
CSJ0521-04-276
Proj IDROW 521-4-276
Work TypeROW UTILITY ADJUSTMENTS
 
2.716103972.0081281.5878.1
Work Order07-31-15
Work Began10-12-15
Work Completed
Time Computed10-29-15
Contract Working Days760
Addl Days Granted0
Working Days Charged594
Percent Time Used78
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0521-04-274
INDUS CONSTRUCTION, L.P. (6.72)
CPAVE, INC. (0.19)
MOBILE ENTERPRISES, INC. (0.01)
S & S BRIDGE PAINTING, INC. (1.63)
FLASHER EQUIPMENT COMPANY (0.62)
Z & L CONCRETE CONTRACTORS, INC. (3.85)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.48)
F & W ELECTRICAL CONTRACTORS, INC. (5.05)
SCOTT DERR PAINTING CO, LLC (0.30)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.01)
NORTEX CONCRETE LIFT & STABILIZATION, INC. (0.06)
Contract #06153001
Totals81882606.041014506.4775914998.6892.7

CountyBEXAR
HighwayIH 410
From0.1 MI N OF US 90
To0.3 MI S OF SH 151
CSJ0521-04-277
Proj IDNH 1602(247)
Work TypeGRAD, STR, BASE, SURF & PAV MARK
 
2.16238980576.2013656562.2135.0
CountyBEXAR
HighwayIH 410
From0.1 MI N OF US 90
To0.3 MI S OF SH 151
CSJ0521-04-284
Proj IDNH 2017(417)
Work TypeROW UTILITY ADJUSTMENTS
 
2.1621565942.251242676.9879.3
CountyBEXAR
HighwayIH 410
FromAT US 90 WEST
ToINTERCHANGE
CSJ0521-05-118
Proj IDNH 1602(247)
Work TypeGRAD,STR,BASE,SURF & PAV MARK
 
0.39033369177.2629954684.1189.7
CountyBEXAR
HighwayIH 410
FromAT US 90 WEST
ToINTERCHANGE
CSJ0521-05-142
Proj IDROW 521-5-142
Work TypeSA ROW ACQ AND UTILITIES
 
0.39013706.0015679.8099.9
Work Order12-27-16
Work Began01-16-17
Work Completed
Time Computed01-16-17
Contract Working Days1,000
Addl Days Granted0
Working Days Charged310
Percent Time Used31
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0521-04-277
THE LEVY COMPANY, L.P. (4.94)
SCOTT DERR PAINTING CO, LLC (0.28)
GEOSOURCE, INC. (0.15)
EGGEMEYER LAND CLEARING, LLC (0.02)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.13)
BADECO, INC (0.27)
FLASHER EQUIPMENT COMPANY (0.56)
LONE STAR EROSION CONTROL (0.13)
AARON CONCRETE CONTRACTORS, L.P. (5.88)
JPC CONSTRUCTION INC DBA JC COMMUNICATIONS (0.16)
LONE STAR SITEWORK, LLC (0.29)
ROYAL REBAR (4.47)
Z & L CONCRETE CONTRACTORS, INC. (2.40)
ROADWAY SPECIALTIES, INC. (1.10)
PRESIDIO CONTRACTING, LLC (0.03)
E&E GROUP INC., DBA LIGHT IT UP ELECTRIC (0.02)
NORTEX CONCRETE LIFT & STABILIZATION, INC. (0.00)
BORTUNCO (0.00)
CALAME CONTRACTING, LLC (0.25)
Contract #12163001
Totals73929401.712610999.4244869603.1060.6

CountyBEXAR
HighwayIH 410
FromFREDRICKSBURG RD
ToIH 35
CSJ0521-04-278
Proj IDNH 2017(985)
Work TypeSURFACE & PAVEMENT MARKINGS
 
10.5223839721.962887820.7275.2
Work Order08-07-17
Work Began09-18-17
Work Completed
Time Computed09-06-17
Contract Working Days88
Addl Days Granted0
Working Days Charged61
Percent Time Used69
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0521-04-278
FLASHER EQUIPMENT COMPANY (6.94)
THE LEVY COMPANY, L.P. (11.30)
ROADWAY SPECIALTIES, INC. (5.43)
Contract #05173219
Totals3839721.968547.942887820.7275.2

