Monthly State Let Construction Report For Lufkin District As Of Jan 10, 2018 Page 2 Of 4

Last Update: Wednesday, January 10, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyANGELINA
HighwayUS 59
FromANGELINA RIVER BRIDGE
To0.520 MI NORTH OF FM 2021
CSJ0176-02-120
Proj IDNH 2017(826)
Work TypeHMA LEVEL UP, OCST AND PFC SURFACE
 
2.6902865623.763144485.1499.9
Work Order04-24-17
Work Began06-19-17
Work Completed
Time Computed05-24-17
Contract Working Days77
Addl Days Granted0
Working Days Charged76
Percent Time Used98
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0176-02-120
PANOLA SIGN & BARRICADE, INC. (0.20)
CLARK CONSTRUCTION OF TEXAS, INC. (8.56)
DUSTROL, INC. (6.64)
AMERICAN REMEDIATION OPTIONS, INC. (0.44)
STRIPE-A-ZONE, INC. (1.13)
NLG CONSTRUCTION, INC. (0.49)
Contract #03173220
Totals2865623.7623703.233144485.1499.9

CountyPOLK
HighwayUS 59
FromSL 393 S
ToTRINITY RIVER
CSJ0177-01-102
Proj IDNH 2017(641)
Work TypeHMA LEVEL-UP, OCST, & PFC
 
1.9702215251.082316061.6399.9
Work Order03-16-17
Work Began05-24-17
Work Completed
Time Computed05-08-17
Contract Working Days55
Addl Days Granted15
Working Days Charged69
Percent Time Used98
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0177-01-102
AWP, INC. (0.24)
CLARK CONSTRUCTION OF TEXAS, INC. (10.11)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.42)
DUSTROL, INC. (4.89)
STRIPING TECHNOLOGY, L.P. (1.85)
CHEROKEE SERVICES (0.36)
WEST TEXAS RUMBLE STRIP (0.18)
HIGHWAY DATA SERVICES (0.05)
Contract #02173007
Totals2215251.0851816.192316061.6399.9

CountySAN JACINTO
HighwayUS 59
From1.00 MILE NORTH OF FM 2914
To1.00 MILE SOUTH OF FM 2914
CSJ0177-02-080
Proj IDSTP 1102(058)HES
Work TypeCNSTR INTRCHANGE & CLOSE CROSSOVERS
 
2.05912895988.9718253075.9699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-31-12
Work Began06-22-12
Work Completed
Time Computed04-02-12
Contract Working Days535
Addl Days Granted398
Working Days Charged933
Percent Time Used100
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0177-02-080
CRABTREE BARRICADE SYSTEMS, INC. (1.02)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.31)
MESA ROD BUSTERS, INC. (2.06)
WEBBER-BALKE FOUNDATION COMPANY, INC. (1.82)
ODUM SERVICES, L.P. (0.12)
KOSSMAN CONTRACTING CO., INC. (0.38)
ENVIRONMENTAL ALLIES, L.P. (0.09)
SCOTT DERR PAINTING CO, LLC (0.16)
TRAF-TEX, INC. (4.36)
DUSTROL, INC. (0.46)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.26)
WILLOW CITY SIGN & RAIL, INC. (0.12)
TRIPLE B SERVICES LLP (37.18)
SMITH & COMPANY (16.56)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.10)
GREY WOLF CLEARING INC. (0.52)
A & B CRUSHED CONCRETE (0.12)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.47)
SILVA, INC. (1.21)
INDUS CONSTRUCTION, L.P. (0.63)
JASSO"S SAWING & SEALING (0.36)
CURB PLANET INC. (0.08)
A-1 EROSION CONTROL, LLC (0.59)
WATERS CONSTRUCTION CO., INC. (0.31)
Contract #12113203
Totals12895988.970.0018253075.9699.9

CountySAN JACINTO
HighwayUS 59
FromJUST S OF UPRR IN SHEPHERD
ToJUST N OF FM 2914
CSJ0177-02-089
Proj IDSTP 2013(916)
Work TypeADD SB FRTG RD & RECONST MAIN LANES
 
