Monthly State Let Construction Report For San Antonio District As Of Oct 16, 2017 Page 4 Of 6

Last Update: Monday, October 16, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWILSON
HighwaySH 97
FromUS 181
ToUS 87
CSJ0328-01-014
Proj IDSTP 1502(611)
Work TypeGRADE, BASE, SC, SURF, PAVMT MRK
 
10.61317618829.4613210548.5174.9
Work Order11-04-15
Work Began06-13-16
Work Completed
Time Computed01-04-16
Contract Working Days455
Addl Days Granted0
Working Days Charged318
Percent Time Used69
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0328-01-014
INTERSTATE BARRICADES & MARKINGS, INC. (2.37)
MURRAY CONSTRUCTION (0.22)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.40)
ROADWAY SPECIALTIES, INC. (3.27)
CATO ELECTRIC COMPANY (0.14)
E-Z BEL CONSTRUCTION, LLC (0.54)
AUSTIN WOOD RECYCLING (0.67)
Contract #08153006
Totals17618829.46819803.4213210548.5174.9

CountyWILSON
HighwaySH 97
FromATASCOSA COUNTY LINE
ToLP 181
CSJ0328-02-043
Proj IDSTP 2017(476)
Work TypeGRADE, BASE, SURF, PAVMT MRK
 
12.72818593935.696923941.8237.2
Work Order02-22-17
Work Began04-07-17
Work Completed
Time Computed03-24-17
Contract Working Days586
Addl Days Granted0
Working Days Charged123
Percent Time Used20
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0328-02-043
MV HENKE COMPANY, LLC (0.34)
RELMCO, INC. (5.70)
THE LEVY COMPANY, L.P. (0.89)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.02)
MPB, INC. (0.47)
GEOSOURCE, INC. (0.93)
FUQUAY, INC. (1.10)
FLASHER EQUIPMENT COMPANY (2.07)
Contract #01173201
Totals18593935.691643156.936923941.8237.2

CountyATASCOSA
HighwaySH 97
From05037
ToIH 37
CSJ0328-03-032
Proj IDSTP 1502(165)
Work TypeGRADE, BASE, SURF, PAVMT MRK
 
6.67811864971.9912289552.01100.0
Work Order07-16-15
Work Began02-01-16
Work Completed09-12-17
Time Computed09-14-15
Contract Working Days286
Addl Days Granted38
Working Days Charged324
Percent Time Used100
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0328-03-032
FLASHER EQUIPMENT COMPANY (0.42)
MURRAY CONSTRUCTION (0.27)
EGGEMEYER LAND CLEARING, LLC (0.36)
LONE STAR EROSION CONTROL (1.75)
INTERSTATE BARRICADES & MARKINGS, INC. (2.27)
THE LEVY COMPANY, L.P. (0.06)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.23)
ROADWAY SPECIALTIES, INC. (0.82)
BILL HALL JR. TRUCKING, LTD. (1.83)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (1.83)
RELMCO, INC. (0.56)
GEOSOURCE, INC. (0.37)
Contract #05153206
Totals11864971.9968978.7412289552.01100.0

CountyATASCOSA
HighwaySH 97
FromUS 281
ToIH 37
CSJ0328-03-035
Proj IDSTP 1702(669)
Work TypeGRD, BSE, SURF, PAV'T MRK
 
3.5328575353.090.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days308
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0328-03-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173206
Totals8575353.090.000.000.0

CountyATASCOSA
HighwaySH 97
From0.6 MILES EAST OF BURNETT AVE
ToSH 16
CSJ0328-05-037
Proj IDSTP 1502(166)
Work TypeGRADE, BASE, SC, SURF, PAVMT MRK
 
9.83717494208.2410273128.1559.7
Work Order07-07-15
Work Began09-08-15
Work Completed
Time Computed09-08-15
Contract Working Days339
Addl Days Granted8
Working Days Charged489
Percent Time Used140
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0328-05-037
LONE STAR EROSION CONTROL (1.05)
ALTUS TRAFFIC MANAGEMENT LLC (0.14)
RELMCO, INC. (2.27)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.14)
INTERSTATE BARRICADES & MARKINGS, INC. (1.62)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.53)
CUATRO T CONSTRUCTION, INC. (17.91)
THE LEVY COMPANY, L.P. (0.39)
CENTRAL ELITE TRANSPORT, LLC (0.18)
GULLEY TRUCKING (0.00)
K-BAR SERVICES, INC. (0.00)
Contract #05153007
Totals17494208.24181698.0510273128.1559.7

