Economic Stimulus Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
091200335 |
TxDOT District |
Houston |
County Name |
Harris |
Funding Status |
Funded |
| Highway |
VA |
Project Length |
.001 Miles |
Project Type |
Economic Stimulus |
Bid Date |
2009-Sep |
| Work From |
VARIOUS LOCATIONS DISTRICTWIDE |
Low Bid Amount |
$898,349.73 |
| Work To |
. |
| Description |
INSTALL TRAFFIC SIGNAL |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Bill Brudnick, P.E. |
Phone: |
(713) 802-5617 |
| Construction Company |
STATEWIDE TRAFFIC SIGNAL COMPANY |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
05/2008 |
06/2008 |
07/2008 |
08/2008 |
01/2009 |
|
|
01/2009 |
| Actual Date |
05/2008 |
06/2008 |
07/2008 |
08/2008 |
01/2009 |
|
|
01/2009 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 11/16/2009 |
08/17/2010 |
188 |
142 |
75.53 % |
98.41 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$44,019.14 |
$42,013.58 |
| Construction |
$1,105,202.98 |
$1,195,086.38 |
Construction Engineering |
$67,376.23 |
$108,499.87 |
Contingency
 |
$62,884.48 |
|
Indirect
 |
$45,636.17 |
|
| Total Cost |
$1,325,119.00 |
$1,345,599.83 |
|
 |