Once a difference in grade has been identified in the design process, the
decision must be made to construct a slope or a retaining wall. If adequate
space exists, consider a slope. A retaining wall is required if adequate space
is not available. Maximum slope steepness is dictated by the quality of fill
soil available and whether or not the slope will be protected with riprap to
eliminate the need for mowing and other maintenance.
Consider the following criteria in choosing a retaining wall: cut or fill
determination, constructibility and aesthetics.
|
Cut or Fill Determination |
|
The first step in wall selection is to determine whether a
wall will be built in a cut or fill situation. Use fill type
walls in fill situations. While fill walls can be built in
cuts, the opposite is not true for all cut walls. The
construction of fill walls in cuts requires additional
excavation behind the face of wall and, possibly, temporary
shoring.For fill walls built in cuts, the cost of the wall,
excavation, and shoring can exceed the cost of a more
suitable cut wall. Wall conditions that determine wall type
selection are fill condition, cut/fill condition, and cut
condition.
Fill Condition
Two common fill
conditions are:
1. Level Ground
This condition is best represented by at-grade
crossings that are upgraded to grade separations by raising one roadway
above the other. This is accomplished by placing fill for the approach to
the new, elevated structure.
Approach retaining walls are commonly needed in
urban areas due to the lack of available right-of-way for side slopes. The
most common fill walls in this situation are mechanically stabilized earth
(MSE) or concrete block.
2. Slopes
Fill walls placed on slopes require special
consideration. Typical fill walls, such as MSE or concrete block built on
slopes, require that a bench be cut into the slope for wall construction.
The back of the bench may need to be supported with temporary shoring.
Consider other wall types if the fill will extend into water. MSE and
concrete block walls can be built if the water can temporarily be lowered or
a cofferdam easily and economically constructed. This assumes that shoring
will not be needed for the excavation back into the slope for the wall
construction. Consider the costs of other wall types, such as sheet piling,
if cofferdams or temporary shoring are required for construction. See the
following diagram of fill on slope.

Cut/Fill Condition
This condition consists of placing fill on the
upper portion of a slope and removing the lower portion of the slope. This
condition is typically encountered when upgrading controlled access facilities
when both the main lanes and frontage roads are widened. See the following
diagram of a cut/fill condition.

Consider the following wall types for this situation:
- L-shaped spread footing
- MSE or Concrete block walls. These wall types require that adequate space
be available to excavate into the slope. The back of the bench must either
be shored or sloped the same as for fill walls on slopes. Other wall types
may be more economical if temporary shoring is necessary.
- Drilled shaft walls. Depending on the location of the wall on the slope,
the drilled shafts may be constructed in one or two stages. If the wall is
closer to the top of the slope, temporary fill may be placed to allow the
shafts to be constructed in one stage. If temporary fill is not used, the
portion of the shaft below the existing ground line is constructed first,
and then the portion above ground is formed and poured as a column. In firm
soil or rock, drilled shaft walls can be an economical alternative.
- Tied-back walls. Use these walls only in a cut/fill situation when the
existing ground line is closer to the top of the wall (located in the upper
half of the wall) than the bottom. Place and compact any fill before
installing soldier piling. Typically tied-back walls are economical only
when significant quantities are used on a project.
- Sheet pile walls. Sheet pile walls have occasionally been used in a
cut/fill situation. The ground must be soft enough to a depth of one to two
times the wall height to allow the piling to be driven. It is difficult to
advance sheet piling in material stiffer than 12 in./100 blows.
- L-shaped spread footing. This wall type is commonly used when a small cut
is made at the base of a slope. The lack of a heel minimizes the excavation
required behind the wall.
Cut Condition
In this condition, the primary operation is removing
ground with little or no fill placed. The wall choices for this condition are
similar to those for the cut/fill condition. The same considerations apply,
except that tied-back and drilled shaft walls are easier to construct. See the
following diagram of a cut condition. Other cut wall types to consider here are
soil or rock nailed walls.