CountyATASCOSA
HighwaySH 97
FromFM 140
To0.6 MILES EAST OF BURNETT AVE
CSJ0328-05-044
Proj IDSTP 1502(612)
Work TypeGRADE, BASE, SC, SURF, PAVMT MRK
 
0.9571760591.97585790.4434.3
CountyATASCOSA
HighwaySH 97
From9.0 MI NORTH OF MCMULLEN C/L
ToFM 140
CSJ0328-06-027
Proj IDSTP 1502(612)
Work TypeGRADE, BASE, SC, SURF, PVMT MRK
 
6.84810776872.666610942.2161.3
Work Order10-30-15
Work Began01-14-16
Work Completed
Time Computed12-29-15
Contract Working Days417
Addl Days Granted0
Working Days Charged432
Percent Time Used103
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0328-05-044
B & B HIGHWAY SERVICES (0.18)
CHEROKEE SERVICES (0.34)
CUATRO T CONSTRUCTION, INC. (10.95)
D & S TEXAS ICON CONSTRUCTION, LLC. (0.07)
INTERSTATE BARRICADES & MARKINGS, INC. (0.39)
THE LEVY COMPANY, L.P. (0.18)
LONE STAR EROSION CONTROL (1.64)
RELMCO, INC. (2.54)
ROADWAY SPECIALTIES, INC. (1.92)
FLASHER EQUIPMENT COMPANY (2.07)
K-BAR SERVICES, INC. (0.02)
Contract #08153208
Totals12537464.63340716.167196732.6557.5

CountyATASCOSA
HighwaySH 97
FromMCMULLEN/ATASCOSA C/L
To2.0 MI N. OF MCMULLEN/ATASCOSA C/L
CSJ0328-06-028
Proj IDSTP 1402(065)
Work TypeGRADE, BASE, SC, SURF, PVMT MRK
 
2.5593835534.674522453.3099.9
CountyMCMULLEN
HighwaySH 97
FromLASALLE/MCMULLEN C/L
ToATASCOSA/MCMULLEN C/L
CSJ0328-07-016
Proj IDSTP 1402(065)
Work TypeGRADE, BASE, SC, SURF, PAVMT MRK
 
10.34014856569.6916085512.7999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-17-14
Work Began11-10-14
Work Completed
Time Computed11-10-14
Contract Working Days331
Addl Days Granted88
Working Days Charged474
Percent Time Used113
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0328-06-028
N-LINE TRAFFIC MAINTENANCE, L.P. (0.49)
LONE STAR EROSION CONTROL (3.08)
F & W ELECTRICAL CONTRACTORS, INC. (0.22)
FLASHER EQUIPMENT COMPANY (1.61)
LONE STAR PAVING (37.44)
TRINITY EAGLEFORD SERVICES LLC (1.21)
GEOSOURCE, INC. (0.99)
CUATRO T CONSTRUCTION, INC. (11.10)
Contract #08143004
Totals18692104.360.0020607966.0999.9

CountyATASCOSA
HighwaySH 97
From2.6 MILES NORTH OF MCMULLEN C/L
To9.0 MI NORTH OF MCMULLEN C/L
CSJ0328-06-029
Proj IDSTP 2016(072)
Work TypeGR, BASE, STRUC, PVMT MRKINGS
 
6.44110114302.984345484.2442.9
Work Order02-10-16
Work Began04-11-16
Work Completed
Time Computed04-10-16
Contract Working Days451
Addl Days Granted0
Working Days Charged368
Percent Time Used81
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0328-06-029
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.19)
CUATRO T CONSTRUCTION, INC. (5.04)
FLASHER EQUIPMENT COMPANY (2.43)
RELMCO, INC. (1.68)
(USE 25816)D & S TEXAS ICON CONSTRUCTION, LLC. (0.53)
FUQUAY, INC. (1.61)
CHEROKEE SERVICES (0.43)
LORENZ FIELD SERVICES, LLC (0.14)
ALTUS TRAFFIC MANAGEMENT LLC (0.43)
R & P CONSTRUCTION (5.70)
K-BAR SERVICES, INC. (0.01)
Contract #09153006
Totals10114302.98271355.924345484.2442.9

CountyATASCOSA
HighwaySH 97
FromMCMULLEN/ATASCOSA C/L
To2.6 MI N. OF MCMULLEN/ATASCOSA C/L
CSJ0328-06-030
Proj IDSTP 1702(814)
Work TypeGRADE, BASE, SC, SURF, PVMT MRK
 
