Monthly State Let Maintenance Report For Lufkin District As Of Apr 12, 2024 Page 1 Of 2

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHOUSTON
HighwaySH0007
FromVARIOUS ROADWAYS IN HOUSTON,
ToTRINITY AND ANGELINA MAINT SECTIONS
CSJ6395-72-001
Proj IDRMC - 639572001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0101715702.462589263.2599.9
Work Order00-00-00
Work Began05-01-22
Work Completed
Time Computed05-01-22
Contract Working Days365
Addl Days Granted365
Working Days Charged701
Percent Time Used96
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6395-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02224015
Totals1715702.46125475.792589263.2599.9

CountyNACOGDOCHES
HighwayUS0059
FromNACOGDOCHES COUNTY MAINTENANCE
ToVARIOUS LOCATIONS
CSJ6411-53-001
Proj IDRMC - 641153001
Work TypeCABLE BARRIER REPAIR
 
0.010189150.00259520.0099.9
Work Order00-00-00
Work Began10-01-22
Work Completed
Time Computed10-01-22
Contract Working Days365
Addl Days Granted365
Working Days Charged548
Percent Time Used75
Contractor(s)
AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 6411-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08224022
Totals189150.000.00259520.0099.9

CountySAN JACINTO
HighwayUS0059
FromSAN JACINTO/POLK MAINT SECTIONS
ToVARIOUS LOCATIONS
CSJ6423-86-001
Proj IDRMC - 642386001
Work TypeTRAFFIC CONTROL SERVICES
 
0.010516075.00587550.0099.9
Work Order00-00-00
Work Began01-02-23
Work Completed
Time Computed01-02-23
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
AWP SAFETY
SUBCONTRACTOR(S) FOR CCSJ: 6423-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11224012
Totals516075.000.00587550.0099.9

CountyPOLK
HighwayUS0059
FromPOLK, SAN JACINTO
ToVARIOUS LOCATIONS
CSJ6424-92-001
Proj IDRMC - 642492001
Work TypeDEBRIS REMOVAL
 
0.010220008.00225248.6899.9
Work Order00-00-00
Work Began02-01-23
Work Completed
Time Computed02-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 6424-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11224210
Totals220008.000.00225248.6899.9

CountyANGELINA
HighwayUS0059
FromANGELINA COUNTY
ToVARIOUS LOCATIONS
CSJ6429-90-001
Proj IDRMC - 642990001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010445235.00418159.8693.9
Work Order00-00-00
Work Began05-01-23
Work Completed
Time Computed05-01-23
Contract Working Days57
Addl Days Granted0
Working Days Charged41
Percent Time Used71
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6429-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02234033
Totals445235.000.00418159.8693.9

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToDISTRICTWIDE
CSJ6443-34-001
Proj IDRMC - 644334001
Work TypeTHERMOPLASTIC PAVEMENT MARKINGS
 
0.010635450.000.000.0
Work Order00-00-00
Work Began01-09-24
Work Completed
Time Computed01-09-24
Contract Working Days365
Addl Days Granted0
Working Days Charged83
Percent Time Used22
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6443-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09234028
Totals635450.000.000.000.0

CountyANGELINA
HighwayUS0059
FromANGELINA COUNTY MAINTENANCE SECTION
ToVARIOUS LOCATIONS
CSJ6444-10-001
Proj IDRMC - 644410001
Work TypeMILL AND INLAY
 
0.0101307515.431312904.6899.9
Work Order00-00-00
Work Began12-01-23
Work Completed
Time Computed12-01-23
Contract Working Days39
Addl Days Granted0
Working Days Charged19
Percent Time Used48
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6444-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234030
Totals1307515.43708942.631312904.6899.9

CountyHOUSTON
HighwaySH0019
FromHOUSTON COUNTY MAINTENANCE SECTION
ToVARIOUS LOCATIONS
CSJ6444-12-001
Proj IDRMC - 644412001
Work TypeMILL AND INLAY
 
0.0101188488.451296224.8699.9
Work Order00-00-00
Work Began01-08-24
Work Completed
Time Computed01-08-24
Contract Working Days24
Addl Days Granted0
Working Days Charged20
Percent Time Used83
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6444-12-001
STRIPING TECHNOLOGY, L.P. (0.00)
DUSTROL, INC. (0.00)
INTERSTATE BARRICADES & MARKINGS, INC. (0.00)
Contract #08234223
Totals1188488.456822.001296224.8699.9

CountyPOLK
HighwayUS0059
FromSAN JACINTO/POLK MAINT SECTIONS
ToVARIOUS LOCATIONS
CSJ6447-46-001
Proj IDRMC - 644746001
Work TypeTRAFFIC CONTROL SERVICES
 
