Monthly State Let Construction Report For Fort Worth District As Of Feb 09, 2018 Page 4 Of 5

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTARRANT
HighwayIH 30
FromIH 35W
ToIH 820
CSJ1068-02-146
Proj IDCM 2018(455)
Work TypeITS FIBER, EQUIP, SATELLITE BLDG
 
7.1952498951.080.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days149
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1068-02-146
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183215
Totals2498951.080.000.000.0

CountyTARRANT
HighwaySS 341
FromWHITE SETTLEMENT ROAD
ToDOWNE DRIVE
CSJ1068-03-022
Proj IDNH 1602(327)
Work TypeLANDSCAPING
 
1.001282864.35250095.4088.4
Work Order09-16-16
Work Began12-12-16
Work Completed
Time Computed10-17-16
Contract Working Days64
Addl Days Granted0
Working Days Charged64
Percent Time Used100
Contractor(s)
GREEN SOURCE ENVIRONMENTAL SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1068-03-022
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.22)
Contract #08163248
Totals282864.352000.00250095.4088.4

CountyWISE
HighwayFM 2264
FromUS 287/81
ToCR 4431
CSJ1310-03-026
Proj IDC 1310-3-26
Work TypeGRADING,BASE,DRAINAGE,STRUCTURE,PAV
 
7.2447015561.581031941.2214.7
Work Order10-09-17
Work Began11-06-17
Work Completed
Time Computed11-06-17
Contract Working Days406
Addl Days Granted0
Working Days Charged51
Percent Time Used12
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1310-03-026
DUSTROL, INC. (0.53)
SOUTHERN CROSS CONTRACTORS, LLC (1.71)
MARCOM"S MOWING SERVICE, LLC (0.50)
TOTAL HIGHWAY MAINTENANCE, LLC (1.63)
WOLFE CONSTRUCTION GROUP, INC. (1.90)
BUYERS BARRICADES, INC. (0.47)
Contract #07173044
Totals7015561.58465580.691031941.2214.7

CountyTARRANT
HighwayFM 1187
FromEAST OF FM 1902
ToBF 1187C
CSJ1330-01-062
Proj IDNH 2017(892)
Work TypeHMAC OVERLAY
 
2.5565144732.722199593.0942.7
Work Order04-24-17
Work Began09-05-17
Work Completed
Time Computed05-25-17
Contract Working Days299
Addl Days Granted163
Working Days Charged73
Percent Time Used53
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1330-01-062
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.35)
TEXOP CONSTRUCTION (6.92)
TOTAL HIGHWAY MAINTENANCE, LLC (0.70)
SOUTHERN CROSS CONTRACTORS, LLC (0.38)
STRIPING TECHNOLOGY, L.P. (1.39)
O. TREVINO CONSTRUCTION, LLC (3.61)
W.O.E. CONSTRUCTION (0.05)
Contract #03173212
Totals5144732.722205.002199593.0942.7

CountyTARRANT
HighwayFM 1187
FromMCCART AVE
ToMAIN ST
CSJ1330-03-003
Proj IDSTP 2017(737)
Work TypeLANDSCAPING
 
3.000540000.00473058.0187.6
Work Order03-16-17
Work Began05-24-17
Work Completed
Time Computed04-16-17
Contract Working Days104
Addl Days Granted0
Working Days Charged55
Percent Time Used52
Contractor(s)
AALC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1330-03-003
DALLAS LITE AND BARRICADE INC. (1.88)
Contract #02173036
Totals540000.001950.00473058.0187.6

CountyWISE
HighwayFM 455
FromAT FM 51
To.
CSJ1352-04-014
Proj IDSTP 1702(464)HES
Work TypeINSTALL INT FLASHING BEACON
 
0.20083369.3137882.6745.4
Work Order08-22-17
Work Began01-12-18
Work Completed
Time Computed10-22-17
Contract Working Days30
Addl Days Granted0
Working Days Charged14
Percent Time Used46
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1352-04-014
ALTUS TRAFFIC MANAGEMENT LLC (3.34)
TCB FOUNDATION DRILLERS, INC. (9.31)
TEXAS HIGHWAY MAINTENANCE, LLC (5.23)
WG ENGINEERING & CONSTRUCTION, LLC (9.79)
ROAD MASTER STRIPING LLC (3.13)
Contract #07173213
Totals83369.3137882.6737882.6745.4

CountyPARKER
HighwayFM 1189
FromYOUNG BEND ROAD
ToHOOD COUNTY LINE
CSJ1468-01-024
Proj IDSTP 1402(036)
Work TypeGR,STR,FLX BS, SC, MBGF,SIGN,PVT MK
 