2.5592924983.580.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-20-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days185
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0328-06-030
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173041
Totals2924983.580.000.000.0

CountyMCMULLEN
HighwaySH 97
FromLASALLE COUNTY LINE
ToATASCOSA COUNTY LINE
CSJ0328-07-014
Proj IDSTP 1702(410)
Work TypeGRADE, BASE, SC, SURF, PAVMT MRK
 
5.0074336031.670.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-17
Work Began09-18-17
Work Completed
Time Computed08-19-17
Contract Working Days312
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0328-07-014
MPB, INC. (2.31)
FLASHER EQUIPMENT COMPANY (6.85)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.22)
LONE STAR EROSION CONTROL (3.95)
THE LEVY COMPANY, L.P. (1.19)
CLARK CONSTRUCTION OF TEXAS, INC. (6.69)
Contract #06173218
Totals4336031.670.000.000.0

CountyWILSON
HighwaySH 123
FromAT FM 537, FM 1347 AND FM 541
To.
CSJ0366-05-044
Proj IDSTP 2017(285)
Work TypeGRAD, BSE, SURF, PAVMT MRK
 
1.313611559.93577526.1194.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-12-16
Work Began05-08-17
Work Completed
Time Computed12-03-16
Contract Working Days33
Addl Days Granted5
Working Days Charged37
Percent Time Used97
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0366-05-044
DELGADO"S CONSTRUCTION (10.77)
FLASHER EQUIPMENT COMPANY (1.30)
D. I. J. CONSTRUCTION, INC. (7.45)
GEOSOURCE, INC. (0.29)
FUQUAY, INC. (1.99)
Contract #11163011
Totals611559.930.00577526.1194.4

CountyGUADALUPE
HighwayBS 123B
From0.2 MI NORTH OF US 90
ToIH 10
CSJ0366-12-026
Proj IDSTP 2016(176)
Work TypeGR, BASE, STR, SURF, CURB,PAV'T MRK
 
1.0225283542.961320206.3524.9
CountyGUADALUPE
HighwayBS 123B
From0.2 MI NORTH OF US 90
ToIH 10
CSJ0366-12-027
Proj IDROW 366-12-27
Work TypeACQUISITION AND UTILITIES
 
1.0221805450.79743578.8541.1
Work Order01-29-16
Work Began05-29-16
Work Completed
Time Computed02-29-16
Contract Working Days375
Addl Days Granted0
Working Days Charged37
Percent Time Used9
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0366-12-026
ENVIRONMENTAL SAFETY SERVICES, INC. (2.69)
E-Z BEL CONSTRUCTION, LLC (0.94)
2 J RESOURCES COMPANY (3.19)
FLASHER EQUIPMENT COMPANY (0.71)
DC CIVIL CONSTRUCTION LLC (16.21)
CLAUDIA SERNA DBA SERNA"S TRUCKING (0.00)
MELENDREZ BROTHERS TRUCKING, INC. (0.06)
Contract #10153217
Totals7088993.7599761.802063785.2029.1

CountyBEXAR
HighwaySL 13
FromFAIRLAWN
ToIH 10
CSJ0521-01-050
Proj IDNH 2016(668)
Work TypeSURFACE & PAVEMENT MARKINGS
 
6.0382849994.413367442.78100.0
Work Order03-09-16
Work Began04-08-16
Work Completed09-25-17
Time Computed04-08-16
Contract Working Days89
Addl Days Granted14
Working Days Charged101
Percent Time Used98
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0521-01-050
INTERSTATE BARRICADES & MARKINGS, INC. (4.88)
SCR CONSTRUCTION CO., INC. (2.38)
Contract #02163006
Totals2849994.4111900.053367442.78100.0

CountyBEXAR
HighwayIH 410
FromSH 151
ToINGRAM RD.
CSJ0521-04-274
Proj IDC 521-4-274
Work TypeGRAD, STR, BASE, SURF, PAV MARKINGS
 
2.71681778634.0468903800.6984.2
CountyBEXAR
HighwayIH 410
FromSH 151
ToINGRAM RD.
CSJ0521-04-276
Proj IDROW 521-4-276
Work TypeROW UTILITY ADJUSTMENTS
 
