Monthly State Let Maintenance Report For El Paso District As Of Oct 16, 2017 Page 2 Of 2

Last Update: Monday, October 16, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6309-17-001
Proj IDRMC - 630917001
Work TypeMISC. CONCRETE REPAIR
 
186.0001311766.4377161.115.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged30
Percent Time Used8
Contractor(s)
SYNERGY PROJECT CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06174010
Totals1311766.4377161.1177161.115.8

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6309-55-001
Proj IDRMC - 630955001
Work TypeTRAFFIC CONTROL
 
100.000659645.00440583.0066.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged183
Percent Time Used50
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174237
Totals659645.0065717.50440583.0066.7

CountyCULBERSON
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6309-56-001
Proj IDRMC - 630956001
Work TypeTRAFFIC CONTROL
 
100.000471241.00375812.5079.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-01-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged183
Percent Time Used50
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6309-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174238
Totals471241.0057962.50375812.5079.7

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6314-50-001
Proj IDRMC - 631450001
Work TypeSPALL AND FULL DEPTH REPAIR
 
160.000596949.30117538.4219.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-14-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged48
Percent Time Used13
Contractor(s)
SYNERGY PROJECT CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06174208
Totals596949.3061303.00117538.4219.6

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6314-51-001
Proj IDRMC - 631451001
Work TypeROADWAY SPALL & FULL DEPTH REPAIR
 
200.000450425.0977718.9917.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-13-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged49
Percent Time Used13
Contractor(s)
SYNERGY PROJECT CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04174210
Totals450425.0949088.0677718.9917.2

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6317-15-001
Proj IDRMC - 631715001
Work TypeMETAL BEAM GUARDRAIL REPAIR
 
100.000684590.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6317-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09174013
Totals684590.000.000.000.0