1.6428948536.8511015660.8199.9
Work Order05-14-14
Work Began08-15-14
Work Completed
Time Computed05-30-14
Contract Working Days230
Addl Days Granted183
Working Days Charged409
Percent Time Used99
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0177-02-089
FLORIDA TRAFFIC CONTROL DEVICES, INC. (0.88)
DOUBLE OAK CONSTRUCTION, INC. (0.67)
CRABTREE BARRICADE SYSTEMS, INC. (0.91)
SMITH & COMPANY (20.62)
WILLOW CITY SIGN & RAIL, INC. (0.59)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.33)
BREDA COMPANY, INC. (0.92)
CPAVE, INC. (1.78)
ROY LEE WALKER (0.13)
THOMAS TRACTOR WORKS, INC. (0.16)
NORWEST SERVICES, LLC (0.06)
SOUTHERN CRUSHED CONCRETE LLC (0.86)
SOUTHEAST GRINDING & GROOVING, LLC (0.37)
HOUSTON SAWING & DRILLING (0.03)
DUSTROL, INC. (0.22)
TEXOP CONSTRUCTION (0.23)
WEST TX RUMBLE STRIP (0.09)
A-1 EROSION CONTROL, LLC (0.01)
Contract #02143221
Totals8948536.851412.7511015660.8199.9

CountySAN JACINTO
HighwayUS 59
From0.50 MI S OF FM 2914
ToLIBERTY COUNTY LINE
CSJ0177-02-091
Proj IDNH 2016(734)
Work TypeHMA LEVEL-UP AND PFC SURFACE
 
16.4612971066.403063773.6199.9
Work Order04-19-16
Work Began05-23-16
Work Completed
Time Computed05-23-16
Contract Working Days94
Addl Days Granted16
Working Days Charged103
Percent Time Used93
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0177-02-091
STRIPING TECHNOLOGY, L.P. (1.46)
INTERSTATE BARRICADES & MARKINGS, INC. (0.60)
COWBELL TRAFFIC SERVICES, INC. (0.39)
CLARK CONSTRUCTION OF TEXAS, INC. (9.33)
AMERICAN REMEDIATION OPTIONS, INC. (6.84)
DUSTROL, INC. (1.05)
NLG CONSTRUCTION, INC. (0.13)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.03)
WEST TX RUMBLE STRIP (0.01)
HIGHWAY DATA SERVICES (0.04)
Contract #02163033
Totals2971066.407229.503063773.6199.9

CountyANGELINA
HighwayUS 69
From0.24 MI NORTH OF FM 841
To1.235 MI S OF FM 1669
CSJ0200-01-083
Proj IDNH 2016(424)
Work TypeRESURFACE WITH THIN OVERLAY MIXTURE
 
6.5871576982.230.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days37
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0200-01-083
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173219
Totals1576982.230.000.000.0

CountyANGELINA
HighwayUS 69
FromHUNTINGTON
ToFM 844
CSJ0200-02-031
Proj IDNH 2013(513)
Work TypeGR STRS BASE & SURF
 
2.1039969131.131892660.9618.9
Work Order07-14-17
Work Began08-17-17
Work Completed
Time Computed08-14-17
Contract Working Days310
Addl Days Granted0
Working Days Charged57
Percent Time Used18
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0200-02-031
STRIPING TECHNOLOGY, L.P. (1.60)
A R BROTHERS CONSTRUCTION SERVICES, INC. (11.45)
AMERICAN REMEDIATION OPTIONS, INC. (1.33)
MOORE BROTHERS CONSTRUCTION COMPANY (31.91)
TEXAS ALTERNATIVE GRASSER, INC. (0.86)
PANOLA SIGN & BARRICADE, INC. (0.33)
DUSTROL, INC. (1.07)
STRIPING SYSTEMS, INC. (0.01)
AWP, INC. DBA AREA WIDE PROTECTIVE (0.09)
Contract #06173006
Totals9969131.13221188.221892660.9618.9

CountyANGELINA
HighwayUS 69
FromFM 844
ToZAVALLA
CSJ0200-02-042
Proj IDNH 1702(519)
Work TypeCLEARING AND GRUBBING
 
10.835890456.22356811.1740.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-23-17
Work Began10-09-17
Work Completed
Time Computed00-00-00
Contract Working Days109
Addl Days Granted0
Working Days Charged53
Percent Time Used48
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0200-02-042
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.06)
Contract #07173216
Totals890456.2294971.64356811.1740.0

