Monthly State Let Construction Report For Atlanta District As Of Jan 10, 2018 Page 1 Of 3

Last Update: Wednesday, January 10, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTITUS ETC
HighwayUS 67 ETC
FromMORRIS C/L
To0.9 MI. E. OF FM 1402
CSJ0010-07-050
Proj IDSTP 2017(703)HESG
Work TypeTEXTURIZE SHOULDERS & CL TEXTURING
 
111.7101295587.02821449.4263.4
Work Order03-22-17
Work Began06-26-17
Work Completed
Time Computed05-22-17
Contract Working Days125
Addl Days Granted0
Working Days Charged106
Percent Time Used84
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0010-07-050
BRYDL CONTRACTING, INC. (2.77)
STRIPING SYSTEMS, INC. (0.16)
Contract #02173228
Totals1295587.020.00821449.4263.4

CountyBOWIE
HighwayUS 67
FromAT BASSETT'S CREEK
To.
CSJ0010-11-069
Proj IDBR 1702(389)
Work TypeCONCRETE STRUCTURE REPAIR
 
0.1291398421.50408513.3129.2
Work Order07-31-17
Work Began09-25-17
Work Completed
Time Computed08-30-17
Contract Working Days192
Addl Days Granted0
Working Days Charged71
Percent Time Used36
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0010-11-069
PANOLA SIGN & BARRICADE, INC. (1.00)
STRIPING TECHNOLOGY, L.P. (5.99)
DUSTIN ALLEN, INC. (15.22)
DUSTROL, INC. (0.88)
Contract #06173021
Totals1398421.5065359.35408513.3129.2

CountyBOWIE ETC
HighwayUS 67 ETC
From0.1 MI W OF SH 8
ToANDERSON CREEK
CSJ0010-11-070
Proj IDSTP 2018(188)
Work TypeSEAL COAT AND PAVEMENT MARKINGS
 
88.8903481443.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-15-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days55
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0010-11-070
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10173004
Totals3481443.500.000.000.0

CountyBOWIE
HighwayUS 67
FromAT IH 369 INTERSECTION
To.
CSJ0010-13-087
Proj IDSTP 2017(333)HES
Work TypeIMPROVE TRAFFIC SIGNAL
 
0.009566437.35543931.3596.0
Work Order01-17-17
Work Began05-30-17
Work Completed
Time Computed05-17-17
Contract Working Days203
Addl Days Granted0
Working Days Charged122
Percent Time Used60
Contractor(s)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0010-13-087
STRIPE-A-ZONE, INC. (4.40)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (2.85)
Contract #12163015
Totals566437.3585117.52543931.3596.0

CountyBOWIE ETC
HighwayFM 991 ETC
FromUS 67 W
ToUS 67 E
CSJ0010-19-010
Proj IDSTP 2018(037)HESG
Work TypePROFILE CENTERLINE & EDGELINE MRKS
 
136.1762282446.780.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-19-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days137
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0010-19-010
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09173003
Totals2282446.780.000.000.0

CountyBOWIE
HighwayUS 82
FromIH 369
ToUS 67
CSJ0046-06-079
Proj IDNH 1702(391)
Work TypePLANING, SURFACING & PAV MRKS
 
3.2101824808.251906851.9799.9
Work Order07-12-17
Work Began09-12-17
Work Completed
Time Computed08-11-17
Contract Working Days60
Addl Days Granted0
Working Days Charged72
Percent Time Used120
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0046-06-079
DUSTROL, INC. (7.61)
O. TREVINO CONSTRUCTION, LLC (5.60)
STRIPING TECHNOLOGY, L.P. (4.69)
TOTAL HIGHWAY MAINTENANCE, LLC (0.32)
BRENDA PRICE TRUCKING (0.30)
W.O.E. CONSTRUCTION (0.43)
STRIPING SYSTEMS, INC. (0.07)
TRP CONSTRUCTION GROUP, LLC (0.09)
Contract #06173208
Totals1824808.2512675.051906851.9799.9

CountyHARRISON
HighwayUS 59
From0.2 MI. S. OF IH 20
ToFM 1186
CSJ0063-01-088
Proj IDNH 1702(151)
Work TypePLANE ACP, ACP SURF, & PAV MARK
 
14.4615342972.805364758.0799.9
Work Order06-21-17
Work Began07-24-17
Work Completed
Time Computed07-21-17
Contract Working Days60
Addl Days Granted0
Working Days Charged56
Percent Time Used93
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0063-01-088
PANOLA SIGN & BARRICADE, INC. (0.12)
B & E CONSTRUCTION INC (4.57)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.75)
STRIPE-A-ZONE, INC. (2.99)
Contract #05173239
Totals5342972.8065459.405364758.0799.9

