Economic Stimulus Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
061302055 |
TxDOT District |
San Antonio |
County Name |
Atascosa |
Funding Status |
Funded |
| Highway |
SH 16 |
Project Length |
.700 Miles |
Project Type |
Economic Stimulus |
Bid Date |
2009-Sep |
| Work From |
AT SH 173, N OF JOURDANTON |
Low Bid Amount |
$107,235.00 |
| Work To |
. |
| Description |
LANDSCAPE |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Gregg Granato, P.E. |
Phone: |
(210) 615-6049 |
| Construction Company |
ENCINO LANDSCAPE, INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
12/2008 |
01/2009 |
02/2009 |
02/2009 |
06/2009 |
02/2009 |
|
06/2009 |
| Actual Date |
01/2009 |
01/2009 |
02/2009 |
03/2009 |
01/2009 |
03/2009 |
|
06/2009 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 10/21/2009 |
12/02/2009 |
39 |
37 |
94.87 % |
85.77 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$5,254.52 |
$9,879.55 |
| Construction |
$149,468.58 |
$113,294.94 |
Construction Engineering |
$8,042.63 |
$33,392.01 |
Contingency
 |
$7,506.45 |
|
Indirect
 |
$5,436.81 |
|
| Total Cost |
$175,708.99 |
$156,566.50 |
|
 |