2.716103972.0081281.5878.1
Work Order07-31-15
Work Began10-12-15
Work Completed
Time Computed10-29-15
Contract Working Days760
Addl Days Granted0
Working Days Charged530
Percent Time Used69
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0521-04-274
INDUS CONSTRUCTION, L.P. (6.72)
CPAVE, INC. (0.19)
MOBILE ENTERPRISES, INC. (0.01)
S & S BRIDGE PAINTING, INC. (1.63)
FLASHER EQUIPMENT COMPANY (0.62)
Z & L CONCRETE CONTRACTORS, INC. (3.85)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.48)
F & W ELECTRICAL CONTRACTORS, INC. (5.05)
SCOTT DERR PAINTING CO, LLC (0.30)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.01)
Contract #06153001
Totals81882606.041367147.5968985082.2784.2

CountyBEXAR
HighwayIH 410
From0.1 MI N OF US 90
To0.3 MI S OF SH 151
CSJ0521-04-277
Proj IDNH 1602(247)
Work TypeGRAD, STR, BASE, SURF & PAV MARK
 
2.16238980576.2011543552.3029.6
CountyBEXAR
HighwayIH 410
From0.1 MI N OF US 90
To0.3 MI S OF SH 151
CSJ0521-04-284
Proj IDNH 2017(417)
Work TypeROW UTILITY ADJUSTMENTS
 
2.1621565942.251000465.9863.8
CountyBEXAR
HighwayIH 410
FromAT US 90 WEST
ToINTERCHANGE
CSJ0521-05-118
Proj IDNH 1602(247)
Work TypeGRAD,STR,BASE,SURF & PAV MARK
 
0.39033369177.2620426845.1261.2
CountyBEXAR
HighwayIH 410
FromAT US 90 WEST
ToINTERCHANGE
CSJ0521-05-142
Proj IDROW 521-5-142
Work TypeSA ROW ACQ AND UTILITIES
 
0.39013706.0015679.8099.9
Work Order12-27-16
Work Began01-16-17
Work Completed
Time Computed01-16-17
Contract Working Days1,000
Addl Days Granted0
Working Days Charged213
Percent Time Used21
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0521-04-277
THE LEVY COMPANY, L.P. (4.94)
SCOTT DERR PAINTING CO, LLC (0.28)
GEOSOURCE, INC. (0.15)
EGGEMEYER LAND CLEARING, LLC (0.02)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.13)
BADECO, INC (0.27)
FLASHER EQUIPMENT COMPANY (0.56)
LONE STAR EROSION CONTROL (0.13)
AARON CONCRETE CONTRACTORS, L.P. (5.88)
JPC CONSTRUCTION INC DBA JC COMMUNICATIONS (0.16)
LONE STAR SITEWORK, LLC (0.29)
ROYAL REBAR (4.47)
Z & L CONCRETE CONTRACTORS, INC. (2.40)
ROADWAY SPECIALTIES, INC. (1.10)
PRESIDIO CONTRACTING, LLC (0.03)
E&E GROUP INC., DBA LIGHT IT UP ELECTRIC (0.02)
Contract #12163001
Totals73929401.715086487.0532986543.2044.6

CountyBEXAR
HighwayIH 410
FromFREDRICKSBURG RD
ToIH 35
CSJ0521-04-278
Proj IDNH 2017(985)
Work TypeSURFACE & PAVEMENT MARKINGS
 
10.5223839721.96396259.2110.3
Work Order08-07-17
Work Began00-00-00
Work Completed
Time Computed09-06-17
Contract Working Days88
Addl Days Granted0
Working Days Charged14
Percent Time Used15
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0521-04-278
FLASHER EQUIPMENT COMPANY (6.94)
THE LEVY COMPANY, L.P. (11.30)
ROADWAY SPECIALTIES, INC. (5.43)
Contract #05173219
Totals3839721.96396259.21396259.2110.3

CountyGUADALUPE
HighwayIH 10
FromSH 46
ToSH 123 B
CSJ0535-01-072
Proj IDC 535-1-72
Work TypeGRAD,BSE,STR,SURF,SIGN,PAV'T MRK
 
