As the I-635 Managed HOV Lanes Project advances, a summary of project activity and public information documents will be available through this page.
Early 2016
- Estimated completion date
January 2011
- Construction begins on Jan. 18, 2011.
December 2010
- Approval to being detailed work on Dec. 19, 2010
June 2010
- LBJ Infrastructure Group obtains financial close on June 22, 2012.
September 2009
- Comprehensive Development Agreement executed with LBJ Infrastructure Group on Sept. 4, 2009.
May 2009
- Financial Disclosure Public Hearing on May 7, 2009
March 2009
February 2009
- New LBJ Project Overview Fact Sheet
- Texas Transportation Commission determines best apparent value
January 2009
June 2008
- FHWA environmentally approves updates to LBJ Managed HOV Lanes Project
March 2008
February 2008
November 2007
October 2007
September 2007
August 2007
June 2007
November 2006
- 16th Public Meeting (11/16/06)
August 2006
May 2006
January 2006
November 2005
May 2005
- TxDOT issues Request for Qualifications for LBJ Managed HOV Lanes Project
June 2004
I-635 Corridor Coalition requests TxDOT deliver LBJ managed HOV lanes as a CDA
December 2002 - April 2004
- TxDOT receives Environmental Clearance for the LBJ Managed Lanes Projects
More Information