Economic Stimulus Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
067508084 |
TxDOT District |
Houston |
County Name |
Montgomery |
Funding Status |
Funded |
| Highway |
IH 45 |
Project Length |
5.096 Miles |
Project Type |
Economic Stimulus |
Bid Date |
2010-Mar |
| Work From |
NORTH OF CALVARY |
Low Bid Amount |
$57,617,648.46 |
| Work To |
SOUTH OF FM 830 |
| Description |
CONSTRUCT NEW ROADWAY LANES |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Bill Brudnick, P.E. |
Phone: |
(713) 802-5617 |
| Construction Company |
WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
01/2007 |
07/2007 |
01/2009 |
12/2009 |
01/2010 |
01/2010 |
01/2010 |
01/2010 |
| Actual Date |
04/2007 |
09/2007 |
04/2009 |
03/2010 |
01/2010 |
01/2010 |
04/2010 |
01/2010 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 05/07/2010 |
05/25/2010 |
1,177 |
892 |
75.79 % |
76.92 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$2,780,201.34 |
$4,042,479.78 |
| Construction |
$56,459,614.15 |
$47,540,103.93 |
Construction Engineering |
$2,269,552.11 |
$1,215,887.55 |
Contingency
 |
$3,404,328.17 |
|
Indirect
 |
$2,882,331.18 |
|
| Total Cost |
$67,796,026.95 |