Soil and rock nailed walls may be constructed in any cut situation but are
best suited for low headroom situations under structures. This is the wall of
choice for turn-around wall construction under bridges. The top of wall should
be no more than 2 ft. above the existing grade.
|
|
|
Constructibility |
|
Drilled shaft and tied-back walls require drilling a
vertical hole in the ground. This dictates that adequate overhead clearance be
available for drilling equipment. If clearance is not available, low headroom
drilling equipment may be used and shaft reinforcement or soldier piling members
spliced as they are inserted in the hole. These operations increase costs
considerably. In a low headroom situation, a nailed wall is the first choice.
Horizontal clearance is a consideration for tied-back and nailed walls.
Tie-backs are often installed with a continuous flight auger somewhat longer
than the depth of the hole, which means 50+ ft. of horizontal clearance is
desired. Sectional augers may be used in limited clearance areas. Nails, being
shorter, typically need around 20 ft. of clearance for installation. Because of
the minimum size of common drilling equipment used, 20-ft. horizontal and 6-ft.
vertical clearances should be considered minimum clearances.
|
|
|
Aesthetics |
|
The final criterion is aesthetics, a difficult area because opinions vary
widely. Within reason, most aesthetic treatments can be accomplished
independently of wall type. Some walls such as concrete block walls, however,
have an appearance so unique that it cannot be duplicated by another wall type.
However, concrete block facing elements can be used with another type wall to
accomplish the aesthetic goal. Contact the Bridge Division for assistance
designing aesthetic treatments for walls. The aesthetic treatment of retaining
walls may involve items such as:
- Form liners to produce various surface finishes
- Paints, stains, or colored concrete to color surfaces
- Various wall geometries to accommodate landscaping
Depending on the treatment selected, cost may not be significantly affected.
The use of simple form liners can be economical, and colored concrete can be
expensive. Normal field surface finishing of colored concrete can yield variable
colors.
Consider also the amount of interaction that will occur between the motoring
public and the aesthetic treatment. A complicated graphic next to a high-speed
roadway is a blur to most passing motorists, who might view the graphic for only
tenths of a second. In this case, a simple form liner might be a more
appropriate treatment. If a wall faces a park or other public area, more
elaborate treatments may be warranted.
Potential wall distortions during construction or after construction may
significantly affect the appearance of the aesthetic. MSE walls, for example,
are flexible wall systems that experience some movement over the life of the
wall.
Aesthetic treatments with landscaping in conjunction with retaining walls
should be done carefully. If extensive watering of landscaping is anticipated,
additional drainage measures may be needed to ensure that excessive pressures do
not build up behind walls.
|
|
|
Alternate Walls |
|
It is sometimes difficult to pick the most suitable wall for a cut or cut/fill
condition. The designer may not be able to evaluate factors that a contractor
considers important, such as equipment availability or haul cost for excavated
soil for MSE wall construction in a cut. In such instances, it is best to
include several wall types in the plans so that the contractor can determine the
most economical choice.When dissimilar wall types are included in the plans for
a single wall, present the wall types as alternates so that the appropriate bid
items may be included in each alternate. An MSE wall alternate in a cut must
include an item for temporary shoring, whereas the tied-back alternate would not
need a shoring item. See the following wall selection flow chart.

|
|
|
Wall Layout Considerations |
|
Carefully consider the location of retaining walls. The location of a wall can
affect the wall quantity significantly.Embankment Side Slopes
Consider a typical grade separation where inadequate right of way requires
retaining walls to be placed along the approach embankment. In these situations,
the walls can be placed at the edge of the upper roadway with the top of wall
coincident with the top of the embankment or at some distance from the edge of
pavement with the slope extending from the edge of pavement to the top of wall.
