Monthly State Let Construction Report For Paris District As Of Jan 10, 2018 Page 3 Of 3

Last Update: Wednesday, January 10, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyGRAYSON
HighwayFM 121
FromAT WEST FORK OF PILOT GROVE CREEK
To.
CSJ0729-02-026
Proj IDBR 1502(261)
Work TypeREPLACE BRIDGE
 
0.1931590415.601559425.4998.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-30-15
Work Began10-20-15
Work Completed
Time Computed08-31-15
Contract Working Days234
Addl Days Granted0
Working Days Charged243
Percent Time Used103
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0729-02-026
ALTUS TRAFFIC MANAGEMENT LLC (1.30)
STRIPE-A-ZONE, INC. (1.56)
ODUM SERVICES, L.P. (2.63)
PENHALL COMPANY (0.22)
FOUNDATION DRILLERS, INC. (3.38)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.36)
W. W. FOUNDATION DRILLING, LTD. (4.13)
MOORE CONSTRUCTION, INC. (1.83)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (2.35)
Contract #06153031
Totals1590415.600.001559425.4998.4

CountyHOPKINS
HighwayFM 1870
FromSH 11
ToCR 2309
CSJ0735-05-017
Proj IDSTP 2016(101)
Work TypeREHABILITATION OF EXISTING ROAD
 
3.8151161897.121135191.0797.7
CountyHOPKINS
HighwayFM 1870
FromSH 11
ToCR 2309
CSJ0735-05-020
Proj IDSTP 2016(102)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
3.819542959.77519647.3395.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-29-16
Work Began03-28-16
Work Completed
Time Computed03-29-16
Contract Working Days120
Addl Days Granted0
Working Days Charged120
Percent Time Used100
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0735-05-017
N-LINE TRAFFIC MAINTENANCE, L.P. (0.64)
MOORE CONSTRUCTION, INC. (3.73)
STRIPING TECHNOLOGY, L.P. (2.49)
CATACON, INC. (1.45)
SCOTT PAVING, INC. (24.79)
SAMMY G. SMALLWOOD (1.27)
STRIPING SYSTEMS, INC. (0.05)
Contract #09153218
Totals1704856.890.001654838.4097.0

CountyHUNT
HighwayFM 272
FromUS 69
ToFM 816
CSJ0764-02-011
Proj IDC 764-2-11
Work TypeREHABILITATION OF EXISTING ROAD
 
6.0883455817.183604999.8699.9
Work Order09-20-16
Work Began10-07-16
Work Completed
Time Computed10-20-16
Contract Working Days202
Addl Days Granted0
Working Days Charged200
Percent Time Used99
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0764-02-011
N-LINE TRAFFIC MAINTENANCE, L.P. (0.50)
STRIPING TECHNOLOGY, L.P. (1.47)
CATOCON, INC. (2.46)
MOORE CONSTRUCTION, INC. (3.34)
SAMMY SMALLWOOD COMPANY (4.09)
BAHENA CONSTRUCTION CO.,INC. (8.01)
MURRAY CONSTRUCTION (1.38)
DUSTROL, INC. (0.33)
Contract #07163021
Totals3455817.1857137.353604999.8699.9

CountyLAMAR
HighwayFM 906
FromCR 45030
ToCR 47400
CSJ0769-02-028
Proj IDSTP 2016(189)
Work TypeREHABILITATION OF EXISTING ROAD
 
10.6554368067.413068489.9070.2
CountyLAMAR
HighwayFM 906
FromFM 197
ToUS 271
CSJ0769-02-030
Proj IDSTP 2016(190)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
4.4541549596.881046894.8767.5
Work Order06-23-16
Work Began09-21-16
Work Completed
Time Computed07-25-16
Contract Working Days345
Addl Days Granted4
Working Days Charged259
Percent Time Used74
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0769-02-028
BAHENA CONSTRUCTION CO.,INC. (8.62)
DUSTIN ALLEN, INC. (6.76)
MOORE CONSTRUCTION, INC. (1.89)
RK HALL, LLC (13.87)
STRIPING TECHNOLOGY, L.P. (2.46)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.82)
WITHERS CONSTRUCTION, LLC (2.12)
LYON BARRICADE AND CONSTRUCTION CO. (0.56)
TEXOP CONSTRUCTION (1.52)
SAMMY GIST ENTERPRISES, INC. (0.31)
Contract #01163215
Totals5917664.29187084.984115384.7769.5

CountyRED RIVER
HighwayFM 412
FromFM 1487
ToFM 44
CSJ0773-01-018
Proj IDSTP 1602(357)
Work TypeREHABILITATION OF EXISTING ROAD
 
5.3782784332.412749797.7998.7
CountyRED RIVER
HighwayFM 412
From0.97 MI SW OF INTERSECTION FM 44
To.
CSJ0773-01-019
Proj IDER 2016(876)
Work TypeMISCELLANEOUS CONSTRUCTION
 
