Monthly State Let Construction Report For San Antonio District As Of Feb 09, 2018 Page 3 Of 6

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyKERR
HighwaySH 27
FromFM 1350
ToSPUR 100
CSJ0142-05-080
Proj IDSTP 2013(719)
Work TypeWIDEN RDWY PASS LANES & OP IMPROV
 
9.0368690979.580.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days261
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0142-05-080
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183002
Totals8690979.580.000.000.0

CountyKENDALL
HighwayRM 473
From2.464 MI W OF US 281
To2.04 MI W OF US 281
CSJ0142-10-024
Proj IDSTP 2018(070)HESG
Work TypeCHEVRONS & PAVEMENT MARKINGS
 
0.42417307.320.000.0
CountyGUADALUPE
HighwaySH 123
FromSH 46
To0.1 MI N OF FM 1681
CSJ0366-03-067
Proj IDSTP 2018(071)HESG
Work TypePAVEMENT MARKINGS
 
9.929146084.510.000.0
CountyCOMAL
HighwayFM 3424
FromRM 32
ToFM 306
CSJ1728-01-007
Proj IDSTP 2018(072)HESG
Work TypePAVEMENT MARKINGS
 
1.35820665.820.000.0
Work Order11-10-17
Work Began00-00-00
Work Completed
Time Computed12-10-17
Contract Working Days59
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0142-10-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09173015
Totals184057.650.000.000.0

CountyKERR
HighwayIH 10
From1.3 MI FROM KERR/GILLESPIE C/L
To0.4 MI EAST OF SH 16
CSJ0142-14-061
Proj IDNH 2018(501)
Work TypeSURFACE & PAVEMENT MARKINGS
 
7.8794379478.030.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0142-14-061
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183221
Totals4379478.030.000.000.0

CountyKERR
HighwayIH 10
From0.7 MILES WEST OF FM 783
To0.3 MI EAST OF FM 783
CSJ0142-14-062
Proj IDNH 1602(227)
Work TypeGRAD, BASE, SURFACE, PVMT MARKINGS
 
1.0002211020.102481466.1599.9
Work Order11-15-16
Work Began04-24-17
Work Completed
Time Computed12-15-16
Contract Working Days87
Addl Days Granted0
Working Days Charged95
Percent Time Used109
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0142-14-062
ROADWAY SPECIALTIES, INC. (4.98)
PRIMATE CONSTRUCTION, INC. (4.94)
FLASHER EQUIPMENT COMPANY (3.09)
F & W ELECTRICAL CONTRACTORS, INC. (0.68)
WEST TEXAS RUMBLE STRIP (0.20)
Contract #09163226
Totals2211020.1018733.492481466.1599.9

CountyWILSON
HighwayUS 87
From2.5 MI N OF FM 539
ToFM 539
CSJ0143-03-044
Proj IDNH 2018(530)
Work TypeGR, BASE, SURF, PVMT MRKINGS
 
2.5172913595.440.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days103
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0143-03-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183206
Totals2913595.440.000.000.0

CountyWILSON
HighwayUS 87
From0.5 MI EAST OF FM 538
ToWILSON/GONZALES COUNTY LINE
CSJ0143-05-032
Proj IDSTP 2017(035)
Work TypeGRAD, BSE, SURF, PAVMT MRK
 
8.9709551891.669664836.0599.9
Work Order11-01-16
Work Began01-16-17
Work Completed
Time Computed12-01-16
Contract Working Days138
Addl Days Granted0
Working Days Charged138
Percent Time Used100
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0143-05-032
FLASHER EQUIPMENT COMPANY (2.11)
WEST TEXAS RUMBLE STRIP (0.13)
ROADWAY SPECIALTIES, INC. (2.39)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.29)
CLAUDIA SERNA DBA SERNA"S TRUCKING (0.46)
Contract #09163002
Totals9551891.66113.759664836.0599.9

CountyCOMAL
HighwaySH 46
From0.2 MI W OF FM 3009
To0.2 MI E OF FM 3009
CSJ0215-01-043
Proj IDSTP 2018(074)HES
Work TypeGRAD, BASE, SURF & SAFETY TREAT
 
0.400431702.120.000.0
CountyCOMAL
HighwaySH 46
FromAT FM 3009
To.
CSJ0215-01-046
Proj IDSTP 2018(075)HESG
Work TypeSIGNALS, SIGNS, ILLUMINATION
 