Placing the wall coincident with the edge of pavement requires an expensive
concrete rail on top of the wall and eliminates any possibility for a future
widening of the upper roadway; however, it improves the long-term serviceability
of the wall. Placing the wall a distance from the edge of pavement requires the
use of a guard fence or concrete barrier at the edge of the pavement. It also
allows future widening of the upper roadway if the provisions are made in the
design and detailing of the wall.
Widening Fill Sections
Fill sections that are being widened present
special considerations. Typically some soil must be excavated to allow
construction of an MSE wall. Placing the face of wall as close as possible to
the toe of existing slope minimizes excavation and temporary shoring. Placing
the wall close to the existing top of embankment requires use of a cut-type wall
or a fill-type wall with extensive shoring.
Depressed Sections
In depressed sections, consider additional width
for the lower roadway to allow for future lane additions. Once retaining walls
are in place, they cannot be moved to accommodate future width requirements.
Bridge Abutments
Place retaining walls a reasonable distance in
front of bridge abutments to allow adequate clearance for wall construction. For
most retaining walls, the face of the wall should be at least 1.5 to 3 ft. in
front of the face of the abutment cap. For tied-back and MSE walls, this is
especially critical because the tiebacks and wall reinforcements may need to be
skewed around the abutment foundations. To improve the appearance of walls,
control of the top of wall profile with vertical curves rather than discreet
elevations at specific points results in a much smoother top of wall.
Structures behind Walls
Consider the proximity of a retaining wall
to structures behind the wall. MSE walls are usually placed at least 1-3 ft. in
front of foundation to allow space for attachment of the reinforcements to the
facing panels and skewing of the reinforcements.
|
|
|
Stability Considerations |
|
Unlike foundation failures, which can occur slowly over a period of years,
retaining walls can fail rapidly in stability with catastrophic results. The
failure of retaining walls can close a transportation facility just as quickly
as a bridge failure. As a result, thoroughly investigate retaining wall
stability. Stability analysis should be conducted for both short- and long-term
conditions.Sliding and Overturning
Sliding involves the lateral
translation of a wall due to inadequate resistance to movement at the base of
the wall. Past failures have involved marginal soil at the base of walls.
Overturning does not involve the soil under the wall but only the mass of the
wall to resist the soil driving forces behind the wall. Because the driving
forces are applied to the wall at roughly two-thirds the wall height above the
base, the wall has a tendency to overturn if the wall mass or geometry is
inadequate. Consult the governing standard for minimum factors of safety for
these two modes of failure.
Eccentricity
The combination of vertical and horizontal loads on a
wall combine to produce a resultant force at the base of a wall, which is not at
the middle of the footing. The distance between the middle of the footing and
the location of the resultant force is the eccentricity. The location of the
resultant force is limited to the middle third of the footing to ensure that the
rear part of the footing does not lift off the ground.
Bearing Pressure
As a result of the weight of the wall mass and the
active driving forces behind a wall, pressure is exerted on the foundation soil
along the base of a wall. The pressure is greatest at the toe of the wall. If
the ultimate bearing capacity of the soil under the toe of the wall is exceeded,
the toe of the wall can plunge down into the foundation soil. The result is a
local distortion of the wall face. A safety factor of 2.0 in bearing capacity is
recommended.
Rotational Stability
Rotational failures of walls encompass the
entire wall as well as a portion of the retained soil. This type of failure does
not depend on the wall design specifically but more on the strength of the
foundation and retained soil. Computer programs can evaluate rotational
stability. A safety factor of 1.3 or higher is usually considered adequate.
Settlement
Settlement can be significant when walls are constructed
on soil softer than approximately 5/12 in. TCP. Settlement is mainly a problem
in the coastal areas of the state where soil softer than 2/12 in. occurs to
depths of 20 to 50 ft. If a bridge approach embankment is constructed over soil
subject to significant settlement, try either to allow as much settlement to
occur before completing the approach or to support the embankment with a
foundation improvement such as stone columns.
