Monthly Local Let Maintenance Report For Fort Worth District As Of Feb 09, 2018 Page 6 Of 6

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyERATH
HighwaySH0006
FromFM 847
ToFM 914
CSJ6319-09-001
Proj IDRMC - 631909001
Work TypeEMERGENCY WORK ON SH 6 IN ERATH COUNTY
 
8.1941755117.003019999.4399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-16-17
Work Completed
Time Computed00-00-00
Contract Working Days47
Addl Days Granted7
Working Days Charged54
Percent Time Used100
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6319-09-001
DUSTROL, INC. (1.18)
TRP CONSTRUCTION GROUP, LLC (4.41)
CROSS ROADS, L.P. (0.74)
Contract #06170240
Totals1755117.00740953.223019999.4399.9

CountyERATH
HighwayUS0067
FromEMC US 67 BRIDGE
ToIN ERATH COUNTY
CSJ6320-21-001
Proj IDEMC - 632021001
Work TypeEMC US67 BRIDGE
 
0.010561010.70404380.0074.4
Work Order10-09-17
Work Began10-09-17
Work Completed
Time Computed10-09-17
Contract Working Days32
Addl Days Granted0
Working Days Charged59
Percent Time Used184
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6320-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07170241
Totals561010.705630.00404380.0074.4