Economic Stimulus Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 091200397 TxDOT District Houston County Name Harris Funding Status Funded
Highway VA Project Length .001 Miles Project Type Economic Stimulus Bid Date 2010-Mar
Work From VARIOUS LOCATIONS DISTRICTWIDE Low Bid Amount $4,068,749.00
Work To .
Description INSTALL TRAFFIC MANAGEMENT TECHNOLOGY
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Bill Brudnick, P.E. Phone: (713) 802-5617
Construction Company SIEMENS INDUSTRY, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
05/13/2010 08/15/2011 260 255 98.08 % 99.73 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $199,368.70 $19,413.74
Construction $5,468,600.80 $4,339,032.18
Construction EngineeringConstruction Engineering Definition $203,437.45 $107,588.12
Contingency Contingency Definition $264,468.69
Indirect Indirect Definition $206,692.45
Total Cost $6,342,568.09 $4,466,034.04