Settlement can be accelerated by
installing vertical drains through the compressible subsoil. Construction of
embankments on very soft soil is also likely to result in rotational stability
failures during construction if no precautions are taken. When encountering
significant layers of soft soil, obtain samples for consolidation testing to
determine potential settlement. Note that data obtained from consolidation
testing is only approximate. Predictions of total settlement based on such data
are commonly higher than observed in the field, and the time predicted for such
settlement to occur can be incorrect by an order of magnitude.
Temper any values
calculated for settlement with previous experience in the area. When significant
settlement is anticipated, the best solution may be to lengthen the bridge and,
thereby, reduce the height of the approach. This is often the most economical
and practical solution.
|
|
|
Design Procedures |
|
The design of retaining walls requires a thorough knowledge of structural and
geotechnical engineering. This does not mean that one person has to design every
aspect of a retaining wall. Design loads and allowable pressures recommended by
a geotechnical engineer are often later used by a structural engineer to design
the wall. The following design procedures convey general methods and do not
address every design situation.Earth Pressure Distribution
Determine
the pressure applied by soil on a retaining structure by different methods
depending upon the wall type. The soil behind walls, which are free to deflect
or move in response to the applied loads, is considered to achieve the active
state. For this condition, calculate the earth pressure based on Rankine's or
Coulomb's methods. The pressure distribution is triangular in shape with the
maximum pressure occurring at the bottom of the wall. This is the case for
spread footing, MSE, drilled shaft, and sheet pile walls. Usually soil pressure
is assumed to increase downward at a rate of 40 psf per ft. of depth.
Structures such as tied-back walls or braced excavation shoring are more or
less fixed and, therefore, unable to achieve the active state. For this
condition, use an earth pressure distribution as proposed by Terzaghi and Peck.
The pressure distribution is in the shape of a trapezoid.
Internal Analysis
Internal analysis refers to the design of the wall
structure to resist the stresses induced by the earth pressure applied to the
wall. This aspect of design comprises mostly structural engineering. The various
elements of the wall must be designed to carry the stresses generated so that an
adequate factor of safety is attained.
- Mechanically Stabilized Earth (MSE) Walls: The internal design of MSE walls involves checking the earth reinforcements for allowable stresses
and anchorage into the mass of select fill behind the face. Make allowances
for metal section loss on the reinforcements when computing tensile
stresses. Alter the reinforcement density and size to attain proper stresses
and anchorage. The overall dimension of the reinforced mass is governed by
external stability.
- Tied-back Walls: The internal design of tied-back walls involves
the analysis of a continuous beam (soldier pile) to determine the support
reactions (tied-back loads) for an applied load diagram (earth pressures).
Correct the tied-back loads determined by the continuous beam analysis to
account for the anchor inclination. Select a soldier pile that will
adequately resist the maximum bending moments from the continuous beam
analysis. Then design the wall facing that spans between the soldier piling.
Analyze this as a simple beam to support the maximum soil pressure. Then
design the facing-soldier pile connection. The typical soil loading is
trapezoidal with a maximum intensity of 36H psf (where H is the wall height
in feet). Walls supporting rock are designed for a 25H psf trapezoidal
pressure distribution. Design pressures higher than 36H may be justified if
walls are constructed in expansive soil.
- Drilled Shaft and Sheet Pile Walls: The design of these walls
involves the analysis of a continuous beam on nonlinear supports. The
nonlinear supports model the soil in which the beam is embedded. This
approach accounts for the bending stiffness of the shaft or pile foundation
unlike other methods, which consider the foundation to be infinitely stiff.
Use the computer program COM624 or LPILE to conduct the analysis. Use the
program to determine the foundation response to the applied load for a range
of embedment depths. Determine a foundation length by examining the
embedment-deflection relationship for a suitable deflection either at the
ground line or the top of wall.
External Analysis
The external analysis of walls examines whether
walls stay where built. A number of failures of walls and embankments prove that
external stability is just as important as internal design. External stability
is routinely evaluated for fill-type walls. Cut-type walls are not routinely
checked for external stability due to the different approaches to their design.
