Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayIH0610
FromIH 610
ToIH 610
CSJ6344-99-001
Proj IDRMC - 634499001
Work TypeGENERAL MAINTENANCE HOU METRO AREA
 
0.0017890502.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6344-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07194014
Totals7890502.500.000.000.0

CountyWALLER
HighwayUS0290
FromVARIOUS HWYS IN WALLER COUNTY
ToVARIOUS HWYS IN WALLER COUNTY
CSJ6345-54-001
Proj IDRMC - 634554001
Work TypeASPHALT PAVEMENT REPAIR
 
0.001561200.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6345-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07194015
Totals561200.000.000.000.0