Monthly Local Let Maintenance Report For Bryan District As Of Feb 09, 2018 Page 3 Of 4

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyROBERTSON
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6319-94-001
Proj IDRMC - 631994001
Work TypeROADSIDE MOWING
 
288.315153808.360.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days49
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LAWRENCE W. SIMS
SUBCONTRACTOR(S) FOR CCSJ: 6319-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12171702
Totals153808.360.000.000.0

CountyGRIMES
HighwayBS0006S
FromVARIOUS
ToVARIOUS
CSJ6320-24-001
Proj IDSUP - 632024001
Work TypeBUILDING JANITORIAL
 
0.0017505.842942.5039.2
Work Order07-19-17
Work Began07-28-17
Work Completed
Time Computed07-25-17
Contract Working Days372
Addl Days Granted0
Working Days Charged191
Percent Time Used51
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6320-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171703
Totals7505.84353.102942.5039.2

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6320-25-001
Proj IDSUP - 632025001
Work TypeTREE REMOVAL
 
0.00130219.001300.004.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-21-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged123
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6320-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06171704
Totals30219.000.001300.004.3

CountyBRAZOS
HighwayFM2154
FromFM 2154
ToAT FM 60
CSJ6320-48-001
Proj IDBPM - 632048001
Work TypeREPAIR OF BEAM IMPACT DAMAGE
 
0.03727640.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days5
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6320-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12171704
Totals27640.000.000.000.0

CountyWASHINGTON
HighwayBS0036J
FromAT LITTLE SANDY CREEK
ToAT LITTLE SANDY CREEK
CSJ6320-57-001
Proj IDBPM - 632057001
Work TypeRIPRAP REPAIR
 
0.057179818.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-16-18
Work Completed
Time Computed00-00-00
Contract Working Days16
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DOZIERS EXCAVATING & HAULING
SUBCONTRACTOR(S) FOR CCSJ: 6320-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12171705
Totals179818.000.000.000.0

CountyFREESTONE
HighwayFM0080
FromVARIOUS
ToVARIOUS
CSJ6320-70-001
Proj IDBPM - 632070001
Work TypePILE REPAIR
 
0.10024990.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-31-18
Work Began01-31-18
Work Completed
Time Computed01-31-18
Contract Working Days10
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXCAVATION COMPANY LLC.
SUBCONTRACTOR(S) FOR CCSJ: 6320-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12171703
Totals24990.000.000.000.0

CountyMADISON
HighwaySH0075
FromVARIOUS
ToVARIOUS
CSJ6321-01-001
Proj IDSUP - 632101001
Work TypeMADISON JANITORIAL
 
0.0106003.913302.0254.9
Work Order08-01-17
Work Began08-01-17
Work Completed
Time Computed08-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged184
Percent Time Used50
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6321-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07171701
Totals6003.91400.283302.0254.9

CountyWASHINGTON
HighwaySH0105
FromVARIOUS
ToVARIOUS
CSJ6321-46-001
Proj IDSUP - 632146001
Work TypePICNIC AREA MAINTENANCE
 
0.00135833.3616618.4846.3
Work Order08-07-17
Work Began08-01-17
Work Completed
Time Computed08-07-17
Contract Working Days365
Addl Days Granted0
Working Days Charged184
Percent Time Used50
Contractor(s)
TIBH INDUSTRIES, INC.
JUNCTION FIVE-O-FIVE
SUBCONTRACTOR(S) FOR CCSJ: 6321-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07171702
Totals35833.362786.4016618.4846.3

CountyWASHINGTON
HighwaySH0105
FromVARIOUS
ToVARIOUS
CSJ6321-54-001
Proj IDSUP - 632154001
Work TypeBUILDING JANITORIAL
 
0.00117219.378579.9349.8
Work Order08-07-17
Work Began08-02-17
Work Completed
Time Computed08-07-17
Contract Working Days364
Addl Days Granted0
Working Days Charged183
Percent Time Used50
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6321-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07171703
Totals17219.371217.208579.9349.8

CountyBURLESON
HighwaySH0021
FromVARIOUS
ToVARIOUS
CSJ6321-70-001
Proj IDRMC - 632170001
Work TypeCLEANING AND SEALING CRACKS
 
0.00192087.1791850.13100.0
Work Order12-11-17
Work Began11-07-17
Work Completed01-02-18
Time Computed12-20-17
Contract Working Days28
Addl Days Granted0
Working Days Charged5
Percent Time Used17
Contractor(s)
GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6321-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171704
Totals92087.1791850.1391850.13100.0