9.0586481549.556834223.4399.9
Work Order10-07-14
Work Began01-25-16
Work Completed
Time Computed10-23-14
Contract Working Days253
Addl Days Granted163
Working Days Charged342
Percent Time Used82
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1468-01-024
RAMBO CONTRACTING, INC. (4.87)
TEXAS ALTERNATIVE GRASSER, INC. (0.76)
PEACHTREE CONSTRUCTION, LTD. (19.95)
CHEROKEE SERVICES (0.03)
FOUNDATION DRILLERS, INC. (0.65)
WEST TEXAS RUMBLE STRIP (0.05)
MARCOM"S MOWING SERVICE, LLC (0.87)
D. I. J. CONSTRUCTION, INC. (1.69)
FORTSON CONTRACTING, INC. (0.49)
Contract #08143043
Totals6481549.557351.206834223.4399.9

CountyHOOD
HighwayFM 167
FromFM 4
To3.712 MILES SOUTH OF FM 4
CSJ1513-01-019
Proj IDSTP 2017(738)HES
Work TypeSFTY TRT FIXED OBJECTS & PVD SHLDRS
 
3.7122616562.961286605.8849.1
Work Order06-14-17
Work Began08-21-17
Work Completed
Time Computed07-15-17
Contract Working Days187
Addl Days Granted0
Working Days Charged102
Percent Time Used54
Contractor(s)
BRETT CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1513-01-019
NORTH EASTERN PAVERS (21.65)
LUZ LERMA CONSTRUCTION, INC. (16.06)
DUSTROL, INC. (0.68)
Contract #05173220
Totals2616562.9647120.321286605.8849.1

CountyJOHNSON
HighwayFM 916
FromSH 171
ToFM 4
CSJ1599-02-014
Proj IDSTP 1402(037)HES
Work TypeGRADING, BASE AND PAVEMENT
 
12.8426925133.468175809.0699.9
Work Order09-30-14
Work Began09-02-15
Work Completed
Time Computed10-16-14
Contract Working Days201
Addl Days Granted86
Working Days Charged421
Percent Time Used146
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1599-02-014
STRIPING TECHNOLOGY, L.P. (0.77)
TOTAL HIGHWAY MAINTENANCE, LLC (0.67)
RAMBO CONTRACTING, INC. (7.05)
FARR FOUNDATION, INC. (2.15)
PEACHTREE CONSTRUCTION, LTD. (21.42)
FORTSON CONTRACTING, INC. (1.19)
TEXAS ALTERNATIVE GRASSER, INC. (0.23)
Contract #08143036
Totals6925133.4616351.418175809.0699.9

CountyJOHNSON
HighwayFM 1807
FromFM 1706
ToJOHNSON/ELLIS COUNTY LINE.
CSJ1600-02-017
Proj IDSTP 1502(545)HES
Work TypeGR, BS, DR, STR, PAV
 
8.8868282797.477838941.2296.2
Work Order10-30-15
Work Began01-04-16
Work Completed
Time Computed11-30-15
Contract Working Days278
Addl Days Granted32
Working Days Charged427
Percent Time Used137
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1600-02-017
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (7.54)
ALTUS TRAFFIC MANAGEMENT LLC (0.31)
STRIPING TECHNOLOGY, L.P. (1.61)
DIAMOND SURFACE, INC. (0.11)
SYNERGY SIGNS & SERVICES, LLC (0.53)
J & M CONTRACTING, COMPANY (16.28)
TEX OP CONSTRUCTION, LP (0.11)
TX TINMAN ENTERPRISES, LLC. (3.02)
DUSTROL, INC. (1.03)
FORTSON CONTRACTING, INC. (0.64)
Contract #08153033
Totals8282797.470.007838941.2296.2

CountyPARKER
HighwayFM 730
FromAT VEAL STATION/FLAT ROCK RD
To.
CSJ1601-01-031
Proj IDSTP 1702(465)HES
Work TypeTRAFFIC SIGNAL
 
0.200179200.00167048.3093.2
Work Order08-16-17
Work Began11-27-17
Work Completed
Time Computed11-15-17
Contract Working Days40
Addl Days Granted0
Working Days Charged28
Percent Time Used70
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1601-01-031
ROAD MASTER STRIPING LLC (1.87)
Contract #07173006
Totals179200.00109908.00167048.3093.2

CountyPARKER
HighwayFM 1886
FromFM 730
ToTARRANT COUNTY LINE
CSJ1605-01-014
Proj IDSTP 2014(478)
Work TypeGR.BS,DR,STRUC AND PAVEMENT
 