However, if exceptionally soft soil is present, check the various aspects of
external stability for cut-type walls. As always, sound engineering judgment
should prevail.
- Sliding and Overturning: Sliding of a retaining wall occurs when
the active driving forces from the soil behind the wall exceed the
frictional or cohesive forces along the base of the wall and the passive
resisting force in front of the wall. Whether to include passive forces in
front of a wall depends on whether that soil will be present during
construction or at some future date. For most calculations, the subsoil is
assumed to be cohesionless with an angle of friction of 30 deg. The
resistance to sliding is the weight of the wall and soil comprising the wall
times the tangent of 30 deg. (0.58), a valid assumption unless soil borings
indicate it is not conservative. When a questionable soil is present, use
triaxial testing to determine the cohesion and angle of friction, which you
can then use to determine sliding resistance. Overturning occurs when the
active driving forces exceed the gravitation resisting forces of the wall
mass. The mass of the wall is considered the reinforced volume for an MSE
wall or the weight of the concrete and soil above the heel for a spread
footing wall. The safety factor is determined by adding moments about the
toe of the wall.
- Eccentricity: The eccentricity is the sum of the moments of the
forces acting at the base of the wall divided by the sum of the vertical
forces. The moments are normally calculated at the rear of the base of the
wall.
- Bearing Pressure: Bearing capacity failures under walls involve
the displacement of soil from under the wall. Use bearing capacity equations
to determine the ultimate capacity of the foundation soil. These equations
require cohesion and friction values determined by triaxial testing. If this
data is not available, use Texas cone penetration data to obtain allowable
bearing pressures from the drilled shaft and spread footing design chart.
The classical bearing capacity equation for the ultimate soil pressure is:

where Nc, Nq, Ng are
theoretical factors based on the geometry of the failing mass of soil
beneath a footing, c is the soil cohesion, and g is the density of the soil.
A safety factor of two is typically required for bearing capacity. The
following figure gives these factors.

-
Rotational Stability: Rotational stability of walls
is a special case of slope stability. The limits of the wall affect where a
potential failure surface can develop. The failure surface for a rotational
failure can be either circular or noncircular depending on the
stratification of the foundation soil. For walls on uniform soft clay, the
failure surfaces tend to be circular. If the soft zone is fairly thin, the
failure surface tends to be noncircular following the soft zone. TxDOT uses
both the GSTABL 7 and UTEXAS computer programs to analyze for stability.
While the subsoil can be tested in advance to obtain strength data for
analysis, the future embankment material properties are unknown. An accurate
answer is difficult to obtain because normally about half of the failure
surface passes through the embankment behind a fill wall. Local experience
may provide some insight into the strength of the proposed fill. While
computer programs are used to evaluate wall stability, an approximate hand
check of the results may be conducted by the method of slices.
|
|
|
Recommended Construction
and Maintenance System Selection |
|
ResponsibilityThe project engineer must ensure that the retaining wall
system selected for a given location is appropriate. MSE wall suppliers are only
responsible for the internal stability of their walls. The overall (global)
stability of an MSE wall system is the responsibility of the engineer who
selects this type of wall for inclusion into the plans.
Geometry
Location geometry most often dictates the selection of a retaining wall system.
The Geotechnical Manual offers information regarding evaluation of geometry and
selection of various wall types. MSE walls are commonly used on TxDOT projects;
however, in many situations--especially cuts--MSE may not be the most
appropriate wall type. Often the additional excavation and shoring required for
installation of MSE walls in cut situations make them uneconomical and difficult
to construct. Sometimes MSE walls are selected because only a geometric layout
and a standard sheet are required in the plans (the final detailed drawings are
produced as shop drawings). This minimal design effort up front makes MSE walls
a popular choice among engineers with limited time and resources. Although
tied-back, soil nailed, drilled shaft and spread footing walls all require
considerably more design effort and time, they are preferable in some cut
situations.