CountyBRAZOS
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6322-06-001
Proj IDSUP - 632206001
Work TypeLITTER PICKUP & DISPOSAL
 
0.0011393354.12456214.0332.7
Work Order10-23-17
Work Began09-30-17
Work Completed
Time Computed10-23-17
Contract Working Days365
Addl Days Granted0
Working Days Charged123
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6322-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07171704
Totals1393354.1286354.87456214.0332.7

CountyLEON
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6322-88-001
Proj IDSUP - 632288001
Work TypePICNIC AREA MAINTENANCE FOR LEON COUNTY
 
0.00138028.2413846.9436.4
Work Order09-13-17
Work Began09-13-17
Work Completed
Time Computed09-13-17
Contract Working Days364
Addl Days Granted0
Working Days Charged153
Percent Time Used42
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6322-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171702
Totals38028.242574.4813846.9436.4

CountyBURLESON
HighwayFM0050
FromVARIOUS
ToVARIOUS
CSJ6322-89-001
Proj IDSUP - 632289001
Work TypePICNIC/CAR POOL MAINT IN BURLESON COUNTY
 
0.00132332.3212146.1537.5
Work Order09-02-17
Work Began09-02-17
Work Completed
Time Computed09-02-17
Contract Working Days364
Addl Days Granted0
Working Days Charged152
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6322-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171703
Totals32332.322108.5912146.1537.5

CountyROBERTSON
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6322-90-001
Proj IDSUP - 632290001
Work TypePICNIC AREA & WEIGH STATION MAINTENANCE
 
0.01026528.989959.8837.5
Work Order10-04-17
Work Began09-02-17
Work Completed
Time Computed10-04-17
Contract Working Days364
Addl Days Granted0
Working Days Charged152
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
JUNCTION FIVE-O-FIVE
SUBCONTRACTOR(S) FOR CCSJ: 6322-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171704
Totals26528.981835.989959.8837.5

CountyGRIMES
HighwayBS0006S
FromVARIOUS
ToVARIOUS
CSJ6322-92-001
Proj IDSUP - 632292001
Work TypePICNIC AREA MAINTENANCE IN GRIMES COUNTY
 
0.00141135.0015940.3238.7
Work Order08-31-17
Work Began09-02-17
Work Completed
Time Computed09-02-17
Contract Working Days364
Addl Days Granted0
Working Days Charged152
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6322-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171705
Totals41135.003067.5615940.3238.7

CountyFREESTONE
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6322-93-001
Proj IDSUP - 632293001
Work TypeBUILDING JANITORIAL
 
0.00118242.527227.9039.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-03-17
Work Completed
Time Computed00-00-00
Contract Working Days363
Addl Days Granted0
Working Days Charged151
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6322-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08171706
Totals18242.521420.027227.9039.6

CountyWASHINGTON
HighwayUS0290
FromAT FM 389
ToAT FM 389
CSJ6323-33-001
Proj IDEMC - 632333001
Work TypeRETAINING WALL REPAIR
 
0.1332118568.001712775.0081.4
Work Order10-09-17
Work Began10-05-17
Work Completed
Time Computed10-09-17
Contract Working Days90
Addl Days Granted0
Working Days Charged106
Percent Time Used117
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6323-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10171740
Totals2118568.00310589.441712775.0081.4

CountyBRAZOS
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6323-71-001
Proj IDSUP - 632371001
Work TypeREMOVAL & DISPOSAL OF SCRAP RUBBER
 
0.010254659.8085827.0433.7
Work Order10-04-17
Work Began10-01-17
Work Completed
Time Computed10-04-17
Contract Working Days336
Addl Days Granted0
Working Days Charged123
Percent Time Used36
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171708
Totals254659.8018635.3685827.0433.7

CountyFREESTONE
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6324-01-001
Proj IDSUP - 632401001
Work TypePICNIC AREA MAINTENANCE
 
0.00121360.003822.5017.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-04-17
Work Completed
Time Computed00-00-00
Contract Working Days362
Addl Days Granted0
Working Days Charged89
Percent Time Used24
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171709
Totals21360.001265.003822.5017.8

CountyMILAM
HighwayFM1915
FromVARIOUS
ToVARIOUS
CSJ6325-33-001
Proj IDBPM - 632533001
Work TypeCONCRETE RIP RAP AND SCOUR REPAIR
 
0.10078905.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days10
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6325-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01181701
Totals78905.000.000.000.0

page 1 | page 2 | page 3 | page 4