CountyHARRISON
HighwayUS 59
FromSH 43(S)
ToIH 20
CSJ0063-01-095
Proj IDNH 2018(384)
Work TypePLANE ACP, ACP SURF, & PAV MARK
 
2.2282387610.510.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days50
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0063-01-095
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183230
Totals2387610.510.000.000.0

CountyPANOLA ETC
HighwayUS 59 ETC
FromAT INTERSECTION OF FM 2792
To.
CSJ0063-10-013
Proj IDSTP 2018(351)HES
Work TypeSAFETY LIGHTING AT INTERSECTION
 
0.015260188.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SOUTH TEXAS ILLUMINATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0063-10-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173024
Totals260188.200.000.000.0

CountyPANOLA
HighwaySH 149
FromUS 79
To0.8 MI S. OF SH 315
CSJ0063-11-042
Proj IDSTP 2016(625)
Work TypeGR, STR, BS, SURF
 
1.98020892969.235008525.2823.9
Work Order08-05-16
Work Began09-08-16
Work Completed
Time Computed09-05-16
Contract Working Days540
Addl Days Granted5
Working Days Charged151
Percent Time Used27
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0063-11-042
PANOLA SIGN & BARRICADE, INC. (0.22)
WEST TEXAS RUMBLE STRIP (0.02)
CARRUTH NURSERY IRRIGATION & LANDSCAPE, INC. (0.51)
SCOTT DERR PAINTING CO, LLC (0.00)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.43)
OSCAR ORDUNO, INC. (0.57)
STRIPING TECHNOLOGY, L.P. (3.67)
CARTHAGE DRILLING, INC. (0.05)
DIRECTIONAL DRILLING (0.03)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.74)
ISAACS CONSTRUCTION SERVICES, LLC. (0.22)
TJT CONSTRUCTION (0.52)
RAYFORD"S TRUCK & TRACTOR (0.28)
Contract #04163202
Totals20892969.23284082.715008525.2823.9

CountyBOWIE
HighwayUS 259
FromAT RED RIVER
To.
CSJ0085-04-033
Proj IDBR 1402(085)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.4167588340.849284338.0799.9
CountyBOWIE
HighwayUS 259
FromON TEXAS SIDE OF RED RIVER BRIDGE
To.
CSJ0085-04-037
Proj IDBR 1402(202)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.3982462742.582503608.5699.9
CountyBOWIE
HighwayUS 259
FromON OKLAHOMA SIDE OF RED RIVER BRIDG
To.
CSJ0085-04-038
Proj IDCC 85-4-38
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.3981789824.15987882.1255.1
Work Order10-09-14
Work Began12-08-14
Work Completed
Time Computed12-08-14
Contract Working Days479
Addl Days Granted0
Working Days Charged241
Percent Time Used50
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0085-04-033
TOTAL HIGHWAY MAINTENANCE, LLC (0.83)
MOORE CONSTRUCTION, INC. (0.26)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (5.86)
DUSTROL, INC. (1.40)
WEST TEXAS RUMBLE STRIP (0.03)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.11)
MCL CONTRACTING, LLC (4.57)
PRIMATE CONSTRUCTION, INC. (0.12)
FARR FOUNDATION, INC. (0.59)
DUSTIN ALLEN, INC. (0.29)
ATS DRILLING, INC. (9.03)
H. V. CAVER, INC. (0.22)
Contract #08143008
Totals11840907.57241821.1612775828.7599.9

CountyBOWIE
HighwayUS 259
From0.1 MI. S. OF US 82 IN DEKALB
To0.3 MI. S. OF FM 44(S)
CSJ0085-04-035
Proj IDSTP 2013(615)
Work TypeGR,STR,BS,SURF & PAV MRK
 
2.9135371369.951836129.1934.1
Work Order05-16-17
Work Began06-20-17
Work Completed
Time Computed06-15-17
Contract Working Days317
Addl Days Granted0
Working Days Charged120
Percent Time Used37
Contractor(s)
H. H. HOWARD & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0085-04-035
HODGES AND SON CONSTRUCTION COMPANY, INC. (18.10)
MORRIS COUNTY CONTRACTORS, L.L.C. (2.02)
MURRAY CONSTRUCTION (0.52)
PANOLA SIGN & BARRICADE, INC. (0.38)
ISAACS CONSTRUCTION SERVICES, LLC. (0.41)
RK HALL, LLC (26.74)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.77)
STRIPE-A-ZONE, INC. (0.23)
TEXOP CONSTRUCTION (1.50)
STRIPING TECHNOLOGY, L.P. (2.66)
Contract #04173040
Totals5371369.95219095.061836129.1934.1

CountyHARRISON
HighwayUS 80
FromAT EAST LANSING ROAD INTERSECTION
To.
CSJ0096-07-047
Proj IDNH 2018(058)
Work TypeGR,STR,CMT TRT SUBGR,ACP,PM & TS
 
