Project ID 091800161 TxDOT District Dallas County Name Dallas Funding Status Funded
Highway VA Project Length .001 Miles Project Type Economic Stimulus Bid Date 2010-Oct
Work From DISTRICTWIDE Low Bid Amount $1,255,000.00
Work To .
Description INSTALL TRAFFIC SIGNAL
Show Project Location
Contact Information
TxDOT Contact Maher Ghanayem, P.E. Phone: (214) 320-6691
Construction Company DURABLE SPECIALTIES, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
11/16/2010 03/14/2011 548 487 88.87 % 91.11 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $61,495.00 $123,185.68
Construction $1,424,730.00 $1,265,434.42
Construction EngineeringConstruction Engineering Definition $94,125.00 $146,918.67
Contingency Contingency Definition $87,850.00
Indirect Indirect Definition $60,867.50
Total Cost $1,729,067.50 $1,535,538.77