0.400141803.700.000.0
CountyCOMAL
HighwaySH 46
From0.3 MI W OF PR 31
To0.1 MI W OF PR 31
CSJ0215-07-026
Proj IDSTP 2018(076)HESG
Work TypeGRAD, SURF, BASE & PAVEMENT MRKINGS
 
0.200108424.480.000.0
Work Order11-15-17
Work Began00-00-00
Work Completed
Time Computed12-15-17
Contract Working Days73
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0215-01-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10173020
Totals681930.300.000.000.0

CountyCOMAL
HighwayBS 46-C
FromIN THE CITY OF NEW BRAUNFELS
To.
CSJ0215-02-056
Proj IDSTP 2014(112)TE
Work TypeGRAD, BSE,SURF, SIDEWALK, SIGN
 
0.661796382.00827451.4499.9
CountyCOMAL
HighwayBS 46-C
FromIN THE CITY OF NEW BRAUNFELS
To.
CSJ0215-02-058
Proj IDROW 215-2-58
Work TypeUTILITY ADJUSTMENTS
 
0.66155799.0010250.0018.3
Work Order12-28-16
Work Began02-01-17
Work Completed
Time Computed09-09-16
Contract Working Days129
Addl Days Granted25
Working Days Charged122
Percent Time Used79
Contractor(s)
MAC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0215-02-056
AUSTIN MATERIALS, LLC (16.80)
E-Z BEL CONSTRUCTION, LLC (9.12)
FLASHER EQUIPMENT COMPANY (4.35)
FUQUAY, INC. (0.86)
Contract #08163216
Totals852181.000.00837701.4498.3

CountyKENDALL
HighwaySH 46
FromUS 87
ToKENDALL / COMAL COUNTY LINE
CSJ0215-06-037
Proj IDSTP 1602(548)
Work TypeGRAD, BSE, STR, SURF, PAV'T MRK
 
3.9055575747.694398911.4878.8
CountyCOMAL
HighwaySH 46
FromCOMAL / KENDALL COUNTY LINE
ToUS 281
CSJ0215-07-022
Proj IDSTP 1602(548)
Work TypeGRAD, BSE, STR, SURF, PAV'T MRK
 
2.0503394595.791868763.0255.0
Work Order10-06-16
Work Began11-07-16
Work Completed
Time Computed11-05-16
Contract Working Days413
Addl Days Granted0
Working Days Charged278
Percent Time Used67
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0215-06-037
MPB, INC. (13.64)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (11.20)
FLASHER EQUIPMENT COMPANY (3.20)
ROADWAY SPECIALTIES, INC. (2.33)
THE LEVY COMPANY, L.P. (0.55)
EGGEMEYER LAND CLEARING, LLC (0.57)
AWP, INC. DBA AREA WIDE PROTECTIVE (0.02)
Contract #08163008
Totals8970343.48205044.026267674.5069.8

CountyCOMAL
HighwaySL 337
FromSH 46, SOUTHERLY
ToIH 35
CSJ0216-01-036
Proj IDSTP 1702(434)
Work TypeGR, STRS, BASE & SURF
 
2.99718902660.073841577.4220.3
CountyCOMAL
HighwaySL 337
FromRIVER ROAD
ToHILLCREST DRIVE
CSJ0216-01-054
Proj IDSTP 1702(435)MM
Work TypeGR, BASE, SURF, PVMT MRK, SGNS, STR
 
1.43112457946.031628383.0913.0
CountyCOMAL
HighwaySL 337
FromRIVER ROAD
ToSH 46
CSJ0216-01-055
Proj IDNH 1702(436)
Work TypeGR,BASE,STRS, SURF
 
2.23010947785.371308815.1011.9
Work Order09-27-17
Work Began10-23-17
Work Completed
Time Computed10-27-17
Contract Working Days1,239
Addl Days Granted0
Working Days Charged74
Percent Time Used5
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0216-01-036
HOSS LAND SERVICE (0.23)
LONE STAR EROSION CONTROL (2.44)
INTERSTATE BARRICADES & MARKINGS, INC. (0.30)
VOGES DRILLING CO. (2.77)
A R DANIEL CONSTRUCTION SERVICES, INC. (0.75)
CHEROKEE SERVICES (0.36)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.20)
H. L. CHAPMAN PIPELINE CONSTRUCTION, INC. (1.98)
HILL COUNTRY BRIDGE, INC (2.46)
GK CONSTRUCTION, LLC (0.41)
HOUSTON SAWING & DRILLING (0.03)
OSCAR ORDUNO, INC. (1.65)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.41)
THE LEVY COMPANY, L.P. (4.91)
FLASHER EQUIPMENT COMPANY (1.01)
R K STEPHENS CONSTRUCTION, LLC (2.21)
ROADWAY SPECIALTIES, INC. (1.07)
SOUTH TEXAS PAINTING COMPANY (0.08)
PIPE WHOLESALERS OF TEXAS, INC. (1.19)
Contract #07173003
Totals42308391.472945737.716778775.6116.0

