Monthly State Let Construction Report For Lufkin District As Of Feb 09, 2018 Page 3 Of 3

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHOUSTON
HighwayCR
FromCR 1155 AT NECHES RIVER RELIEF
To.
CSJ0911-28-033
Proj IDBR 2014(435)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.070619443.50583680.3594.2
Work Order05-16-17
Work Began08-15-17
Work Completed
Time Computed08-14-17
Contract Working Days62
Addl Days Granted0
Working Days Charged50
Percent Time Used80
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-28-033
SOUTHWEST ENVIRONMENT SERVICES LLC (0.75)
DUSTIN ALLEN, INC. (4.06)
PANOLA SIGN & BARRICADE, INC. (0.70)
Contract #04173012
Totals619443.503200.00583680.3594.2

CountySHELBY
HighwayCR
FromCR 4059 AT POOR JOE CREEK
To.
CSJ0911-39-038
Proj IDBR 1602(393)
Work TypeBRIDGE REPLACEMENT
 
0.119619833.68247249.1739.8
Work Order09-05-17
Work Began10-13-17
Work Completed
Time Computed10-05-17
Contract Working Days144
Addl Days Granted0
Working Days Charged47
Percent Time Used32
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0911-39-038
HODGES AND SON CONSTRUCTION COMPANY, INC. (3.77)
AWP, INC. DBA AREA WIDE PROTECTIVE (1.71)
AMERICAN REMEDIATION OPTIONS, INC. (8.17)
Contract #07173220
Totals619833.6835198.17247249.1739.8

CountySHELBY
HighwayCR
FromCR 4789 AT TRIB OF BLACKWATER CREEK
To.
CSJ0911-39-050
Proj IDBR 1602(396)
Work TypeBRIDGE REPLACEMENT
 
0.104671325.95269212.0040.1
Work Order06-14-17
Work Began09-12-17
Work Completed
Time Computed09-12-17
Contract Working Days127
Addl Days Granted0
Working Days Charged47
Percent Time Used37
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0911-39-050
AMERICAN REMEDIATION OPTIONS, INC. (9.48)
FREDONIA CONSTRUCTION SERVICES (1.48)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.27)
AREA WIDE PROTECTIVE, INC. (0.91)
Contract #05173010
Totals671325.95900.00269212.0040.1

CountyNACOGDOCHES
HighwayFM 343
FromCHEROKEE COUNTY LINE
ToFM 225
CSJ0926-02-010
Proj IDSTP 2017(315)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
13.6881213495.601172006.5196.5
CountyNACOGDOCHES
HighwayFM 343
FromCHEROKEE COUNTY LINE
ToFM 225
CSJ0926-02-011
Proj IDSTP 2017(314)
Work TypeRECONSTRUCT AND WIDEN PAVEMENT
 
6.8443510530.023270587.8593.1
Work Order01-17-17
Work Began02-22-17
Work Completed
Time Computed02-16-17
Contract Working Days175
Addl Days Granted0
Working Days Charged144
Percent Time Used82
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0926-02-010
AMERICAN REMEDIATION OPTIONS, INC. (3.22)
A R BROTHERS CONSTRUCTION SERVICES, INC. (9.56)
COLD CREEK CONSTRUCTION, LTD (6.20)
PANOLA SIGN & BARRICADE, INC. (0.54)
STRIPING TECHNOLOGY, L.P. (2.36)
STRIPING SYSTEMS, INC. (0.03)
Contract #12163028
Totals4724025.621687.384442594.3694.0

CountyNACOGDOCHES
HighwayFM 1087
FromUS 259
ToFM 95
CSJ0926-05-008
Proj IDSTP 2017(643)HES
Work TypeSFT FIXED OBJ
 
10.916775621.06847701.0699.9
Work Order03-16-17
Work Began05-18-17
Work Completed
Time Computed04-17-17
Contract Working Days137
Addl Days Granted0
Working Days Charged128
Percent Time Used93
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0926-05-008
COLD CREEK CONSTRUCTION, LTD (1.51)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.03)
LONESTAR TRAFFIC SAFETY, LLC (0.97)
Contract #02173004
Totals775621.0624990.00847701.0699.9

CountyHOUSTON
HighwayFM 227
From0.5 MI E OF CR 1685
ToSH 21
CSJ0937-02-033
Proj IDSTP 2017(644)
Work TypeRECONSTRUCT AND WIDEN PAVEMENT
 