The stability of each proposed retaining wall installation must be evaluated.
Usually this involves a simple review of the wall height, site geometry, and
soil borings. Walls with heights of 20 feet or less, situated on level ground,
with soils borings indicating Texas Cone Penetrometer (TCP) blow counts in
excess of 20 blows per foot should not require a detailed analysis. Walls taller
than 20 feet, situated on slopes, or on soils weaker than 20 blows per foot
should be looked at more closely. In general, place walls on any slope steeper
than 4:1 only with a careful review of both short and long-term stability. Of
particular concern are walls placed on freshly cut slopes, where the soil data
may indicate high strengths at the excavation level. Freshly exposed material
will soften with time, and an assessment of long-term strengths must be made
when analyzing walls in this situation. Local districts may want to modify these
guidelines based on their experience with specific projects and local
conditions.
Soil Characteristics
The Texas Cone Penetrometer is poorly
correlated for very low soil strengths and may yield overly conservative
results. When evaluating stability of walls on soils weaker than 20 blows per
foot, it may be appropriate to conduct laboratory or in-situ testing in addition
to the TCP. Triaxial or direct shear laboratory tests will generally yield more
accurate soil strengths for this type of analysis.
Engineers in the Geotechnical Branch of the Bridge Division are available to
assist with the determination of testing for specific situations and with the
slope stability analysis.
|
|
|
Recommended Construction
Practices |
|
Actual Soil ConditionsBecause soil borings are taken at discrete
locations, it is difficult to determine what soils conditions will be
experienced over a wider area. During construction of retaining walls, evaluate
the proposed retaining wall location and notify the project designers of
potential problems. Of concern are soils that are soft or wet, areas that are
producing groundwater, and areas that exhibit slope failures during excavation.
Each of these indicates potential stability problems and should be brought to
the attention of the wall designer. It may be necessary to remove and replace
poor soils, install drains, or modify the wall to address such field conditions.
Adherence to plans and specifications
Assure adherence to plans and
specifications during construction, especially with respect to width of
reinforced volume, length of straps, and type of backfill used. A number of the
short and long-term retaining wall performance problems are the result of
contractor failure to adhere to specification and plan requirements.
Plumb
MSE walls require particularly close attention to placement
and compaction of select fill. Monitor wall panels for verticality upon
completion of the backfilling of each panel. Initial panel batter should be
modified as required to achieve a plumb retaining wall. In many cases failure to
evaluate panel plumbness throughout construction has resulted in walls that are
significantly out of tolerance.
Weather
Make close observation of the retaining wall and backfill
after heavy rainfall, particularly in areas with higher volumes of rainfall.
Rain can soften or loosen the compacted backfill, and any rain that seeps into
the backfill can increase pressures on the wall panels. Check the temporary
surface cover for cracks and quickly seal any cracks to prevent seepage into the
backfill.
Base Backfill
Backfill the excavated area in the base of retaining
walls as quickly as possible. Accumulation of groundwater or surface water in
this area will soften the soils and reduce the stability of the walls.
Excavation at the base of an existing wall for installation of storm sewer,
roadway, of other structure should not proceed without a determination of wall
stability in the excavated condition.
Filter Fabric
Cohesionless select fill is subject to erosion and
piping if subjected to large quantities of water flowing into the wall. Filter
fabric is required at each panel joint and is designed to retain wall backfill
while allowing the water to pass. Gaps or voids in the filter fabric allow fill
to escape from behind the wall.
