Economic Stimulus Project Detail

Data updated on: 4/02/2014 8:12 AM Print This Page
Project Summary
Project ID 362201001 TxDOT District Pharr County Name Cameron Funding Status Funded
Highway SH 550 Project Length 2.866 Miles Project Type Economic Stimulus Bid Date 2010-Mar
Work From OLD PORT ISABEL RD, ON NEW LOC Low Bid Amount $34,161,741.40
Work To SH 48
Description CONSTRUCT NEW TOLLROAD
Show Project Location
Contact Information
TxDOT Contact Homero Bazan, P.E. Phone: (956) 702-6214
Construction Company ANDERSON COLUMBIA CO., INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
05/13/2010 08/02/2010 390 655 143.33 % 100.31 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $1,638,409.60 $416,703.38
Construction $36,841,547.18 $37,567,713.82
Construction EngineeringConstruction Engineering Definition $1,504,661.88 $1,190,049.60
Contingency Contingency Definition $3,009,323.76
Indirect Indirect Definition $2,163,369.41
Total Cost $45,157,311.83 $39,174,466.80