Monthly State Let Construction Report For Amarillo District As Of Jan 10, 2018 Page 2 Of 2

Last Update: Wednesday, January 10, 2018
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHANSFORD
HighwaySH 15
FromSH 136 IN GURVER
ToSH 207 IN SPEARMAN
CSJ0308-02-029
Proj IDSTP 1602(139)
Work TypeRESTORATION OF EXISTING ROADWAY
 
19.9009135715.427080952.7377.5
Work Order07-28-16
Work Began00-00-00
Work Completed
Time Computed08-26-16
Contract Working Days210
Addl Days Granted20
Working Days Charged151
Percent Time Used65
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0308-02-029
H & F TRUCKING (22.50)
WOLFE CONSTRUCTION GROUP, INC. (0.08)
DUSTROL, INC. (0.37)
BARRICADES UNLIMITED (1.27)
HJC FARMS, INC. (0.00)
Contract #05163030
Totals9135715.421288666.057080952.7377.5

CountyLIPSCOMB
HighwaySH 15
FromFM 1455
ToOKLAHOMA STATE LINE
CSJ0355-01-048
Proj IDSTP 1602(191)
Work TypeOVERLAY
 
12.3624980635.65653100.0013.1
CountyLIPSCOMB
HighwaySH 15
FromOCHILTREE COUNTY LINE
To1000' EAST OF COUNTY ROAD 4
CSJ0355-02-031
Proj IDSTP 1602(191)
Work TypeOVERLAY
 
3.118986876.400.000.0
CountyLIPSCOMB
HighwaySH 23
FromFM 377
To11.05 MILES NORTH OF US 83
CSJ1337-01-023
Proj IDSTP 1602(191)
Work TypeOVERLAY
 
10.0632183107.752255986.8499.9
Work Order08-05-16
Work Began00-00-00
Work Completed
Time Computed09-04-16
Contract Working Days77
Addl Days Granted0
Working Days Charged70
Percent Time Used90
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0355-01-048
BARRICADES UNLIMITED (2.40)
Contract #06163023
Totals8150619.800.002909086.8435.6

CountyROBERTS
HighwaySH 70
FromNORTH CANADIAN RIVER BRIDGE
ToOCHILTREE COUNTY LINE
CSJ0490-04-037
Proj IDSTP 2014(579)
Work TypeREHABILITATE EXISTING ROADWAY
 
5.8485139086.585207476.3399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-18-14
Work Began12-10-14
Work Completed
Time Computed09-02-14
Contract Working Days197
Addl Days Granted40
Working Days Charged341
Percent Time Used143
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0490-04-037
BARRICADES UNLIMITED (0.99)
HJC FARMS, INC. (3.77)
HUDSON, INC. (0.81)
TEXAS ALTERNATIVE GRASSER, INC. (0.43)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.84)
WEST TEXAS RUMBLE STRIP (0.08)
W.S. CONSTRUCTION COMPANY (5.84)
E. DIAZ TRUCKING (2.85)
Contract #04143003
Totals5139086.580.005207476.3399.9

CountyMOORE
HighwaySH 152
FromDUMAS CITY LIMITS
ToHUTCHINSON COUNTY LINE
CSJ0557-01-028
Proj IDSTP 2016(683)
Work TypeRESTORATION
 
47.26315561610.5317528755.8499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-24-16
Work Began07-06-16
Work Completed
Time Computed06-23-16
Contract Working Days130
Addl Days Granted20
Working Days Charged129
Percent Time Used86
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0557-01-028
BARRICADES UNLIMITED (0.84)
DUSTROL, INC. (2.04)
W.S. CONSTRUCTION COMPANY (1.58)
CF TRUCKING, LLC (1.46)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.11)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.15)
HJC FARMS, INC. (0.21)
VANCE BROTHERS, INC. (5.72)
Contract #02163003
Totals15561610.530.0017528755.8499.9

CountyDALLAM
HighwayFM 1727
FromFM 3310
To7 MI WEST OF FM 3489
CSJ0794-01-018
Proj IDSTP 1502(296)HES
Work TypeWIDEN ROADWAY FOR SAFETY
 
11.3626170063.746346223.6199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-16-15
Work Began02-24-16
Work Completed
Time Computed01-11-16
Contract Working Days114
Addl Days Granted19
Working Days Charged150
Percent Time Used112
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0794-01-018
BARRICADES UNLIMITED (0.73)
LANCO TURF & SEEDING, INC. (0.30)
COWBELL TRAFFIC SERVICES, INC. (0.40)
HJC FARMS, INC. (1.37)
E. DIAZ TRUCKING (2.28)
STRIPE-A-ZONE, INC. (0.24)
HOLMES CONSTRUCTION CO., L.P. (0.31)
Contract #06153218
Totals6170063.740.006346223.6199.9

CountyPOTTER
HighwayVA
FromAT VARIOUS LOCATIONS IN AMARILLO
To.
CSJ0904-00-160
Proj IDSTP 2015(649)
Work TypeCONSTRUCT CURB RAMPS
 
0.0012895601.552981454.2599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-08-15
Work Began07-06-15
Work Completed
Time Computed05-24-15
Contract Working Days274
Addl Days Granted14
Working Days Charged300
Percent Time Used104
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-160
ONE WAY CONCRETE (56.56)
BTA SERVICES, LTD. (1.91)
W.A. ROBBINS CONSTRUCTION CO., INC. (6.35)
QLVS, INC. DBA PHASE 3 ELECTRIC (1.30)
PAVEMENT MARKINGS INC. (2.36)
Contract #03153026
Totals2895601.550.002981454.2599.9