CountyBEXAR
HighwayIH 410
From1.4 MI SOUTH OF US 90
To0.9 MI SOUTH OF FM 2536
CSJ0521-05-145
Proj IDNH 2018(533)
Work TypeSURFACE & PAVEMENT MARKERS
 
3.7382494814.180.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days41
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0521-05-145
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183224
Totals2494814.180.000.000.0

CountyGUADALUPE
HighwayIH 10
FromSH 46
ToSH 123 B
CSJ0535-01-072
Proj IDC 535-1-72
Work TypeGRAD,BSE,STR,SURF,SIGN,PAV'T MRK
 
2.02729174029.3228807447.1898.7
Work Order07-30-15
Work Began11-30-15
Work Completed
Time Computed11-30-15
Contract Working Days782
Addl Days Granted0
Working Days Charged537
Percent Time Used68
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0535-01-072
AARON CONCRETE CONTRACTORS, L.P. (0.82)
ALTUS TRAFFIC MANAGEMENT LLC (0.32)
DIAMOND SURFACE, INC. (0.02)
FLASHER EQUIPMENT COMPANY (0.57)
RAMMING PAVING COMPANY (14.42)
ROADWAY SPECIALTIES, INC. (0.52)
DRILL TECH DRILLING & SHORING, INC. (4.11)
DYWIDAG-SYSTEMS INTERNATIONAL_USA,INC. (0.36)
K.L. DURHAM CONSTRUCTION, LLC (0.07)
MURRAY CONSTRUCTION (0.28)
PENHALL COMPANY (AUSTIN) (0.07)
RICE ENVIRONMENTAL SERVICES (0.68)
SCR CONSTRUCTION CO., INC. (0.21)
VOGES DRILLING (1.00)
THE LEVY COMPANY, L.P. (5.40)
CP REBAR AND PT INSTALLATION (0.35)
FRANK JR REINFORCEMENT LLC (0.07)
TEXAS HIGHWAY WALLS (1.10)
2 J RESOURCES COMPANY (5.73)
MK1 CONSTRUCTION SERVICES, LLC (1.86)
LONE STAR PAVING (0.05)
Contract #05153003
Totals29174029.32801323.1628807447.1898.7

CountyGUADALUPE
HighwayIH 10
From0.3 MI EAST OF FM 1104
To0.3 MI WEST OF CR 216
CSJ0535-02-048
Proj IDNH 2018(404)
Work TypeGRAD,STR,SURF,ILLUM,PAVT MRK,SCALES
 
1.2613343191.830.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days198
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0535-02-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183018
Totals3343191.830.000.000.0

CountyATASCOSA
HighwaySH 16
From0.937 MI S OF FM 3350
To0.951 MI N OF CR 306
CSJ0613-02-057
Proj IDSTP 1502(276)HES
Work TypeCENTERLINE TEXTURING
 
4.00035128.4031228.0088.8
CountyATASCOSA
HighwaySH 16
FromSH 97
To0.2 MI SOUTH OF SP 282
CSJ0613-02-058
Proj IDSTP 1502(275)
Work TypeGRADING, HMA, SURF, PAV MRK
 
7.77313453085.6313472690.7999.9
Work Order08-20-15
Work Began10-19-15
Work Completed
Time Computed10-20-15
Contract Working Days146
Addl Days Granted178
Working Days Charged407
Percent Time Used125
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0613-02-057
CHEROKEE SERVICES (0.15)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.76)
FLASHER EQUIPMENT COMPANY (1.20)
WEST TX RUMBLE STRIP (0.03)
D&S TEXAS ICON CONSTRUCTION, LLC (0.18)
FUQUAY, INC. (0.80)
CUATRO T CONSTRUCTION, INC. (2.04)
AARON CONCRETE CONTRACTORS, L.P. (0.45)
MURRAY CONSTRUCTION (0.07)
Contract #06153207
Totals13488214.03257606.6513503918.7999.9

CountyMEDINA
HighwayFM 462
From0.1 MI NORTH OF CR 532
To0.4 MI SOUTH OF CR 540
CSJ0848-01-041
Proj IDSTP 1702(427)
Work TypeGR, BASE, SURF, PVMT MRKINGS
 
