Economic Stimulus Project Detail

Data updated on: 10/01/2014 8:23 AM Print This Page
Project Summary
Project ID 067508084 TxDOT District Houston County Name Montgomery Funding Status Funded
Highway IH 45 Project Length 5.096 Miles Project Type Economic Stimulus Bid Date 2010-Mar
Work From NORTH OF CALVARY Low Bid Amount $57,617,648.46
Work To SOUTH OF FM 830
Description CONSTRUCT NEW ROADWAY LANES
Show Project Location
Contact Information
TxDOT Contact Pamela Elmer, P.E. Phone: (713) 802-5646
Construction Company WILLIAMS BROTHERS CONSTRUCTION CO., INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
05/07/2010 05/25/2010 1,177 1,204 101.43 % 98.26 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $2,780,201.34 $4,046,839.57
Construction $56,459,614.15 $60,928,077.94
Construction EngineeringConstruction Engineering Definition $2,269,552.11 $1,912,016.38
Contingency Contingency Definition $3,404,328.17
Indirect Indirect Definition $2,882,331.18
Total Cost $67,796,026.95 $66,886,933.89