Economic Stimulus Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
091546036 |
TxDOT District |
San Antonio |
County Name |
Guadalupe |
Funding Status |
Funded |
| Highway |
VA |
Project Length |
.001 Miles |
Project Type |
Economic Stimulus |
Bid Date |
2009-Sep |
| Work From |
VARIOUS LOCATIONS IN SEGUIN |
Low Bid Amount |
$614,743.40 |
| Work To |
ON IH 10, US 90 US 90A, SH 123 |
| Description |
LANDSCAPE |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Gregg Granato, P.E. |
Phone: |
(210) 615-6049 |
| Construction Company |
LEGENDS LANDSCAPES LLC |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
05/2008 |
05/2008 |
05/2008 |
05/2008 |
05/2008 |
05/2008 |
|
09/2008 |
| Actual Date |
05/2007 |
07/2007 |
09/2007 |
12/2007 |
12/2007 |
12/2007 |
|
12/2007 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 10/16/2009 |
11/01/2009 |
125 |
98 |
78.40 % |
95.99 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$30,122.43 |
$12,989.68 |
| Construction |
$854,093.50 |
$626,056.00 |
Construction Engineering |
$46,105.76 |
$114,637.59 |
Contingency
 |
$43,032.04 |
|
Indirect
 |
$31,167.49 |
|
| Total Cost |
$1,004,521.22 |
$753,683.27 |
|
 |