2.8172846962.561849711.9364.9
Work Order07-20-17
Work Began08-28-17
Work Completed
Time Computed08-19-17
Contract Working Days198
Addl Days Granted0
Working Days Charged112
Percent Time Used56
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0848-01-041
D.I.J. CONSTRUCTION, INC (1.74)
LONE STAR EROSION CONTROL (6.70)
ROADWAY SPECIALTIES, INC. (3.71)
AREA WIDE PROTECTIVE, INC. (0.93)
Contract #06173040
Totals2846962.56453051.031849711.9364.9

CountyWILSON
HighwayFM 775
FromUS 87
ToFM 3432
CSJ0850-04-027
Proj IDSTP 2018(534)
Work TypeSURFACE, PAV T MRK
 
5.2771910636.820.000.0
CountyWILSON
HighwayFM 775
FromAT FM 3432/CR 319
To.
CSJ3440-01-013
Proj IDSTP 2018(535)HES
Work TypeSIGNALS, SIGNS & ILLUMINATION
 
0.109185631.570.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days85
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0850-04-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183231
Totals2096268.390.000.000.0

CountyECTOR
HighwayVA
FromON IH 10 IN PECOS COUNTY
To.
CSJ0906-00-180
Proj IDNH 2017(558)
Work TypeINSTALL DMS
 
0.001112682.11118676.7999.9
CountyTOM GREEN
HighwayVA
FromON IH 10 FROM KIMBLE/KERR CO LINE
ToTO CROCKETT/PECOS COUNTY LINE
CSJ0907-00-183
Proj IDNH 2017(558)
Work TypeINSTALL DMS
 
0.001683074.05709198.0999.9
CountyBEXAR
HighwayVA
FromON IH 10 FROM CITY OF BOERNE
ToKIMBLE/KERR COUNTY LINE
CSJ0915-00-194
Proj IDNH 2017(558)
Work TypeINSTALL DMS
 
0.001960828.16993165.4799.9
Work Order03-15-17
Work Began00-00-00
Work Completed
Time Computed04-14-17
Contract Working Days123
Addl Days Granted6
Working Days Charged145
Percent Time Used112
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-180
E&E GROUP INC., DBA LIGHT IT UP ELECTRIC (10.81)
JCD CONSTRUCTION, LLC (2.68)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (13.71)
FLASHER EQUIPMENT COMPANY (1.13)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.36)
GRUPO CONSTRUCTOR VELACOR, LLC (2.73)
Contract #02173235
Totals1756584.32233377.341821040.3599.9

CountyBEXAR
HighwayVA
FromDISTRICTWIDE GUIDESIGNS FY14
To.
CSJ0915-00-155
Proj IDSTP 2014(562)
Work TypeDISTRICTWIDE GUIDESIGNS FY14
 
0.001998524.12612045.9261.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-20-14
Work Began07-20-14
Work Completed
Time Computed07-21-14
Contract Working Days208
Addl Days Granted4
Working Days Charged559
Percent Time Used263
Contractor(s)
SURETEC INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-155
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04143205
Totals998524.120.00612045.9261.2

CountyBEXAR
HighwayVA
FromDISTRICTWIDE GUIDESIGNS FY16
To.
CSJ0915-00-159
Proj IDSTP 2016(902)
Work TypeDISTRICTWIDE GUIDESIGNS FY16
 
0.0012452827.792675994.7999.9
Work Order06-03-16
Work Began11-07-16
Work Completed
Time Computed07-03-16
Contract Working Days360
Addl Days Granted0
Working Days Charged274
Percent Time Used76
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-159
FLASHER EQUIPMENT COMPANY (1.14)
ENVIRONMENTAL SAFETY SERVICES, INC. (8.75)
JCD CONSTRUCTION, LLC (0.11)
AMERICAN TRAFFIC CONTROL (15.49)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (0.87)
Contract #04163232
Totals2452827.79119430.572675994.7999.9

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2016
To.
CSJ0915-00-166
Proj IDSTP 2016(669)
Work TypeDISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.0011355867.971071266.5579.0
Work Order03-28-16
Work Began06-09-16
Work Completed
Time Computed04-27-16
Contract Working Days320
Addl Days Granted0
Working Days Charged229
Percent Time Used71
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-166
FLASHER EQUIPMENT COMPANY (2.31)
HEARN CO. (6.88)
Contract #02163034
Totals1355867.970.001071266.5579.0