2.02729174029.3226169543.7089.7
Work Order07-30-15
Work Began11-30-15
Work Completed
Time Computed11-30-15
Contract Working Days782
Addl Days Granted0
Working Days Charged459
Percent Time Used58
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0535-01-072
AARON CONCRETE CONTRACTORS, L.P. (0.82)
ALTUS TRAFFIC MANAGEMENT LLC (0.32)
DIAMOND SURFACE, INC. (0.02)
FLASHER EQUIPMENT COMPANY (0.57)
RAMMING PAVING COMPANY (14.04)
ROADWAY SPECIALTIES, INC. (0.52)
DRILL TECH DRILLING & SHORING, INC. (4.11)
DYWIDAG-SYSTEMS INTERNATIONAL_USA,INC. (0.36)
K.L. DURHAM CONSTRUCTION, LLC (0.07)
MURRAY CONSTRUCTION (0.28)
PENHALL COMPANY (AUSTIN) (0.07)
RICE ENVIRONMENTAL SERVICES (0.68)
SCR CONSTRUCTION CO., INC. (0.21)
VOGES DRILLING (1.00)
THE LEVY COMPANY, L.P. (5.40)
CP REBAR AND PT INSTALLATION (0.35)
FRANK JR REINFORCEMENT LLC (0.07)
TEXAS HIGHWAY WALLS (1.10)
2 J RESOURCES COMPANY (5.73)
MK1 CONSTRUCTION SERVICES, LLC (1.86)
Contract #05153003
Totals29174029.32457603.3826169543.7089.7

CountyATASCOSA
HighwaySH 16
From0.937 MI S OF FM 3350
To0.951 MI N OF CR 306
CSJ0613-02-057
Proj IDSTP 1502(276)HES
Work TypeCENTERLINE TEXTURING
 
4.00035128.4031228.0088.8
CountyATASCOSA
HighwaySH 16
FromSH 97
To0.2 MI SOUTH OF SP 282
CSJ0613-02-058
Proj IDSTP 1502(275)
Work TypeGRADING, HMA, SURF, PAV MRK
 
7.77313453085.6313062008.0399.3
Work Order08-20-15
Work Began10-19-15
Work Completed
Time Computed10-20-15
Contract Working Days146
Addl Days Granted22
Working Days Charged407
Percent Time Used242
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0613-02-057
CHEROKEE SERVICES (0.15)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.76)
FLASHER EQUIPMENT COMPANY (1.20)
WEST TX RUMBLE STRIP (0.03)
D&S TEXAS ICON CONSTRUCTION, LLC (0.18)
FUQUAY, INC. (0.80)
CUATRO T CONSTRUCTION, INC. (2.04)
AARON CONCRETE CONTRACTORS, L.P. (0.45)
MURRAY CONSTRUCTION (0.07)
Contract #06153207
Totals13488214.033404.0013093236.0399.3

CountyMEDINA
HighwayFM 462
From0.1 MI NORTH OF CR 532
To0.4 MI SOUTH OF CR 540
CSJ0848-01-041
Proj IDSTP 1702(427)
Work TypeGR, BASE, SURF, PVMT MRKINGS
 
2.8172846962.56393491.4113.8
Work Order07-20-17
Work Began08-28-17
Work Completed
Time Computed08-19-17
Contract Working Days198
Addl Days Granted0
Working Days Charged29
Percent Time Used14
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0848-01-041
D.I.J. CONSTRUCTION, INC (1.74)
LONE STAR EROSION CONTROL (6.70)
ROADWAY SPECIALTIES, INC. (3.71)
AREA WIDE PROTECTIVE, INC. (0.93)
Contract #06173040
Totals2846962.56383349.88393491.4113.8

CountyECTOR
HighwayVA
FromON IH 10 IN PECOS COUNTY
To.
CSJ0906-00-180
Proj IDNH 2017(558)
Work TypeINSTALL DMS
 
0.001112682.1117094.5015.1
CountyTOM GREEN
HighwayVA
FromON IH 10 FROM KIMBLE/KERR CO LINE
ToTO CROCKETT/PECOS COUNTY LINE
CSJ0907-00-183
Proj IDNH 2017(558)
Work TypeINSTALL DMS
 
0.001683074.05210990.5930.8
CountyBEXAR
HighwayVA
FromON IH 10 FROM CITY OF BOERNE
ToKIMBLE/KERR COUNTY LINE
CSJ0915-00-194
Proj IDNH 2017(558)
Work TypeINSTALL DMS
 
0.001960828.161032785.1199.9
Work Order03-15-17
Work Began00-00-00
Work Completed
Time Computed04-14-17
Contract Working Days123
Addl Days Granted6
Working Days Charged71
Percent Time Used55
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0906-00-180
E&E GROUP INC., DBA LIGHT IT UP ELECTRIC (10.81)
JCD CONSTRUCTION, LLC (2.68)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (13.71)
FLASHER EQUIPMENT COMPANY (1.13)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.36)
Contract #02173235
Totals1756584.32236932.561260870.2071.7

page 1 | page 2 | page 3 | page 4 | page 5 | page 6