CountyCOMAL
HighwaySH 46
FromIH 35
ToGUADALUPE/COMAL COUNTY LINE
CSJ0216-01-051
Proj IDSTP 2017(591)
Work TypeGRAD, BSE, SURF, PAVMT MRK
 
1.0091167074.681216278.2899.9
CountyGUADALUPE
HighwaySH 46
FromCOMAL COUNTY LINE
ToFM 758
CSJ0216-02-058
Proj IDSTP 2017(591)
Work TypeGRAD, BSE, SURF, PAVMT MRK
 
1.6491844522.931910781.7899.9
Work Order03-16-17
Work Began04-28-17
Work Completed
Time Computed04-17-17
Contract Working Days122
Addl Days Granted0
Working Days Charged124
Percent Time Used101
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0216-01-051
TRP CONSTRUCTION GROUP, LLC (1.24)
K.L. DURHAM CONSTRUCTION, LLC (4.09)
E-Z BEL CONSTRUCTION, LLC (6.39)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.79)
ROADWAY SPECIALTIES, INC. (2.13)
AWP, INC. (1.13)
Contract #02173218
Totals3011597.6173089.163127060.0699.9

CountyCOMAL
HighwayUS 281
FromSB MAINLANE @ GUADALUPE RIVER
To.
CSJ0253-03-067
Proj IDBR 1702(038)
Work TypeGRAD,BSE,STRUCTURE,SURF,CLN & PAINT
 
0.1723271173.60186893.035.7
Work Order06-14-17
Work Began08-07-17
Work Completed
Time Computed07-14-17
Contract Working Days304
Addl Days Granted0
Working Days Charged32
Percent Time Used10
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0253-03-067
S&S BRIDGE PAINTING (39.67)
FLASHER EQUIPMENT COMPANY (0.94)
AUSTIN MATERIALS, LLC (4.28)
Contract #05173036
Totals3271173.609250.00186893.035.7

CountyBEXAR
HighwayUS 281
FromLP 1604
To0.8 MI.NORTH OF STONE OAK
CSJ0253-04-146
Proj IDNH 2017(592)
Work TypeGR, STRS, BASE, SIGN, DELIN & PAV
 
3.778179542332.7141095972.9522.8
CountyBEXAR
HighwayUS 281
FromLP 1604
To0.8 MI.NORTH OF STONE OAK
CSJ0253-04-151
Proj IDSTP 1602(378)
Work TypeROW ACQUISITION
 
3.57712759009.884385825.7234.3
Work Order03-15-17
Work Began08-01-17
Work Completed
Time Computed04-14-17
Contract Working Days1,077
Addl Days Granted0
Working Days Charged134
Percent Time Used12
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0253-04-146
FLASHER EQUIPMENT COMPANY (0.58)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.60)
LONE STAR EROSION CONTROL (0.59)
ROYAL VISTA INC. (4.54)
W. W. FOUNDATION DRILLING, LTD. (1.75)
WEBBER BARRIER SERVICES, LLC. (1.70)
H. L. CHAPMAN PIPELINE CONSTRUCTION, INC. (1.99)
EARTH REINFORCEMENTS LLC (0.95)
LONE STAR PAVING (7.22)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.17)
HOUSTON SAWING & DRILLING (0.03)
THE LEVY COMPANY, L.P. (5.61)
(USE 26300)BRADCO, LLC (2.06)
GEOSOURCE, INC. (0.05)
GK CONSTRUCTION, LLC (0.09)
HOSS LAND SERVICES LLC (0.01)
E&E GROUP INC., DBA LIGHT IT UP ELECTRIC (0.01)
CP REBAR AND PT INSTALLATION (0.87)
JPC CONSTRUCTION INC DBA JC COMMUNICATIONS (1.25)
DU MOR ENTERPRISES (0.50)
TEXAS HIGHWAY WALLS (0.75)
INDUS ROAD & BRIDGE, INC (2.29)
FUQUAY, INC. (1.18)
H. L. CHAPMAN PIPELINE CONSTRUCTION, INC. (0.17)
DAKOTA UTILITY CONTRACTORS, INC. (0.15)
H. L. CHAPMAN PIPELINE CONSTRUCTION, INC. (0.11)
JPC CONSTRUCTION INC DBA JC COMMUNICATIONS (0.10)
SUPERIOR PUMP SOLUTIONS LLC (0.02)
Contract #02173001
Totals192301342.594680450.0145481798.6723.6

