Economic Stimulus Project Detail

Data updated on: 4/02/2014 8:12 AM Print This Page
Project Summary
Project ID 141502040 TxDOT District Houston County Name Fort Bend Funding Status Funded
Highway FM 1464 Project Length 2.724 Miles Project Type Economic Stimulus Bid Date 2010-Feb
Work From SHILOH LAKES DR Low Bid Amount $13,611,377.00
Work To SH 99
Description WIDEN ROADWAY
Show Project Location
Contact Information
TxDOT Contact Bill Brudnick, P.E. Phone: (713) 802-5617
Construction Company HASSELL CONSTRUCTION COMPANY, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
04/14/2010 06/14/2010 393 652 107.95 % 94.95 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $666,957.47 $1,097,486.18
Construction $16,635,183.07 $14,177,850.22
Construction EngineeringConstruction Engineering Definition $612,511.97 $701,217.56
Contingency Contingency Definition $952,796.39
Indirect Indirect Definition $691,457.95
Total Cost $19,558,906.85 $15,976,553.96