0.092100550.00100750.0099.9
Work Order09-15-16
Work Began10-11-16
Work Completed
Time Computed10-20-16
Contract Working Days162
Addl Days Granted16
Working Days Charged173
Percent Time Used97
Contractor(s)
SAMMY GIST ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0773-01-018
CHEROKEE SERVICES (0.29)
DUSTIN ALLEN, INC. (4.73)
HIGHWAY 19 CONSTRUCTION, LLC (12.35)
MOORE CONSTRUCTION, INC. (4.07)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.41)
TOTAL HIGHWAY MAINTENANCE, LLC (1.88)
WITHERS CONSTRUCTION, LLC (2.74)
SAMMY SMALLWOOD COMPANY (0.79)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.86)
SOUTHERN CROSS CONTRACTORS, LLC (0.79)
Contract #07163027
Totals2884882.4179305.152850547.7998.8

CountyGRAYSON
HighwayCR
FromCR 202-2
ToAT ELBA CREEK
CSJ0901-19-182
Proj IDBR 2016(436)
Work TypeBRIDGE REPLACEMENT
 
0.197931194.17921195.1798.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-08-16
Work Began09-09-16
Work Completed
Time Computed09-07-16
Contract Working Days125
Addl Days Granted0
Working Days Charged126
Percent Time Used100
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0901-19-182
TOTAL HIGHWAY MAINTENANCE, LLC (0.67)
PENHALL COMPANY (0.64)
WOLFE CONSTRUCTION GROUP, INC. (0.46)
W. W. FOUNDATION DRILLING, LTD. (6.78)
ODUM SERVICES, L.P. (5.31)
Contract #06163029
Totals931194.170.00921195.1798.9

CountyRED RIVER
HighwayVA
FromLAMAR COUNTY LINE (CR2113)
ToFM 2120
CSJ0901-27-048
Proj IDSTP 2017(408)TAPS
Work TypeTAP PROJECT
 
9.070519916.510.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days133
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SAMMY GIST ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0901-27-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173016
Totals519916.510.000.000.0

CountyLAMAR
HighwayCR
FromAT CANE CREEK
ToCR 510-1
CSJ0901-29-065
Proj IDBR 2014(599)
Work TypeBRIDGE REPLACEMENT
 
0.136656785.40618528.0095.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-09-15
Work Began11-06-15
Work Completed
Time Computed10-09-15
Contract Working Days209
Addl Days Granted0
Working Days Charged228
Percent Time Used109
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0901-29-065
MOORE CONSTRUCTION, INC. (1.18)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (8.12)
SAMMY SMALLWOOD COMPANY (6.83)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.45)
Contract #07153047
Totals656785.400.00618528.0095.9

CountyLAMAR
HighwayCR
FromCR 430-1
ToAT BIG SANDY CREEK
CSJ0901-29-084
Proj IDBR 2016(888)
Work TypeBRIDGE REPLACEMENT
 
0.145724233.90729052.2099.9
Work Order11-22-16
Work Began01-06-17
Work Completed
Time Computed12-22-16
Contract Working Days213
Addl Days Granted0
Working Days Charged174
Percent Time Used81
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0901-29-084
TOTAL HIGHWAY MAINTENANCE, LLC (1.14)
COMEN ENTERPRISE LLC (5.40)
WOLFE CONSTRUCTION GROUP, INC. (1.19)
Contract #10163222
Totals724233.9011643.00729052.2099.9

CountyLAMAR
HighwayVA
From0.142 MI S OF US 82 (BOIS D'ARC ST)
ToRED RIVER COUNTY LINE (RRCR 2113)
CSJ0901-29-087
Proj IDSTP 2017(413)TAPS
Work TypeTAP PROJECT
 
12.280679839.401000.000.1
Work Order10-16-17
Work Began12-18-17
Work Completed
Time Computed11-15-17
Contract Working Days344
Addl Days Granted0
Working Days Charged12
Percent Time Used3
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0901-29-087
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09173023
Totals679839.401000.001000.000.1

CountyFANNIN
HighwayFM 1550
FromSH 34
ToFM 824
CSJ1482-02-019
Proj IDC 1482-2-19
Work TypeREHABILITATION OF EXISTING ROAD
 
4.8753303723.032156257.4765.2
Work Order04-24-17
Work Began05-25-17
Work Completed
Time Computed05-24-17
Contract Working Days179
Addl Days Granted0
Working Days Charged120
Percent Time Used67
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 1482-02-019
MOORE CONSTRUCTION, INC. (2.14)
DUSTIN ALLEN, INC. (3.48)
SOUTHERN CROSS CONTRACTORS, LLC (0.26)
TOTAL HIGHWAY MAINTENANCE, LLC (0.54)
CATOCON, INC. (7.09)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.94)
STRIPING TECHNOLOGY, L.P. (1.48)
STRIPING SYSTEMS, INC. (0.00)
Contract #03173025
Totals3303723.03419148.302156257.4765.2

