Monthly Local Let Maintenance Report For El Paso District As Of Feb 09, 2018 Page 2 Of 4

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6270-50-001
Proj IDRMC - 627050001
Work TypeSURFACE FINISHING FOR TEPEES
 
1.00062900.72129472.2499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-15-14
Work Began00-00-00
Work Completed
Time Computed07-16-14
Contract Working Days40
Addl Days Granted0
Working Days Charged30
Percent Time Used75
Contractor(s)
BXB GROUP INCORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6270-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06142401
Totals62900.720.00129472.2499.9

CountyCULBERSON
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6276-91-001
Proj IDRMC - 627691001
Work TypeCONCRETE RIPRAP & CHANNEL REPAIRS
 
1.000372398.38366074.4098.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-07-15
Work Began07-20-15
Work Completed
Time Computed07-20-15
Contract Working Days96
Addl Days Granted64
Working Days Charged121
Percent Time Used75
Contractor(s)
KEGLEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6276-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05152412
Totals372398.380.00366074.4098.3

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6283-42-001
Proj IDRMC - 628342001
Work TypeCULVERT AND STORM SEWER CLEANING
 
400.000268875.00334176.4099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-20-15
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02152404
Totals268875.000.00334176.4099.9

CountyHUDSPETH
HighwayUS0062
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6284-26-001
Proj IDRMC - 628426001
Work TypePICNIC AREA MAINTENANCE
 
5.00029340.0022195.0075.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-01-15
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged336
Percent Time Used92
Contractor(s)
M.A.C
SUBCONTRACTOR(S) FOR CCSJ: 6284-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04152402
Totals29340.000.0022195.0075.6

CountyCULBERSON
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6284-54-001
Proj IDRMC - 628454001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
270.00096175.00113160.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-06-15
Work Completed03-28-16
Time Computed00-00-00
Contract Working Days66
Addl Days Granted0
Working Days Charged64
Percent Time Used96
Contractor(s)
MIJELUM
SUBCONTRACTOR(S) FOR CCSJ: 6284-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03152411
Totals96175.000.00113160.00100.0

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6285-11-001
Proj IDRMC - 628511001
Work TypeCLEANING & SWEEPING HIGHWAYS
 
600.000305765.17358117.9899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-18-15
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
SYNERGY PROJECT CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04152403
Totals305765.170.00358117.9899.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6285-48-001
Proj IDRMC - 628548001
Work TypeCLEANING & SWEEPING HIGHWAYS
 
600.000283175.00403815.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-26-15
Work Began00-00-00
Work Completed06-17-16
Time Computed07-13-15
Contract Working Days365
Addl Days Granted0
Working Days Charged340
Percent Time Used93
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05152408
Totals283175.000.00403815.50100.0

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6285-74-001
Proj IDRMC - 628574001
Work TypeCONCRETE RAIL REPAIR
 
10.000341900.00744191.4499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged279
Percent Time Used76
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06152404
Totals341900.000.00744191.4499.9

CountyCULBERSON
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6287-60-001
Proj IDRMC - 628760001
Work TypePOTHOLE REPAIR
 
500.000384825.00741900.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-27-15
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged256
Percent Time Used70
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05152409
Totals384825.000.00741900.0099.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6293-10-001
Proj IDSUP - 629310001
Work TypeJANITORIAL/LANDSCAPE MAINTENANCE SERVICE
 
1.000373028.18391129.0899.9
Work Order10-01-15
Work Began10-01-15
Work Completed
Time Computed10-01-15
Contract Working Days730
Addl Days Granted92
Working Days Charged822
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6293-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09152432
Totals373028.1815105.43391129.0899.9

CountyEL PASO
HighwayIH0010
FromEL PASO DISTRICT COMPLEX
ToEL PASO DISTRICT COMPLEX
CSJ6293-50-001
Proj IDSUP - 629350001
Work TypeJANITORIAL DHQ
 
1.000336378.00336378.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-01-15
Work Began00-00-00
Work Completed
Time Computed10-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged701
Percent Time Used96
Contractor(s)
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6293-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09152431
Totals336378.000.00336378.0099.9

CountyHUDSPETH
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6293-96-001
Proj IDRMC - 629396001
Work TypeROADWAY LEVEL UP
 
1.800421150.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6293-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01162406
Totals421150.000.000.000.0

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6294-03-001
Proj IDRMC - 629403001
Work TypeMOWING HIGHWAY RIGHT-OF-WAY
 
100.00068635.0056247.5581.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged43
Percent Time Used71
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6294-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10152403
Totals68635.000.0056247.5581.9

CountyEL PASO
HighwayUS0062
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6295-55-001
Proj IDRMC - 629555001
Work TypePICNIC AREA MAINTENANCE
 
5.00024239.6743544.6399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted92
Working Days Charged457
Percent Time Used100
Contractor(s)
A CUT ABOVE LAWN MAINTENANCE & SPRINKLER CO.
SUBCONTRACTOR(S) FOR CCSJ: 6295-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12152404
Totals24239.670.0043544.6399.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6295-65-001
Proj IDRMC - 629565001
Work TypeJANITORIAL GROUND MAINTENANCE
 
200.00050072.0061432.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-02-16
Work Began03-02-16
Work Completed
Time Computed03-02-16
Contract Working Days365
Addl Days Granted68
Working Days Charged433
Percent Time Used100
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6295-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12152408
Totals50072.000.0061432.0099.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6298-14-001
Proj IDSUP - 629814001
Work TypeHIGHWAY LANDSCAPE MAINTENANCE
 
30.0001659870.201489083.6989.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged702
Percent Time Used96
Contractor(s)
TIBH INDUSTRIES, INC.
BORDER TM INDUSTRIES, INC
SUBCONTRACTOR(S) FOR CCSJ: 6298-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02162402
Totals1659870.2054884.531489083.6989.7

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6300-11-001
Proj IDRMC - 630011001
Work TypeCLEANING & SWEEPING HIGHWAYS
 
600.000312795.00384298.3399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-19-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted318
Working Days Charged592
Percent Time Used86
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05162402
Totals312795.0048330.00384298.3399.9

CountyPRESIDIO
HighwayUS0067
FromPRESIDIO COUNTY
ToBREWSTER COUNTY
CSJ6300-29-001
Proj IDRMC - 630029001
Work TypePICNIC AREA LITTER BARREL
 
271.00057360.0089893.41100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-25-16
Work Began07-01-16
Work Completed10-31-17
Time Computed07-01-16
Contract Working Days365
Addl Days Granted123
Working Days Charged488
Percent Time Used100
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6300-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04162411
Totals57360.000.0089893.41100.0

CountyHUDSPETH
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6300-31-001
Proj IDRMC - 630031001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
270.000126745.00107518.4086.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-11-16
Work Completed
Time Computed00-00-00
Contract Working Days66
Addl Days Granted0
Working Days Charged70
Percent Time Used106
Contractor(s)
MESA D CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6300-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04162413
Totals126745.000.00107518.4086.6

CountyHUDSPETH
HighwayUS0062
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6300-32-001
Proj IDRMC - 630032001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
231.00081718.0039692.72100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-23-16
Work Began06-07-16
Work Completed11-14-16
Time Computed06-07-16
Contract Working Days66
Addl Days Granted6
Working Days Charged73
Percent Time Used101
Contractor(s)
MESA D CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6300-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04162410
Totals81718.000.0039692.72100.0

page 1 | page 2 | page 3 | page 4