CountyPOTTER
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0904-00-164
Proj IDSTP 2017(593)
Work TypeTHERMOPLASTIC STRIPING
 
1.0001085462.591384436.0799.9
Work Order03-15-17
Work Began00-00-00
Work Completed
Time Computed04-14-17
Contract Working Days72
Addl Days Granted33
Working Days Charged104
Percent Time Used99
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-164
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173034
Totals1085462.590.001384436.0799.9

CountyPOTTER
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0904-00-169
Proj IDSTP 2018(003)
Work TypeCRACK SEAL
 
1.000839950.50585959.8569.7
CountyPOTTER
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0904-00-177
Proj IDC 904-00-177
Work TypeCRACK SEAL
 
1.000155791.90111758.9071.7
Work Order11-13-17
Work Began00-00-00
Work Completed
Time Computed11-13-17
Contract Working Days60
Addl Days Granted0
Working Days Charged21
Percent Time Used35
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-169
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10173224
Totals995742.40697718.75697718.7570.0

CountyPOTTER
HighwayCR
FromON DEWEY AVE AT WEST AMARILLO CREEK
To.
CSJ0904-02-037
Proj IDBR 2014(554)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.0411220116.751369746.18100.0
Work Order06-22-16
Work Began06-28-16
Work Completed10-13-17
Time Computed06-29-16
Contract Working Days56
Addl Days Granted27
Working Days Charged95
Percent Time Used114
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-02-037
BARRICADES UNLIMITED (0.31)
L. A. FULLER & SONS CONSTRUCTION, LTD. (1.87)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (13.83)
SOUTH TEXAS PAINTING COMPANY (0.62)
WOLFE CONSTRUCTION GROUP, INC. (0.27)
MCL CONTRACTING, LLC (0.77)
Contract #04163235
Totals1220116.750.001369746.18100.0

CountyHARTLEY
HighwayFM 767
FromAT PUNTA DE AGUA CREEK
To.
CSJ1108-01-020
Proj IDBR 2018(436)
Work TypeBRIDGE REPLACEMENT
 
0.5314253525.120.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days280
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1108-01-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183019
Totals4253525.120.000.000.0

CountyPOTTER
HighwayRM 1061
FromFM 2381
To7.5 MILES NORTH OF FM 2381
CSJ1245-02-043
Proj IDSTP 1502(299)HES
Work TypeWIDEN ROADWAY FOR SAFETY
 
10.5397907537.757828291.3098.9
CountyPOTTER
HighwayRM 1061
From10.50 MILES NORTH OF FM 2381
ToOLDHAM COUNTY LINE
CSJ1245-02-044
Proj IDSTP 1502(355)
Work TypeADD PASSING LANES FOR SAFETY
 
12.8372230786.342411533.7999.9
Work Order08-20-15
Work Began02-03-16
Work Completed
Time Computed08-03-15
Contract Working Days234
Addl Days Granted19
Working Days Charged238
Percent Time Used94
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1245-02-043
BARRICADES UNLIMITED (1.85)
HJC FARMS, INC. (1.25)
W.S. CONSTRUCTION COMPANY (9.93)
WILLIS ELECTRIC CO., LP (0.46)
Contract #06153245
Totals10138324.090.0010239825.0999.9

CountyHEMPHILL
HighwayRM 2654
FromSH 33
ToFM 277
CSJ2612-01-011
Proj IDSSW 2612-1-11
Work TypeSAFETY WIDENING OF ROADWAY
 
8.2155653751.985587891.9198.8
Work Order09-16-16
Work Began02-01-17
Work Completed
Time Computed10-17-16
Contract Working Days272
Addl Days Granted0
Working Days Charged166
Percent Time Used61
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2612-01-011
AOC ENVIRONMENTAL, INC. (0.70)
BARRICADES UNLIMITED (0.65)
DOUBLE A CONTRACTING, L.P. (0.96)
DUSTROL, INC. (1.26)
HJC FARMS, INC. (2.76)
HODGES AND SON CONSTRUCTION COMPANY, INC. (8.74)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC (13.65)
O. TREVINO CONSTRUCTION, LLC (1.34)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.87)
W.O.E. CONSTRUCTION (0.18)
WILLIS ELECTRIC CO., LP (0.39)
S & S BRIDGE PAINTING, INC. (0.74)
Contract #07163219
Totals5653751.9870756.395587891.9198.8

CountyRANDALL
HighwayLP 335
FromIH 27, E
ToBNSF RR
CSJ2635-02-022
Proj IDDMO 2012(189)
Work TypeADDITIONAL 2 LANES AND BRIDGES
 
3.00032232646.8627091628.4684.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-04-14
Work Began11-03-14
Work Completed
Time Computed03-20-14
Contract Working Days645
Addl Days Granted180
Working Days Charged168
Percent Time Used36
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2635-02-022
ALAMO BROTHERS CONCRETE, INC. (7.46)
BARRICADES UNLIMITED (1.53)
LONE STAR PRODUCTS (FLOWER MOUND) (0.00)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.73)
MCL CONTRACTING, LLC (0.04)
PENHALL COMPANY (AUSTIN) (0.02)
WILLIS ELECTRIC CO., LP (2.97)
SCOTT DERR PAINTING CO, LLC (0.12)
DUSTIN ALLEN, INC. (0.00)
Contract #12133202
Totals32232646.860.0027091628.4684.0

page 1 | page 2