0.090482088.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-14-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days83
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0096-07-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09173013
Totals482088.800.000.000.0

CountyHARRISON ETC
HighwayUS 80 ETC
FromGREGG C/L
ToFM 450
CSJ0096-07-049
Proj IDSTP 2018(194)HES
Work TypeUPGRADE MBGF
 
66.709951647.730.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-15-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days155
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
B & E CONSTRUCTION INC
SUBCONTRACTOR(S) FOR CCSJ: 0096-07-049
PANOLA SIGN & BARRICADE, INC. (2.45)
DUSTIN ALLEN, INC. (49.14)
Contract #10173011
Totals951647.730.000.000.0

CountyPANOLA
HighwaySH 43
FromFM 959
ToRUSK C/L
CSJ0207-04-036
Proj IDSTP 2018(385)
Work TypePLANE ACP, ACP SURF, & PAV MARK
 
4.0852083697.620.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0207-04-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183207
Totals2083697.620.000.000.0

CountyBOWIE
HighwayUS 71
FromAT US 67 INTERSECTION
To.
CSJ0217-02-035
Proj IDSTP 1702(446)HES
Work TypeIMPROVE INTERSECTION SAFETY
 
0.203435854.530.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-14-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days160
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0217-02-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11173217
Totals435854.530.000.000.0

CountyBOWIE
HighwayUS 59
FromAT FM 989
To.
CSJ0218-01-095
Proj IDSTP 2018(352)HES
Work TypeSIGNALS & SAFETY LIGHTING
 
1.000175785.350.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days72
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SOUTH TEXAS ILLUMINATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0218-01-095
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173011
Totals175785.350.000.000.0

CountyTITUS
HighwayUS 271
FromAT RIPLEY CREEK
To.
CSJ0221-05-064
Proj IDBR 1702(392)
Work TypeREPLACE BRIDGES AND APPROACHES
 
1.1178911050.613065342.6534.3
Work Order07-20-17
Work Began08-14-17
Work Completed
Time Computed08-21-17
Contract Working Days325
Addl Days Granted0
Working Days Charged83
Percent Time Used25
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0221-05-064
STRIPING TECHNOLOGY, L.P. (1.23)
ISAACS CONSTRUCTION SERVICES, LLC. (1.56)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.31)
TOTAL HIGHWAY MAINTENANCE, LLC (0.36)
TEXOP CONSTRUCTION (1.47)
ODUM SERVICES, L.P. (1.63)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.07)
SCOTT DERR PAINTING CO, LLC (0.08)
BOWMAN ENGINEERING & CONSULTING, INC (0.11)
Contract #06173205
Totals8911050.611037821.373065342.6534.3

CountyTITUS
HighwaySH 49
FromAT ARIZONA STREET INTERSECTION
To.
CSJ0248-01-072
Proj IDSTP 1702(393)HES
Work TypeIMPROVE INTERSECTION SAFETY
 
0.009418186.60164177.4039.2
Work Order07-14-17
Work Began11-29-17
Work Completed
Time Computed11-13-17
Contract Working Days161
Addl Days Granted0
Working Days Charged23
Percent Time Used14
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0248-01-072
CARTHAGE DRILLING, INC. (4.70)
PANOLA SIGN & BARRICADE, INC. (2.56)
Contract #06173031
Totals418186.6035280.00164177.4039.2

CountyTITUS
HighwayUS 271
From0.7 MI. N. OF FM 3417
To0.3 MI. S. OF FM 3417
CSJ0248-01-077
Proj IDNH 1702(147)
Work TypeGR,STR,CONC PAVMT,& PAV MK
 
1.10512222495.523199646.3326.1
Work Order06-26-17
Work Began07-26-17
Work Completed
Time Computed07-26-17
Contract Working Days208
Addl Days Granted12
Working Days Charged63
Percent Time Used28
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0248-01-077
STRIPING TECHNOLOGY, L.P. (2.28)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.23)
JOHN WRIGHT CONSTRUCTION (0.79)
CARRUTH NURSERY IRRIGATION & LANDSCAPE, INC. (1.43)
BOWMAN ENGINEERING & CONSTRUCTION, INC. (3.41)
MORRIS COUNTY CONTRACTORS, LLC (0.56)
PANOLA SIGN & BARRICADE, INC. (0.13)
CF SOUTHWEST ENVIRONMENT SERVICES LLC (1.86)
DIAMOND SURFACE, INC. (0.06)
ISAACS CONSTRUCTION SERVICES, LLC. (0.17)
BOWMAN ENGINEERING & CONSTRUCTION, INC. (0.07)
Contract #05173039
Totals12222495.52252338.613199646.3326.1

page 1 | page 2 | page 3