CountySAN JACINTO
HighwayUS 190
FromWALKER COUNTY LINE
ToPOLK COUNTY LINE
CSJ0213-02-043
Proj IDSTP 1602(080)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
14.0372543073.002164999.1085.1
Work Order06-27-16
Work Began07-26-16
Work Completed
Time Computed07-26-16
Contract Working Days246
Addl Days Granted0
Working Days Charged241
Percent Time Used97
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0213-02-043
ODUM SERVICES, L.P. (9.53)
B-N-T SERVICES, LLC (12.07)
Contract #05163008
Totals2543073.001389.602164999.1085.1

CountyPOLK
HighwayUS 190
FromONALASKA
ToFM 2457
CSJ0213-03-097
Proj IDSTP 2013(515)
Work TypeADD PASSING LANES
 
21.94313913635.9613476217.5796.8
Work Order11-24-15
Work Began02-01-16
Work Completed
Time Computed12-24-15
Contract Working Days223
Addl Days Granted0
Working Days Charged222
Percent Time Used99
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0213-03-097
ROADSAFE TRAFFIC SYSTEMS, INC. (0.65)
WILLOW CITY SIGN & RAIL, INC. (0.48)
WATERS CONSTRUCTION CO., INC. (4.26)
TEXOP CONSTRUCTION (0.87)
TEXAS LAND CLEARING SERVICE (1.42)
LUDCO, INC. (0.21)
DUSTIN ALLEN, INC. (5.72)
COWBELL TRAFFIC SERVICES, INC. (0.14)
J & M CONTRACTING, COMPANY (20.43)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.53)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.01)
Contract #09153004
Totals13913635.961950.0013476217.5796.8

CountyTRINITY
HighwayUS 287
FromSH 94
ToHARRISON AVE IN GROVETON
CSJ0319-01-064
Proj IDSTP 2017(827)
Work TypeRECONSTRUCT EXISTING PAVEMENT
 
4.7001947390.021956241.5699.9
Work Order04-19-17
Work Began05-31-17
Work Completed
Time Computed05-22-17
Contract Working Days80
Addl Days Granted0
Working Days Charged75
Percent Time Used93
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0319-01-064
A R BROTHERS CONSTRUCTION SERVICES, INC. (9.98)
(USE 26352)AWP, INC. (1.02)
STRIPE-A-ZONE, INC. (1.05)
WEST TEXAS RUMBLE STRIP (0.29)
NIXON ENGINEERING, L.L.C. (0.07)
HOUSTON TRUCKING & PAVING CO. (0.84)
Contract #03173009
Totals1947390.020.001956241.5699.9

CountyNACOGDOCHES
HighwaySH 103
FromANGELINA COUNTY LINE
ToSAN AUGUSTINE COUNTY LINE
CSJ0336-06-028
Proj IDSTP 2018(156)HES
Work TypeIMPROVE GUARDRAIL TO DES STANDARDS
 
20.681597891.990.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-15-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days74
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0336-06-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10173013
Totals597891.990.000.000.0

CountyTRINITY
HighwayUS 287
FromHOUSTON COUNTY LINE
ToSH 94
CSJ0340-02-025
Proj IDSTP 1602(082)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
22.2511687891.221367748.5181.0
Work Order07-11-16
Work Began09-26-16
Work Completed
Time Computed08-10-16
Contract Working Days178
Addl Days Granted1
Working Days Charged144
Percent Time Used80
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0340-02-025
N-LINE TRAFFIC MAINTENANCE, L.P. (0.84)
DUSTIN ALLEN, INC. (6.67)
COLD CREEK CONSTRUCTION, LTD (7.93)
USA LANDSCAPE SERVICES EAST TEAST (1.94)
Contract #05163028
Totals1687891.220.001367748.5181.0

CountyPOLK
HighwayFM 356
From1.12 MI N OF US 190
ToUS 190
CSJ0475-11-031
Proj IDSTP 1602(273)
Work TypeGR,STR,CURB,GUTTER,BASE,SURF
 
