Economic Stimulus Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
109101016 |
TxDOT District |
Dallas |
County Name |
Kaufman |
Funding Status |
Funded |
| Highway |
FM 740 |
Project Length |
.183 Miles |
Project Type |
Economic Stimulus |
Bid Date |
2009-Jul |
| Work From |
BUFFALO CREEK |
Low Bid Amount |
$2,856,520.65 |
| Work To |
' |
| Description |
REPLACE BRIDGE |
| Project Note |
This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources. |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Mo Bur, P.E. |
Phone: |
(214) 320-6281 |
| Construction Company |
DOUGHTIE CONSTRUCTION CO., INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
02/2008 |
06/2008 |
12/2008 |
04/2009 |
06/2009 |
03/2008 |
|
06/2009 |
| Actual Date |
02/2008 |
06/2008 |
10/2008 |
04/2009 |
06/2009 |
03/2008 |
|
06/2009 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 09/28/2009 |
02/16/2010 |
389 |
463 |
124.80 % |
100.83 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$150,444.64 |
$359,091.04 |
| Construction |
$3,303,452.22 |
$3,601,078.45 |
Construction Engineering |
$153,514.94 |
$302,651.99 |
Contingency
 |
$199,569.42 |
|
Indirect
 |
$133,557.99 |
|
| Total Cost |
$3,940,539.21 |
$4,262,821.48 |
|
 |