Economic Stimulus Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 070003014 TxDOT District Austin County Name Travis Funding Status Funded
Highway SH 71 Project Length 1.524 Miles Project Type Economic Stimulus Bid Date 2010-Feb
Work From 0.27 MI EAST OF RO DRIVE Low Bid Amount $8,080,390.25
Work To 1.4 MI WEST OF BEE CREEK
Description CONSTRUCT CENTER TURN LANES
Show Project Location
Contact Information
TxDOT Contact Walter Barfield, P.E. Phone: (512) 832-7136
Construction Company AUSTIN BRIDGE & ROAD, LP
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
04/08/2010 06/07/2010 369 670 100.00 % 101.27 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $433,573.74 $220,853.83
Construction $9,051,419.79 $10,126,455.97
Construction EngineeringConstruction Engineering Definition $446,055.69 $823,559.17
Contingency Contingency Definition $575,875.55
Indirect Indirect Definition $581,342.76
Total Cost $11,088,267.53 $11,170,868.97