Monthly State Let Maintenance Report For Lufkin District As Of Feb 09, 2018 Page 1 Of 1

Last Update: Friday, February 09, 2018
FTP Icon
page 1

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS THROUGHOUT
ToLUFKIN AREA MAINTENANCE SECTIONS
CSJ6304-86-001
Proj IDRMC - 630486001
Work TypeON-CALL TRAFFIC CONTROL_SERVICES
 
0.010964900.0077335.008.0
Work Order02-13-17
Work Began02-21-17
Work Completed
Time Computed02-21-17
Contract Working Days365
Addl Days Granted0
Working Days Charged337
Percent Time Used92
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6304-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164220
Totals964900.000.0077335.008.0

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToWITHIN THE LUFKIN DISTRICT
CSJ6309-64-001
Proj IDBPM - 630964001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010329924.00275778.5083.5
Work Order05-09-17
Work Began05-09-17
Work Completed
Time Computed05-09-17
Contract Working Days40
Addl Days Granted5
Working Days Charged17
Percent Time Used37
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6309-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02174206
Totals329924.000.00275778.5083.5

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN ANGELINA,
ToNACOGDOCHES, AND SHELBY COUNTY MAINT SEC
CSJ6320-98-001
Proj IDRMC - 632098001
Work TypeMILL AND INLAY
 
0.100988330.50895321.7590.5
Work Order00-00-00
Work Began11-06-17
Work Completed
Time Computed11-06-17
Contract Working Days40
Addl Days Granted0
Working Days Charged21
Percent Time Used52
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6320-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08174012
Totals988330.5016794.37895321.7590.5

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS IN HOUSTON, POLK,
ToTRINITY AND SAN JACINTO MAINT. SECTIONS
CSJ6320-99-001
Proj IDRMC - 632099001
Work TypeMILL AND INLAY
 
0.1001387213.56392896.0028.3
Work Order02-05-18
Work Began01-22-18
Work Completed
Time Computed02-05-18
Contract Working Days40
Addl Days Granted0
Working Days Charged8
Percent Time Used20
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6320-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08174213
Totals1387213.56392896.00392896.0028.3

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToWITHIN THE LUFKIN DISTRICT
CSJ6324-31-001
Proj IDBPM - 632431001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010464563.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6324-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174021
Totals464563.000.000.000.0

page 1