Monthly State Let Maintenance Report For El Paso District As Of Apr 12, 2024 Page 2 Of 3

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6425-30-001
Proj IDRMC - 642530001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.010897525.00643843.72100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-23
Work Completed01-03-23
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6425-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12224028
Totals897525.005000.00643843.72100.0

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6428-18-001
Proj IDRMC - 642818001
Work TypeCOMMUNICATION CABLE
 
1985311.56595905.5130.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged336
Percent Time Used46
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6428-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03234217
Totals1985311.56114926.51595905.5130.0

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6428-20-001
Proj IDRMC - 642820001
Work TypePAVEMENT MARKINGS
 
649236.00337333.2551.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged230
Percent Time Used63
Contractor(s)
MIJELUM, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6428-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05234015
Totals649236.0030177.00337333.2551.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6429-06-001
Proj IDMMC - 642906001
Work TypeHOT MIX
 
0.010439500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-01-23
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted120
Working Days Charged183
Percent Time Used76
Contractor(s)
JOBE MATERIALS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6429-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03234020
Totals439500.000.000.000.0

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6429-14-001
Proj IDRMC - 642914001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.0101096192.781345821.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-16-23
Work Completed02-28-23
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged382
Percent Time Used52
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6429-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02234032
Totals1096192.78162528.701345821.50100.0

CountyHUDSPETH
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6431-58-001
Proj IDBPM - 643158001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.0101643286.64528808.5332.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged50
Percent Time Used50
Contractor(s)
SPARTAN CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6431-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10234011
Totals1643286.64226723.87528808.5332.1

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6435-00-001
Proj IDRMC - 643500001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.010999905.40970130.0797.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-07-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged269
Percent Time Used36
Contractor(s)
SYNERGY PROJECT CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6435-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05234210
Totals999905.40123162.04970130.0797.0

CountyBREWSTER
HighwayUS0090
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6436-33-001
Proj IDRMC - 643633001
Work TypeTRAFFIC CONTROL SERVICES
 
0.010410000.00135935.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed05-30-23
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged188
Percent Time Used51
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6436-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05234211
Totals410000.000.00135935.00100.0

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6437-83-001
Proj IDRMC - 643783001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.010400550.00343558.9985.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-15-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged230
Percent Time Used31
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6437-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234026
Totals400550.0051572.50343558.9985.7

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6438-27-001
Proj IDRMC - 643827001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.010735425.00273829.8237.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged244
Percent Time Used66
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6438-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234412
Totals735425.0042831.32273829.8237.2

CountyEL PASO
HighwaySL0375
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6443-60-001
Proj IDMMC - 644360001
Work TypeDE-ICING SALT
 
0.010299056.0251692.8417.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted180
Working Days Charged150
Percent Time Used41
Contractor(s)
NSG LOGISTICS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6443-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234021
Totals299056.020.0051692.8417.2

CountyBREWSTER
HighwayUS0090
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6444-08-001
Proj IDRMC - 644408001
Work TypeCULVERT CLEANING
 
0.010711600.00238280.0033.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged126
Percent Time Used34
Contractor(s)
E.V.G. ENTERPRISE
SUBCONTRACTOR(S) FOR CCSJ: 6444-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09234208
Totals711600.0028715.00238280.0033.4

CountyBREWSTER
HighwayFM0170
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6446-12-001
Proj IDMMC - 644612001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010799135.00133862.4216.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted180
Working Days Charged143
Percent Time Used39
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6446-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09234209
Totals799135.0054285.73133862.4216.7

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6451-29-001
Proj IDRMC - 645129001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.0101201850.00425883.5535.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged88
Percent Time Used24
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6451-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10234012
Totals1201850.0077419.45425883.5535.4

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6451-31-001
Proj IDRMC - 645131001
Work TypeTRAFFIC CONTROL SERVICES
 
0.010729500.00184738.7525.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged84
Percent Time Used23
Contractor(s)
FC TRAFFIC CONTROL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6451-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234013
Totals729500.0073950.00184738.7525.3

CountyBREWSTER
HighwayUS0090
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6451-77-001
Proj IDRMC - 645177001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.0101194460.00131121.4410.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged14
Percent Time Used3
Contractor(s)
DIGG COMMERCIAL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6451-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01244018
Totals1194460.00131121.44131121.4410.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6454-27-001
Proj IDRMC - 645427001
Work TypeBRIDGE REPAIR
 
0.010772250.00193310.8825.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged31
Percent Time Used8
Contractor(s)
HAWK CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6454-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234015
Totals772250.00193310.88193310.8825.0

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6454-87-001
Proj IDRMC - 645487001
Work TypeTRAFFIC CONTROL SERVICES
 
0.010777475.0058390.007.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged32
Percent Time Used8
Contractor(s)
APACHE BARRICADE & SIGN
SUBCONTRACTOR(S) FOR CCSJ: 6454-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234028
Totals777475.0058390.0058390.007.5

CountyBREWSTER
HighwaySH0118
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6454-89-001
Proj IDMMC - 645489001
Work TypeWINTER WEATHER MATERIAL
 
0.010280710.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged57
Percent Time Used31
Contractor(s)
NSG LOGISTICS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6454-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234029
Totals280710.000.000.000.0

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6455-23-001
Proj IDRMC - 645523001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010672233.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged31
Percent Time Used8
Contractor(s)
DOUBLE H CONTRACTING INC.
SUBCONTRACTOR(S) FOR CCSJ: 6455-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234016
Totals672233.000.000.000.0

page 1 | page 2 | page 3