29.8883134729.032887650.5692.1
Work Order03-15-17
Work Began04-24-17
Work Completed
Time Computed04-24-17
Contract Working Days166
Addl Days Granted2
Working Days Charged117
Percent Time Used69
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0937-02-033
A R BROTHERS CONSTRUCTION SERVICES, INC. (19.28)
INTERSTATE BARRICADES & MARKINGS, INC. (4.89)
COLD CREEK CONSTRUCTION, LTD (7.58)
PANOLA SIGN & BARRICADE, INC. (0.70)
AMERICAN REMEDIATION OPTIONS, INC. (4.69)
USA LANDSCAPE SERVICES EAST TEAST (0.19)
Contract #02173046
Totals3134729.0320104.592887650.5692.1

CountyHOUSTON
HighwayFM 227
FromAT HICKORY CREEK
To.
CSJ0937-03-013
Proj IDBR 1502(259)
Work TypeREMOVE AND REPLACE EXISTING BRIDGE
 
0.5032633662.022616792.0799.5
Work Order07-22-15
Work Began05-11-16
Work Completed
Time Computed05-11-16
Contract Working Days161
Addl Days Granted23
Working Days Charged189
Percent Time Used102
Contractor(s)
PIERCE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0937-03-013
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.87)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.64)
DREWERY CONSTRUCTION COMPANY, INCORPORATED (4.27)
DUSTIN ALLEN, INC. (1.31)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.65)
DUSTROL, INC. (0.69)
PENHALL COMPANY (0.25)
STRIPING TECHNOLOGY, L.P. (0.68)
MESA ROD BUSTERS, INC. (0.32)
JOHN L. BILLINGSLEY LOGGING, LLC (0.94)
DAVIS MOTOR CRANE SERVICE, INC. (1.79)
B & E CONSTRUCTION INC. (0.52)
Contract #06153037
Totals2633662.027037.642616792.0799.5

CountyHOUSTON
HighwayFM 227
FromSH 21
ToSH 7
CSJ0937-03-016
Proj IDSTP 1702(636)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
26.6361576406.00650419.4641.2
Work Order09-14-17
Work Began10-10-17
Work Completed
Time Computed10-10-17
Contract Working Days223
Addl Days Granted0
Working Days Charged68
Percent Time Used30
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0937-03-016
ODUM SERVICES, L.P. (7.51)
Contract #08173016
Totals1576406.0064878.98650419.4641.2

CountySAN AUGUSTINE
HighwayFM 705
FromSH 147
To2.49 MI S OF FM 83
CSJ1079-01-031
Proj IDSTP 2015(420)HRR
Work TypeSAFETY TREAT FIXED OBJECTS
 
22.3791266570.981190050.2493.9
Work Order11-02-15
Work Began12-09-15
Work Completed
Time Computed12-02-15
Contract Working Days336
Addl Days Granted0
Working Days Charged325
Percent Time Used96
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1079-01-031
DUSTIN ALLEN, INC. (12.83)
PANOLA SIGN & BARRICADE, INC. (1.57)
Contract #09153226
Totals1266570.983212.001190050.2493.9

CountyNACOGDOCHES
HighwayFM 1275
FromAT FM 2609
To.
CSJ1407-03-016
Proj IDSTP 2017(498)HES
Work TypeIMPROVE TRAFFIC SIGNAL
 
0.400272731.70292649.4099.9
Work Order02-13-17
Work Began05-30-17
Work Completed
Time Computed05-15-17
Contract Working Days40
Addl Days Granted10
Working Days Charged48
Percent Time Used96
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 1407-03-016
CARTHAGE DRILLING, INC. (3.36)
COX CONTRACTORS, INC. (4.39)
Contract #01173253
Totals272731.700.00292649.4099.9

CountySAN AUGUSTINE
HighwayFM 711
FromSHELBY COUNTY LINE
ToUS 96
CSJ1680-01-016
Proj IDSTP 2018(428)
Work TypeRECONSTRUCT AND WIDEN PAVEMENT
 
11.3315195793.420.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days175
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1680-01-016
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183027
Totals5195793.420.000.000.0

CountySAN JACINTO
HighwayFM 1127
FromUS 59
ToEND OF PAVEMENT
CSJ1681-01-012
Proj IDSTP 2017(500)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
13.9661585479.801267839.3779.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-15-17
Work Began03-15-17
Work Completed
Time Computed03-15-17
Contract Working Days153
Addl Days Granted0
Working Days Charged132
Percent Time Used86
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 1681-01-012
ODUM SERVICES, L.P. (2.89)
PIPE WHOLESALERS OF TEXAS, INC. (8.80)
Contract #01173234
Totals1585479.800.001267839.3779.9

CountyNACOGDOCHES
HighwayFM 1878
FromAT LA NANA CREEK
To.
CSJ1810-01-032
Proj IDBR 2017(829)
Work TypeBRIDGE REPLACEMENT
 
