Monthly State Let Maintenance Report For Bryan District As Of Jan 10, 2018 Page 2 Of 2

Last Update: Wednesday, January 10, 2018
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBRAZOS
HighwayBS0006R
FromVARIOUS
ToVARIOUS
CSJ6315-29-001
Proj IDRMC - 631529001
Work TypeHMA MILL AND INLAY
 
0.001687930.000.000.0
Work Order11-20-17
Work Began10-25-17
Work Completed
Time Computed11-27-17
Contract Working Days66
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6315-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174204
Totals687930.000.000.000.0

CountyWALKER
HighwaySH0030
FromVARIOUS
ToVARIOUS
CSJ6315-30-001
Proj IDRMC - 631530001
Work TypeHMA MILL AND INLAY
 
0.001672700.00448727.6366.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-31-17
Work Completed
Time Computed00-00-00
Contract Working Days66
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6315-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174205
Totals672700.000.00448727.6366.7

CountyWALKER
HighwaySH0030
FromVARIOUS
ToVARIOUS
CSJ6317-38-001
Proj IDRMC - 631738001
Work TypeSPOT BASE REPAIR
 
0.001878327.50483218.3655.0
Work Order10-26-17
Work Began10-26-17
Work Completed
Time Computed10-26-17
Contract Working Days118
Addl Days Granted0
Working Days Charged19
Percent Time Used16
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6317-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174005
Totals878327.50243735.80483218.3655.0

CountyWASHINGTON
HighwayUS0290
FromVARIOUS
ToVARIOUS
CSJ6317-39-001
Proj IDRMC - 631739001
Work TypeSPOT BASE REPAIR
 
0.001850911.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-10-17
Work Completed
Time Computed00-00-00
Contract Working Days118
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6317-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174206
Totals850911.000.000.000.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6317-40-001
Proj IDRMC - 631740001
Work TypeSPOT BASE REPAIR
 
0.001816109.50168166.36100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed12-11-17
Time Computed00-00-00
Contract Working Days118
Addl Days Granted27
Working Days Charged10
Percent Time Used6
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6317-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08174206
Totals816109.500.00168166.36100.0

CountyBRAZOS
HighwayFM0060
FromSH 47
ToBRAZOS RIVER
CSJ6317-54-001
Proj IDRMC - 631754001
Work TypeSEAL COAT AND HMA OVERLAY
 
3.3431487658.38611567.4041.1
Work Order11-20-17
Work Began10-25-17
Work Completed
Time Computed11-20-17
Contract Working Days36
Addl Days Granted0
Working Days Charged6
Percent Time Used16
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6317-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174207
Totals1487658.38611567.40611567.4041.1

CountyBRAZOS
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6318-25-001
Proj IDRMC - 631825001
Work TypeINSTALLATION OF DRIVEWAY PIPE
 
0.001649408.00252525.0038.8
Work Order09-21-17
Work Began08-30-17
Work Completed
Time Computed09-21-17
Contract Working Days730
Addl Days Granted0
Working Days Charged123
Percent Time Used16
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6318-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174006
Totals649408.000.00252525.0038.8

CountyBURLESON
HighwayFM0060
FromSH 36
To1.2 MI. WEST OF FM 2039
CSJ6319-04-001
Proj IDRMC - 631904001
Work TypeSEAL COAT AND HMA OVERLAY
 
7.1181023189.870.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days26
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6319-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10174016
Totals1023189.870.000.000.0

CountyWALKER
HighwaySH0030
FromVARIOUS
ToVARIOUS
CSJ6319-27-001
Proj IDRMC - 631927001
Work TypeSPOT PAVEMENT MARKINGS
 
0.001311200.0044418.9414.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-14-17
Work Began10-13-17
Work Completed
Time Computed09-14-17
Contract Working Days730
Addl Days Granted0
Working Days Charged48
Percent Time Used6
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6319-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174007
Totals311200.000.0044418.9414.2

CountyLEON
HighwayUS0079
FromTRM OFFSET 426 + 0.894
ToTRM OFFSET 434 + 0.858
CSJ6320-46-001
Proj IDRMC - 632046001
Work TypeOVERLAY, PLANING, MBGF, BRIDGE RAIL
 
5.0592153409.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-16-17
Work Completed
Time Computed00-00-00
Contract Working Days55
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6320-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09174008
Totals2153409.700.000.000.0

CountyWASHINGTON
HighwayUS0290
FromVARIOUS
ToVARIOUS
CSJ6323-02-001
Proj IDRMC - 632302001
Work TypeFLAGGING AND TRAFFIC CONTROL
 
0.0011969791.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ALTUS TRAFFIC MANAGEMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 6323-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11174006
Totals1969791.500.000.000.0

page 1 | page 2