0.010716170.00248370.0034.6
Work Order00-00-00
Work Began01-02-24
Work Completed
Time Computed01-02-24
Contract Working Days365
Addl Days Granted0
Working Days Charged91
Percent Time Used24
Contractor(s)
AWP SAFETY
SUBCONTRACTOR(S) FOR CCSJ: 6447-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10234207
Totals716170.00126579.00248370.0034.6

CountyPOLK
HighwayUS0059
FromPOLK COUNTY MAINTENANCE
ToVARIOUS LOCATIONS
CSJ6449-57-001
Proj IDRMC - 644957001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010410196.250.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days74
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6449-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01244214
Totals410196.250.000.000.0

CountySAN JACINTO
HighwayUS0059
FromSAN JACINTO COUNTY MAINTENANCE
ToVARIOUS LOCATIONS
CSJ6451-35-001
Proj IDRMC - 645135001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010183650.470.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days42
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6451-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244210
Totals183650.470.000.000.0

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6451-37-001
Proj IDRMC - 645137001
Work TypeREFLECTIVE PAVEMENT MARKINGS (LONG LINE)
 
0.010399400.000.000.0
Work Order00-00-00
Work Began01-09-24
Work Completed
Time Computed01-09-24
Contract Working Days365
Addl Days Granted0
Working Days Charged83
Percent Time Used22
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6451-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09234213
Totals399400.000.000.000.0

CountyNACOGDOCHES
HighwayUS0059
FromNACOGDOCHES COUNTY MAINTENANCE
ToVARIOUS LOCATIONS
CSJ6451-75-001
Proj IDRMC - 645175001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010272318.180.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days56
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6451-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244009
Totals272318.180.000.000.0

CountySHELBY
HighwayUS0059
FromSHELBY COUNTY
ToVARIOUS LOCATIONS
CSJ6452-61-001
Proj IDRMC - 645261001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010239608.190.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-05-24
Work Began00-00-00
Work Completed
Time Computed04-08-24
Contract Working Days50
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SERVIN MOWING
SUBCONTRACTOR(S) FOR CCSJ: 6452-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244010
Totals239608.190.000.000.0

CountyANGELINA
HighwayBU0069J
FromANG HOU & TRIN COUNTIES MAINT. YARD
ToANG HOU & TRIN COUNTIES MAINT. YARD
CSJ6453-49-001
Proj IDMMC - 645349001
Work TypeLIMESTONE ROCK ASPHALT
 
0.0101066720.00543697.3450.9
Work Order00-00-00
Work Began11-27-23
Work Completed
Time Computed11-27-23
Contract Working Days120
Addl Days Granted120
Working Days Charged126
Percent Time Used52
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6453-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10234021
Totals1066720.000.00543697.3450.9

CountySAN JACINTO
HighwayUS0059
FromPOLK, SAN JACINTO
ToVARIOUS LOCATIONS
CSJ6453-67-001
Proj IDRMC - 645367001
Work TypeDEBRIS REMOVAL
 
0.010251307.1943675.0317.3
Work Order00-00-00
Work Began02-01-24
Work Completed
Time Computed02-01-24
Contract Working Days365
Addl Days Granted0
Working Days Charged60
Percent Time Used16
Contractor(s)
AAD CONTRACTING INC.
SUBCONTRACTOR(S) FOR CCSJ: 6453-67-001
ROY LEE WALKER (0.00)
L & M MOWING CONTRACTORS, LLC (0.00)
Contract #11234023
Totals251307.1928269.9943675.0317.3

CountyANGELINA
HighwayUS0059
FromWITHIN THE LUFKIN DISTRICT
ToVARIOUS LOCATIONS
CSJ6456-17-001
Proj IDBPM - 645617001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010583220.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 6456-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234024
Totals583220.000.000.000.0

CountyPOLK
HighwayBU0059J
FromWITHIN THE LUFKIN DISTRICT
ToVARIOUS LOCATIONS
CSJ6456-19-001
Proj IDBPM - 645619001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010330272.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 6456-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234214
Totals330272.000.000.000.0

CountyHOUSTON
HighwayUS0287
FromHOUSTON COUNTY
ToVARIOUS LOCATIONS
CSJ6460-42-001
Proj IDRMC - 646042001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010274421.420.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days52
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SERVIN MOWING
SUBCONTRACTOR(S) FOR CCSJ: 6460-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01244026
Totals274421.420.000.000.0

CountyANGELINA
HighwaySH0007
FromVARIOUS ROADWAYS IN HOUSTON,
ToTRINITY AND ANGELINA MAINT SECTIONS
CSJ6462-57-001
Proj IDRMC - 646257001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0101289920.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6462-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244230
Totals1289920.000.000.000.0

page 1 | page 2