CountyBANDERA
HighwaySH 16
FromKERR COUNTY LINE
ToFM 2107
CSJ0291-04-024
Proj IDSTP 2015(933)HES
Work TypeGR, BASE, SURF & PAVMT MARKINGS
 
5.6702553976.462358800.0993.6
CountyBANDERA
HighwaySH 16
FromKERR COUNTY LINE
To0.6 MI S OF MESA VERDE ROAD
CSJ0291-04-025
Proj IDSTP 2015(934)HES
Work TypeGRS, BSE, SURF, STR, MBGF
 
2.700530989.38476053.7989.6
CountyBANDERA
HighwaySH 16
From0.2 MI WEST OF WINANS CROSSING
To2.8 MI EAST OF FM 470
CSJ0291-05-046
Proj IDSTP 2015(935)HES
Work TypeSTR, MBFG, GR,BASE, SURF & PVMT_MRK
 
6.0301760096.081619957.6992.0
Work Order06-11-15
Work Began10-01-15
Work Completed
Time Computed09-10-15
Contract Working Days442
Addl Days Granted33
Working Days Charged444
Percent Time Used108
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0291-04-024
RELMCO, INC. (28.06)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (10.94)
FLASHER EQUIPMENT COMPANY (4.11)
FUQUAY, INC. (3.91)
M.V. HENKE ENTERPRISES, INC. (1.67)
GEOSOURCE, INC. (1.36)
MURRAY CONSTRUCTION (2.00)
VOGES DRILLING CO. (0.60)
Contract #04153203
Totals4845061.92113761.204454811.5792.6

CountyWILSON
HighwaySH 97
FromUS 181
ToUS 87
CSJ0328-01-014
Proj IDSTP 1502(611)
Work TypeGRADE, BASE, SC, SURF, PAVMT MRK
 
10.61317618829.4614817177.8484.0
Work Order11-04-15
Work Began06-13-16
Work Completed
Time Computed01-04-16
Contract Working Days455
Addl Days Granted0
Working Days Charged380
Percent Time Used83
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0328-01-014
INTERSTATE BARRICADES & MARKINGS, INC. (2.37)
MURRAY CONSTRUCTION (0.22)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.40)
ROADWAY SPECIALTIES, INC. (3.27)
CATO ELECTRIC COMPANY (0.14)
E-Z BEL CONSTRUCTION, LLC (0.54)
AUSTIN WOOD RECYCLING (0.67)
Contract #08153006
Totals17618829.4628099.0514817177.8484.0

CountyWILSON
HighwaySH 97
FromATASCOSA COUNTY LINE
ToLP 181
CSJ0328-02-043
Proj IDSTP 2017(476)
Work TypeGRADE, BASE, SURF, PAVMT MRK
 
12.72818593935.6912135212.4265.2
Work Order02-22-17
Work Began04-07-17
Work Completed
Time Computed03-24-17
Contract Working Days586
Addl Days Granted0
Working Days Charged204
Percent Time Used34
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0328-02-043
MV HENKE COMPANY, LLC (0.34)
RELMCO, INC. (5.70)
THE LEVY COMPANY, L.P. (0.89)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.02)
MPB, INC. (0.47)
GEOSOURCE, INC. (0.93)
FUQUAY, INC. (1.10)
FLASHER EQUIPMENT COMPANY (2.07)
Contract #01173201
Totals18593935.691172734.2612135212.4265.2

CountyATASCOSA
HighwaySH 97
FromUS 281
ToIH 37
CSJ0328-03-035
Proj IDSTP 1702(669)
Work TypeGRD, BSE, SURF, PAV'T MRK
 
3.5328575353.091573249.7918.3
Work Order09-18-17
Work Began10-18-17
Work Completed
Time Computed10-18-17
Contract Working Days308
Addl Days Granted0
Working Days Charged63
Percent Time Used20
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0328-03-035
LONE STAR EROSION CONTROL (1.35)
FLASHER EQUIPMENT COMPANY (0.45)
E-Z BEL CONSTRUCTION, LLC (2.42)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.92)
CHEROKEE SERVICES (0.59)
ROADWAY CONSTRUCTION, LLC (1.61)
MURRAY CONSTRUCTION (0.83)
GEOSOURCE, INC. (0.43)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.06)
Contract #08173206
Totals8575353.09395330.021573249.7918.3