Sealing
Sealing of coping joints prevents excessive quantities of
water from entering the top of the wall. The current RW(TRF) standard sheet
requires all coping joints be sealed. This item of work should be required in
the field and monitored for compliance.
|
|
|
Recommended Maintenance |
|
Periodically inspect walls for evidence of backfill loss, loss of joint seals,
or movement. Reseal joints, particularly those that may allow surface water to
enter the wall backfill. If evidence of backfill loss is observed, backfill the
effected area with select fill if the area is accessible, or use flowable fill
if access is restricted. Water infiltration into voids in walls can cause
excessive pressures within the wall and result in displaced panels and wall
failures. Treat voided areas when they are small and manageable, as they will
always increase in size with time.Design Recommendations
MSE Walls
have been the most common retaining wall type on TxDOT projects for the past two
decades. The advantages of MSE walls include their low cost, low design effort,
speed of construction, and attractive appearance. MSE walls will continue to be
used in large quantities on TxDOT projects in the coming years. With this in
mind, the Bridge Division recommends that the following be considered on
upcoming projects utilizing MSE walls:
1. Selection of backfill for MSE walls
The 2004 Retaining Wall Standard
Specification (Item 423) lists four types of select backfill for MSE walls. Type
"B" is the default backfill for permanent MSE walls. It is a good quality
backfill, and will result in acceptable wall performance. Type "A" is a coarser,
higher quality material, exhibiting improved constructability and performance.
It is generally a more expensive backfill material, but should be considered for
projects where the enhanced performance would be desirable. With the
introduction of the new Type "A" material in the 2004 Standards Specifications,
it is no longer desirable for projects to include specific coarser backfill
gradations in project general notes. Type "C" backfill is used only on temporary
MSE walls, and is not appropriate for permanent walls. Type "D" backfill is a
free-draining, rock backfill. Type "D" is intended for use in MSE walls that are
subjected to inundation. Retaining walls subject to inundation should clearly
state that Type "D" backfill will be required below the 100-year water elevation
noted in the plans. Alternately, the entire wall volume may be specified as Type
"D". For projects requiring Type "A" or "D" backfill in the MSE walls, either
the general notes or the wall layouts themselves should clearly designate the
required backfill type. If no backfill type is specified, the specification
reverts to Type "B".
2. Increase Minimum Embedment
Consider increasing the minimum embedment of MSE walls from one foot to two
feet below finished grade. On projects where a small amount of fill is
to be placed below the wall, the designer may want to specify a minimum
embedment of two feet below finished grade or natural ground, whichever is
lower. The standard embedment of MSE walls is currently required to be one foot
unless otherwise shown in the plans. Several Districts have begun requiring a
minimum embed of two feet. Two feet gives a greater margin of error against
inaccurate surveys or grading, and provides an additional measure of stability
in soft soils. Projects over hard ground, or requiring excavation into rock may
want to retain the one-foot embedment.
3. Steep Slopes
Discourage the placement of walls on slopes steeper than 4:1. Many
soils in Texas exhibit marginal slope stability at 3:1 or even 4:1. The
additional load of a wall on these slopes reduces their stability and may result
in a failure. If project requirements dictate walls on slopes (perched walls), a
detailed slope stability analysis should be performed, and measures should be
taken to assure wall stability.
4. Avoid Using Cement-Stabilized Backfill
Although
cement-stabilized backfill is an option allowed in our standard specifications
and is an easy short-term solution, it compromises the long-term performance of
the wall because it reduces the wall's flexibility and it does not allow
drainage through the wall. On projects where settlement is anticipated due to
soft soil, a general note should be added to the plans eliminating
cement-stabilized backfill as an option.
Retaining walls serve well, but there are some key points for successful wall
performance: the correct system must be chosen for each location, and proper
construction practices must be employed. Also, as described above, there are a
number of design and maintenance issues that are equally important. Feel free to
call Mark McClelland, P.E., at (512) 416-2226.
|
|
|
Proprietary Retaining Wall
System Review |
|
|
|
Approved Concrete Block
Retaining Wall Systems |
|
|
|
Approved MSE Panel Systems |
|
|
|
Loss of Backfill in
Mechanically Stabilized Earth |
|
|
|
Underwater Drilled Shaft
Construction |
|
|