Economic Stimulus Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 271801009 TxDOT District Austin County Name Travis Funding Status Funded
Highway RM 2769 Project Length .753 Miles Project Type Economic Stimulus Bid Date 2010-Apr
Work From RM 620 WEST 0.75 MI Low Bid Amount $4,093,286.00
Work To PROPOSED ANDERSON MILL RD
Description CONSTRUCT NEW ROADWAY LANES
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Walter Barfield, P.E. Phone: (512) 832-7136
Construction Company CASH CONSTRUCTION COMPANY, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
05/28/2010 08/31/2010 284 377 98.95 % 96.72 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $178,238.16 $958,131.68
Construction $3,919,782.61 $4,530,630.91
Construction EngineeringConstruction Engineering Definition $181,875.67 $403,729.59
Contingency Contingency Definition $236,438.37
Indirect Indirect Definition $238,984.63
Total Cost $4,755,319.44 $5,892,492.18