0.1171774829.451454321.9482.6
Work Order04-24-17
Work Began05-25-17
Work Completed
Time Computed05-24-17
Contract Working Days115
Addl Days Granted0
Working Days Charged131
Percent Time Used113
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1810-01-032
PANOLA SIGN & BARRICADE, INC. (2.73)
TEX OP CONSTRUCTION, LP (0.58)
AMERICAN REMEDIATION OPTIONS, INC. (2.01)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.38)
STRIPING TECHNOLOGY, L.P. (0.52)
BOWMAN ENGINEERING & CONSULTING, INC (0.21)
FREDONIA CONSTRUCTION SERVICES (0.56)
Contract #03173037
Totals1774829.45191991.821454321.9482.6

CountyHOUSTON
HighwayFM 3151
FromFM 1280
ToFM 230
CSJ1875-03-022
Proj IDC 1875-3-22
Work TypeRECONSTRUCT AND WIDEN PAVEMENT
 
4.5903146993.472800659.5589.5
Work Order00-00-00
Work Began05-09-16
Work Completed
Time Computed04-25-16
Contract Working Days114
Addl Days Granted0
Working Days Charged131
Percent Time Used114
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1875-03-022
AMERICAN REMEDIATION OPTIONS, INC. (2.85)
DREWERY BROS TREE SERVICE, INC. (1.35)
PANOLA SIGN & BARRICADE, INC. (0.62)
STRIPING TECHNOLOGY, L.P. (2.00)
G & L FLOWERS TRUCKING (1.61)
ROCKIN" DRIVEWAYS (18.58)
FREDONIA CONSTRUCTION (0.31)
STRIPING SYSTEMS, INC. (0.04)
Contract #12153043
Totals3146993.470.002800659.5589.5

CountyTRINITY
HighwayFM 2262
FromFM 2501
ToSH 94
CSJ2387-01-017
Proj IDSTP 2017(647)
Work TypeRECONSTRUCT AND WIDEN PAVEMENT
 
14.1664311589.97711891.5016.5
Work Order11-10-17
Work Began01-08-18
Work Completed
Time Computed12-11-17
Contract Working Days129
Addl Days Granted0
Working Days Charged19
Percent Time Used14
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2387-01-017
A R BROTHERS CONSTRUCTION SERVICES, INC. (3.40)
PANOLA SIGN & BARRICADE, INC. (0.68)
STRIPING TECHNOLOGY, L.P. (2.23)
Contract #10173216
Totals4311589.97711891.50711891.5016.5

CountyPOLK
HighwayFM 1316
FromSH 146
To2.193 MI E OF SH 146
CSJ2510-01-016
Proj IDSTP 1702(120)HES
Work TypeSAFETY TREAT FIXED OJECTS
 
6.539568648.50529555.0093.1
Work Order06-14-17
Work Began07-25-17
Work Completed
Time Computed07-17-17
Contract Working Days93
Addl Days Granted2
Working Days Charged85
Percent Time Used89
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2510-01-016
PANOLA SIGN & BARRICADE, INC. (1.49)
Contract #05173235
Totals568648.5087113.00529555.0093.1

CountyANGELINA
HighwayUS 59 ETC
FromBU 59 N
ToBU 59 S
CSJ2553-01-117
Proj IDSTP 2017(650)HES
Work TypeIMPROVE GUARDRAIL TO DES STANDARDS
 
6.1661891195.251743432.2292.1
Work Order03-16-17
Work Began05-15-17
Work Completed
Time Computed05-15-17
Contract Working Days113
Addl Days Granted7
Working Days Charged110
Percent Time Used91
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2553-01-117
STRIPING TECHNOLOGY, L.P. (0.65)
LYNCO CONSTRUCTION (27.91)
Contract #02173231
Totals1891195.2517883.201743432.2292.1

CountyANGELINA
HighwayFM 1194
FromLP 287
ToFM 3150
CSJ2960-01-012
Proj IDSTP 2018(254)HES
Work TypePROVIDE ADDITIONAL PAVED SURF WIDTH
 
0.659459200.63182003.0839.6
Work Order12-04-17
Work Began01-24-18
Work Completed
Time Computed01-03-18
Contract Working Days50
Addl Days Granted0
Working Days Charged9
Percent Time Used18
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 2960-01-012
A R BROTHERS CONSTRUCTION SERVICES, INC. (7.28)
PANOLA SIGN & BARRICADE, INC. (1.24)
STRIPING TECHNOLOGY, L.P. (5.14)
MOORE BROTHERS CONSTRUCTION COMPANY (28.23)
AMERICAN REMEDIATION OPTIONS, INC. (1.20)
Contract #11173009
Totals459200.63182003.08182003.0839.6

page 1 | page 2 | page 3