5.7484834822.795073406.0399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-07-14
Work Began06-12-14
Work Completed
Time Computed05-23-14
Contract Working Days256
Addl Days Granted81
Working Days Charged411
Percent Time Used121
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1605-01-014
RAMBO CONTRACTING, INC. (4.85)
BICK"S CONSTRUCTION, INC. (16.34)
TOTAL HIGHWAY MAINTENANCE, LLC (1.93)
MARCOM"S MOWING SERVICE, LLC (0.53)
WEST TEXAS RUMBLE STRIP (0.08)
AAA DRILLING FOUNDATION CO., INC. (0.36)
LIRA ELECTRIC (1.57)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.81)
TEXAS ALTERNATIVE GRASSER, INC. (0.79)
ELLIS-MCGINNIS CONSTRUCTION CO. (1.86)
CHEROKEE SERVICES (0.04)
Contract #03143221
Totals4834822.790.005073406.0399.9

CountyTARRANT
HighwayFM 1938
From0.2 MILE SOUTH OF FM 1709
ToRANDOL MILL RD/WESTLAKE C/L
CSJ1978-01-050
Proj IDSTP 1402(039)MM
Work TypeGR, BS, DR, STRUCTURES & PAVEMENT
 
1.74320575236.8718259491.1188.7
Work Order01-16-15
Work Began03-23-15
Work Completed
Time Computed02-01-15
Contract Working Days554
Addl Days Granted373
Working Days Charged695
Percent Time Used74
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1978-01-050
DALLAS LITE AND BARRICADE INC. (0.38)
GJ SEEDING, LLC (0.59)
THELIN RECYCLING COMPANY, L.P. (0.25)
AUSTCO, INC. (0.05)
NORTH TEXAS CONTRACTING, INC. (35.34)
LIRA ELECTRIC (2.63)
FARR FOUNDATION, INC. (0.60)
BREDA COMPANY, INC. (0.50)
W.O.E. CONSTRUCTION (9.26)
TEXAS SHAFTS, INC. (0.76)
CROSSROADS DECORATIVE PAVEMENT (0.09)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (2.75)
SCOTT DERR PAINTING CO, LLC (0.06)
TRP CONSTRUCTION GROUP, LLC (0.67)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (5.69)
A & A CONSTRUCTION (0.06)
MARCOM"S MOWING SERVICE, LLC (0.32)
BRENDA PRICE TRUCKING (0.68)
INLET STRUCTURE SPECIALTIES LTD. (3.12)
JM MATERIALS, INC. (0.50)
KLP COMMERCIAL, LLC (8.05)
TEX OP CONSTRUCTION, LP (0.41)
VENEGAS MASONRY (0.43)
BIG DOG DRILLING, LLC (0.18)
MURRAY-WARD CONTRACTING (0.03)
Contract #08143005
Totals20575236.87102577.7918259491.1188.7

CountyTARRANT
HighwayFM 1220
FromEAGLE MOUNTAIN ELEM SCHOOL
To1,100 FT. NORTH OF BAILEY BOSWELL
CSJ2079-01-043
Proj IDSTP 2013(901)
Work TypeGRADING, BASE AND PAVEMENT
 
2.8798350775.032981354.5035.7
Work Order03-31-16
Work Began01-17-17
Work Completed
Time Computed09-12-16
Contract Working Days278
Addl Days Granted12
Working Days Charged227
Percent Time Used78
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 2079-01-043
CEN CONCRETE CONSTRUCTION COMPANY, INC. (6.08)
MICA CORPORATION (1.27)
FARR FOUNDATION, INC. (1.20)
TOTAL HIGHWAY MAINTENANCE, LLC (2.02)
TINMAN ENTERPRISES (1.66)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (4.07)
W.O.E. CONSTRUCTION (3.82)
ECONOMY TREE SERVICES, LLC (0.43)
COMEN ENTERPRISE LLC (1.65)
Contract #01163037
Totals8350775.0336082.042981354.5035.7

CountyJOHNSON
HighwayFM 1902
FromTARRANT COUNTY LINE
ToFM 917
CSJ2118-02-019
Proj IDSTP 1502(547)HES
Work TypeGR, BS, DR, STR, & PVT
 