1.0797653712.005757827.5775.2
Work Order09-15-16
Work Began11-14-16
Work Completed
Time Computed10-17-16
Contract Working Days162
Addl Days Granted25
Working Days Charged184
Percent Time Used98
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0475-11-031
CEN TEX HYDROSEED, INC. (1.83)
J & M CONTRACTING, COMPANY (42.30)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.62)
WATERS CONSTRUCTION CO., INC. (1.41)
WILLOW CITY SIGN & RAIL, INC. (1.53)
THIRD COAST SERVICES LLC (1.23)
TEXAS LAND CLEARING SERVICE (0.97)
TEXOP CONSTRUCTION (0.93)
Contract #07163039
Totals7653712.00226775.105757827.5775.2

CountyNACOGDOCHES
HighwaySH 7
FromAT FM 2782
To.
CSJ0553-03-033
Proj IDSTP 1702(111)HES
Work TypeINSTALL FLASHING BEACON
 
0.20044900.0043800.0097.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-21-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days15
Addl Days Granted0
Working Days Charged13
Percent Time Used86
Contractor(s)
LUDCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0553-03-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173008
Totals44900.000.0043800.0097.5

CountyNACOGDOCHES
HighwayFM 95
FromAT PARALLEL CREEK
To.
CSJ0706-03-020
Proj IDBR 1502(622)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.2891783241.531771405.7799.7
Work Order10-30-15
Work Began03-01-16
Work Completed
Time Computed03-01-16
Contract Working Days120
Addl Days Granted18
Working Days Charged147
Percent Time Used106
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0706-03-020
AMERICAN REMEDIATION OPTIONS, INC. (5.48)
PANOLA SIGN & BARRICADE, INC. (0.67)
STRIPING TECHNOLOGY, L.P. (0.70)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.29)
Contract #08153239
Totals1783241.531158.301771405.7799.7

CountyNACOGDOCHES
HighwayFM 95
FromAT TERRAPIN CREEK
To.
CSJ0706-04-019
Proj IDBR 2018(426)
Work TypeBRIDGE REPLACEMENT
 
0.2321145849.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days141
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0706-04-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183218
Totals1145849.400.000.000.0

CountySAN AUGUSTINE
HighwayUS 96
FromSHELBY COUNTY LINE
ToFM 3451
CSJ0809-03-038
Proj IDNH 2013(514)
Work TypeADD PASSING LANES AND RECONST PVMT
 
3.8047319958.626887329.7094.8
Work Order11-12-15
Work Began03-30-16
Work Completed
Time Computed03-21-16
Contract Working Days149
Addl Days Granted0
Working Days Charged199
Percent Time Used133
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0809-03-038
PANOLA SIGN & BARRICADE, INC. (0.19)
COLD CREEK CONSTRUCTION, LTD (1.64)
AMERICAN REMEDIATION OPTIONS, INC. (2.74)
A R BROTHERS CONSTRUCTION SERVICES, INC. (4.64)
DUSTROL, INC. (1.52)
LONGVIEW BRIDGE AND ROAD, LTD. (42.07)
STRIPING TECHNOLOGY, L.P. (1.93)
WEST TEXAS RUMBLE STRIP (0.06)
STRIPING SYSTEMS, INC. (0.02)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.89)
HIGHWAY DATA SERVICES (0.01)
Contract #08153048
Totals7319958.625984.886887329.7094.8

CountyPOLK
HighwayCR
FromBLUEWATER RD OVER BLUE BRANCH
To.
CSJ0911-04-034
Proj IDBR 2001(480)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.231885751.00864610.3598.0
Work Order06-02-16
Work Began09-12-16
Work Completed
Time Computed09-01-16
Contract Working Days128
Addl Days Granted0
Working Days Charged135
Percent Time Used105
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-034
AMERICAN REMEDIATION OPTIONS, INC. (6.59)
PANOLA SIGN & BARRICADE, INC. (1.53)
Contract #04163212
Totals885751.000.00864610.3598.0

CountyPOLK
HighwayCR
FromCARMONA RD AT BRUSHY CREEK
To.
CSJ0911-04-067
Proj IDBR 1502(205)
Work TypeBRIDGE REPLACEMENT
 
0.2251019437.731017967.7599.8
Work Order08-03-16
Work Began11-29-16
Work Completed
Time Computed10-26-16
Contract Working Days121
Addl Days Granted3
Working Days Charged113
Percent Time Used91
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-067
AMERICAN REMEDIATION OPTIONS, INC. (6.83)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.88)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.00)
MCL CONTRACTING, LLC (0.78)
Contract #06163027
Totals1019437.731275.751017967.7599.8