Monthly State Let Maintenance Report For El Paso District As Of Jan 10, 2018 Page 2 Of 2

Last Update: Wednesday, January 10, 2018
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6309-17-001
Proj IDRMC - 630917001
Work TypeMISC. CONCRETE REPAIR
 
186.0001311766.43326619.9124.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
SYNERGY PROJECT CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06174010
Totals1311766.4392938.44326619.9124.8

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6309-55-001
Proj IDRMC - 630955001
Work TypeTRAFFIC CONTROL
 
100.000659645.00620342.0094.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged275
Percent Time Used75
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174237
Totals659645.0060632.00620342.0094.0

CountyCULBERSON
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6309-56-001
Proj IDRMC - 630956001
Work TypeTRAFFIC CONTROL
 
100.000471241.00514450.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-01-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged275
Percent Time Used75
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6309-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174238
Totals471241.008462.50514450.0099.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6314-50-001
Proj IDRMC - 631450001
Work TypeSPALL AND FULL DEPTH REPAIR
 
160.000596949.30284558.2147.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-14-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged140
Percent Time Used38
Contractor(s)
SYNERGY PROJECT CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06174208
Totals596949.3055865.92284558.2147.6

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6314-51-001
Proj IDRMC - 631451001
Work TypeROADWAY SPALL & FULL DEPTH REPAIR
 
200.000450425.09281166.5462.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-13-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged141
Percent Time Used38
Contractor(s)
SYNERGY PROJECT CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04174210
Totals450425.0916854.07281166.5462.4

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6317-12-001
Proj IDRMC - 631712001
Work TypeCLEANING & SWEEPING
 
140.000513970.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174011
Totals513970.000.000.000.0

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6317-14-001
Proj IDRMC - 631714001
Work TypeCLEANING & SWEEPING
 
140.000490963.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184013
Totals490963.000.000.000.0

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6317-15-001
Proj IDRMC - 631715001
Work TypeMETAL BEAM GUARDRAIL REPAIR
 
100.000684590.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-02-18
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6317-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09174013
Totals684590.000.000.000.0

CountyBREWSTER
HighwayUS0090
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6321-81-001
Proj IDRMC - 632181001
Work TypeBUNDLE BID
 
100.0002673601.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MIJELUM
SUBCONTRACTOR(S) FOR CCSJ: 6321-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174211
Totals2673601.000.000.000.0

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIIONS
CSJ6324-46-001
Proj IDRMC - 632446001
Work TypeMETAL BEAM GUARD FENCE
 
100.000587667.250.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BOWEN INDUSTRIAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174212
Totals587667.250.000.000.0

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6324-50-001
Proj IDRMC - 632450001
Work TypeBARRICADES,SIGNS AND TRAFFIC CONTROL
 
200.000445800.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174012
Totals445800.000.000.000.0

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6324-51-001
Proj IDRMC - 632451001
Work TypeBARRICADES,SIGNS,TRAFFIC CONTROL
 
100.000463020.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174013
Totals463020.000.000.000.0

CountyCULBERSON
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6324-52-001
Proj IDRMC - 632452001
Work TypeBARRICADES,SIGNS,TRAFFIC CONTROL
 
100.000329950.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6324-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174213
Totals329950.000.000.000.0

CountyCULBERSON
HighwayRM0652
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6324-65-001
Proj IDRMC - 632465001
Work TypePOTHOLE REPAIR
 
100.000433000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MIJELUM
SUBCONTRACTOR(S) FOR CCSJ: 6324-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174014
Totals433000.000.000.000.0

page 1 | page 2