CountyHUNT
HighwayFM 1569
From3.316 MILES WEST OF US 69
ToUS 69
CSJ1493-01-017
Proj IDSTP 2018(280)
Work TypeREHABILITATION OF EXISTING ROAD
 
6.3773081938.390.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-08-17
Work Began00-00-00
Work Completed
Time Computed01-08-18
Contract Working Days165
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1493-01-017
ANCHOR CONTRACTING, LLC (0.23)
MARCOM"S MOWING SERVICE, LLC (1.42)
LYON BARRICADE AND CONSTRUCTION CO. (0.65)
CATOCON, INC. (2.67)
BAHENA CONSTRUCTION CO.,INC. (15.62)
DUSTIN ALLEN, INC. (1.19)
J. H. ODEN CONTRACTING COMPANY (4.77)
TRP CONSTRUCTION GROUP, LLC (1.26)
Contract #11173014
Totals3081938.390.000.000.0

CountyFANNIN
HighwayFM 1752
FromSH 56
To0.13 MI SOUTH OF US 82
CSJ1708-01-013
Proj IDSTP 2018(372)
Work TypeREHABILITATION OF EXISTING ROAD
 
1.093612686.330.000.0
CountyFANNIN
HighwayFM 1752
FromSH 56
ToFM 898
CSJ1708-02-012
Proj IDC 1708-2-12
Work TypeREHABILITATION OF EXISTING ROAD
 
6.2994231025.330.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days250
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 1708-01-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173212
Totals4843711.660.000.000.0

CountyFANNIN
HighwayFM 1629
FromSH 121
ToSH 78
CSJ1980-01-008
Proj IDSTP 2018(373)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
5.7341344262.920.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days112
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SAMMY GIST ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1980-01-008
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173018
Totals1344262.920.000.000.0

CountyGRAYSON
HighwaySH 11
FromUS 69
ToGRAYSON COUNTY LINE
CSJ2139-01-007
Proj IDSTP 2017(746)
Work TypeREHABILITATION OF EXISTING ROAD
 
7.6419962020.613724602.0637.3
Work Order03-16-17
Work Began04-27-17
Work Completed
Time Computed04-17-17
Contract Working Days270
Addl Days Granted0
Working Days Charged120
Percent Time Used44
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 2139-01-007
WOLFE CONSTRUCTION GROUP, INC. (0.82)
BAHENA CONSTRUCTION CO.,INC. (10.67)
ALTUS TRAFFIC MANAGEMENT LLC (0.25)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (1.09)
WITHERS CONSTRUCTION, LLC (1.95)
MORRIS COUNTY CONTRACTORS, LLC (1.54)
JM YANEZ CONSTRUCTION, INC. (4.31)
STRIPING TECHNOLOGY, L.P. (0.71)
TEXOP CONSTRUCTION (0.06)
STRIPING SYSTEMS, INC. (0.00)
Contract #02173205
Totals9962020.61590686.163724602.0637.3

CountyGRAYSON
HighwayFM 1417
FromUS 75
ToFM 691
CSJ2455-01-032
Proj IDSTP 2016(841)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
12.30919817292.16775847.853.9
Work Order08-19-16
Work Began11-27-17
Work Completed
Time Computed09-19-16
Contract Working Days424
Addl Days Granted141
Working Days Charged15
Percent Time Used5
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 2455-01-032
N-LINE TRAFFIC MAINTENANCE, L.P. (0.22)
WITHERS CONSTRUCTION, LLC (0.92)
Contract #06163004
Totals19817292.16667053.85775847.853.9

CountyHUNT
HighwaySS 1570
FromSH 66
ToUS 380
CSJ2659-02-001
Proj IDSTP 1602(136)MM
Work TypeCONSTRUCT ROADWAY
 
1.8607109675.993696294.1351.9
Work Order12-28-16
Work Began01-13-17
Work Completed
Time Computed01-27-17
Contract Working Days300
Addl Days Granted0
Working Days Charged167
Percent Time Used55
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2659-02-001
N-LINE TRAFFIC MAINTENANCE, L.P. (0.33)
TRP CONSTRUCTION GROUP, LLC (0.52)
HIGHWAY 19 CONSTRUCTION, LLC (16.54)
COMEN ENTERPRISE LLC (0.71)
CATOCON, INC. (0.14)
MOORE CONSTRUCTION, INC. (1.76)
BAHENA CONSTRUCTION CO.,INC. (8.72)
TEXOP CONSTRUCTION (0.12)
AUSTIN BRIDGE & ROAD SERVICES, LP (18.64)
BOWMAN ENGINEERING & CONSULTING, INC (0.13)
Contract #11163031
Totals7109675.9996353.723696294.1351.9

page 1 | page 2 | page 3