7.6696740440.334086474.7160.6
Work Order09-19-16
Work Began01-24-17
Work Completed
Time Computed10-20-16
Contract Working Days354
Addl Days Granted0
Working Days Charged250
Percent Time Used70
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2118-02-019
DALLAS LITE AND BARRICADE INC. (1.44)
DUSTROL, INC. (3.23)
FORTSON CONTRACTING, INC. (2.24)
J & M CONTRACTING COMPANY (14.47)
MARCOM"S MOWING SERVICE, LLC (0.91)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.37)
TRP CONSTRUCTION GROUP, LLC (1.63)
C & J TREE SERVICE (0.34)
W.O.E. CONSTRUCTION (0.14)
Contract #07163207
Totals6740440.33711026.654086474.7160.6

CountyTARRANT
HighwaySH 360
FromNORTH OF E ABRAM ST
ToIH 20 INTERCHANGE
CSJ2266-02-086
Proj IDNH 2018(456)
Work TypeWIDEN & RECONSTRUCT 6 TO 8 LANES
 
5.42453391000.010.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days797
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FLUOR HEAVY CIVIL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2266-02-086
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183001
Totals53391000.010.000.000.0

CountyTARRANT
HighwaySH 360
From0.349 MI N OF SH 180
To0.158 MI N OF SH 180
CSJ2266-02-146
Proj IDSTP 1702(738)HESG
Work TypeSAFETY TREAT FIXED OBJECTS
 
0.191281936.15117491.7041.6
Work Order11-01-17
Work Began01-12-18
Work Completed
Time Computed12-02-17
Contract Working Days24
Addl Days Granted0
Working Days Charged9
Percent Time Used37
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 2266-02-146
TOTAL HIGHWAY MAINTENANCE, LLC (6.82)
WEBBER BARRIER SERVICES, LLC. (12.95)
PRECISION STRIPING (2.37)
Contract #08173242
Totals281936.15117491.70117491.7041.6

CountyPALO PINTO
HighwayFM 2353
FromSH-16
ToPR-36
CSJ2290-01-009
Proj IDSTP 1502(335)
Work TypeGR,BS,STRUCTURE AND PAVEMENTS
 
5.8805278946.235928225.6199.9
Work Order07-31-15
Work Began10-12-15
Work Completed
Time Computed08-29-15
Contract Working Days299
Addl Days Granted65
Working Days Charged361
Percent Time Used99
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2290-01-009
LUZ LERMA CONSTRUCTION, INC. (16.74)
HJC FARMS, INC. (1.98)
ALTUS TRAFFIC MANAGEMENT LLC (0.59)
STRIPING TECHNOLOGY, L.P. (1.83)
M.A.R. TRUCKING (0.20)
WEST TEXAS RUMBLE STRIP (0.07)
NIXON ENGINEERING, L.L.C. (0.06)
Contract #06153243
Totals5278946.2312223.905928225.6199.9

CountyPARKER
HighwayFM 1187
FromFM 5
ToTARRANT COUNTY LINE
CSJ2291-01-013
Proj IDSTP 2014(772)
Work TypeGR,BS,STR,SURFACE,SIGNING & MARKING
 
7.2046785848.592291210.8333.7
Work Order08-08-14
Work Began12-10-14
Work Completed
Time Computed08-24-14
Contract Working Days374
Addl Days Granted0
Working Days Charged120
Percent Time Used32
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 2291-01-013
RAMBO CONTRACTING, INC. (20.05)
TEXAS ALTERNATIVE GRASSER, INC. (0.90)
NORTHEASTERN PAVERS, INC. (14.31)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED (0.49)
HJC FARMS, INC. (0.77)
WEST TEXAS RUMBLE STRIP (0.07)
TRP CONSTRUCTION GROUP, LLC (1.08)
Contract #06143231
Totals6785848.59397993.812291210.8333.7

CountyTARRANT
HighwayIH 20
FromEB AND WB IH 20 OVER BOWEN RD
ToEB AND WB IH 20 OVER RUSH CREEK
CSJ2374-05-081
Proj IDBR 1702(739)
Work TypeUPGRADE BRIDGE & APPROACH RAILING
 
2.010966661.00424443.5043.9
Work Order09-14-17
Work Began12-08-17
Work Completed
Time Computed10-15-17
Contract Working Days121
Addl Days Granted0
Working Days Charged29
Percent Time Used23
Contractor(s)
IOWA BRIDGE & CULVERT, LC
SUBCONTRACTOR(S) FOR CCSJ: 2374-05-081
CROSSROADS, L.P. (2.35)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (1.55)
PENHALL COMPANY (3.10)
COMEN ENTERPRISE LLC (6.27)
Contract #08173215
Totals966661.00209136.00424443.5043.9

page 1 | page 2 | page 3 | page 4 | page 5