CountyATASCOSA
HighwaySH 97
From0.6 MILES EAST OF BURNETT AVE
ToSH 16
CSJ0328-05-037
Proj IDSTP 1502(166)
Work TypeGRADE, BASE, SC, SURF, PAVMT MRK
 
9.83717494208.2411751518.9368.8
Work Order07-07-15
Work Began09-08-15
Work Completed
Time Computed09-08-15
Contract Working Days339
Addl Days Granted8
Working Days Charged569
Percent Time Used163
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0328-05-037
LONE STAR EROSION CONTROL (1.05)
ALTUS TRAFFIC MANAGEMENT LLC (0.14)
RELMCO, INC. (2.27)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.14)
INTERSTATE BARRICADES & MARKINGS, INC. (1.62)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.53)
CUATRO T CONSTRUCTION, INC. (17.91)
THE LEVY COMPANY, L.P. (0.39)
CENTRAL ELITE TRANSPORT, LLC (0.18)
GULLEY TRUCKING (0.00)
K-BAR SERVICES, INC. (0.00)
CLARK CONSTRUCTION OF TEXAS, INC. (1.78)
Contract #05153007
Totals17494208.24395949.6811751518.9368.8

CountyATASCOSA
HighwaySH 97
FromFM 140
To0.6 MILES EAST OF BURNETT AVE
CSJ0328-05-044
Proj IDSTP 1502(612)
Work TypeGRADE, BASE, SC, SURF, PAVMT MRK
 
0.9571760591.97832185.7654.2
CountyATASCOSA
HighwaySH 97
From9.0 MI NORTH OF MCMULLEN C/L
ToFM 140
CSJ0328-06-027
Proj IDSTP 1502(612)
Work TypeGRADE, BASE, SC, SURF, PVMT MRK
 
6.84810776872.667209044.1266.8
Work Order10-30-15
Work Began01-14-16
Work Completed
Time Computed12-29-15
Contract Working Days417
Addl Days Granted0
Working Days Charged513
Percent Time Used123
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0328-05-044
B & B HIGHWAY SERVICES (0.18)
CHEROKEE SERVICES (0.34)
CUATRO T CONSTRUCTION, INC. (10.95)
D & S TEXAS ICON CONSTRUCTION, LLC. (0.07)
INTERSTATE BARRICADES & MARKINGS, INC. (0.39)
THE LEVY COMPANY, L.P. (0.18)
LONE STAR EROSION CONTROL (1.64)
RELMCO, INC. (2.54)
ROADWAY SPECIALTIES, INC. (1.92)
FLASHER EQUIPMENT COMPANY (2.07)
K-BAR SERVICES, INC. (0.02)
Contract #08153208
Totals12537464.6375139.358041229.8865.1

CountyATASCOSA
HighwaySH 97
FromMCMULLEN/ATASCOSA C/L
To2.0 MI N. OF MCMULLEN/ATASCOSA C/L
CSJ0328-06-028
Proj IDSTP 1402(065)
Work TypeGRADE, BASE, SC, SURF, PVMT MRK
 
2.5593835534.674522453.3099.9
CountyMCMULLEN
HighwaySH 97
FromLASALLE/MCMULLEN C/L
ToATASCOSA/MCMULLEN C/L
CSJ0328-07-016
Proj IDSTP 1402(065)
Work TypeGRADE, BASE, SC, SURF, PAVMT MRK
 
10.34014856569.6916085512.7999.9
Work Order10-17-14
Work Began11-10-14
Work Completed
Time Computed11-10-14
Contract Working Days331
Addl Days Granted88
Working Days Charged474
Percent Time Used113
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0328-06-028
N-LINE TRAFFIC MAINTENANCE, L.P. (0.49)
LONE STAR EROSION CONTROL (3.08)
F & W ELECTRICAL CONTRACTORS, INC. (0.22)
FLASHER EQUIPMENT COMPANY (1.61)
LONE STAR PAVING (37.44)
TRINITY EAGLEFORD SERVICES LLC (1.21)
GEOSOURCE, INC. (0.99)
CUATRO T CONSTRUCTION, INC. (11.10)
Contract #08143004
Totals18692104.360.0020607966.0999.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6