Economic Stimulus Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
054302047 |
TxDOT District |
Houston |
County Name |
Fort Bend |
Funding Status |
Funded |
| Highway |
FM 359 |
Project Length |
2.424 Miles |
Project Type |
Economic Stimulus |
Bid Date |
2010-Feb |
| Work From |
W OF FARMER ROAD |
Low Bid Amount |
$11,784,812.15 |
| Work To |
US 90A |
| Description |
WIDEN ROADWAY |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Bill Brudnick, P.E. |
Phone: |
(713) 802-5617 |
| Construction Company |
HASSELL CONSTRUCTION COMPANY, INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
06/2006 |
08/2009 |
09/2009 |
10/2009 |
06/2006 |
11/2009 |
11/2009 |
11/2009 |
| Actual Date |
06/2006 |
08/2009 |
09/2009 |
10/2009 |
06/2006 |
11/2009 |
11/2009 |
11/2009 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 04/01/2010 |
04/19/2010 |
468 |
728 |
124.23 % |
96.95 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$577,455.80 |
$1,767,710.02 |
| Construction |
$13,744,628.54 |
$12,560,761.08 |
Construction Engineering |
$530,316.55 |
$737,670.40 |
Contingency
 |
$766,012.79 |
|
Indirect
 |
$598,668.46 |
|
| Total Cost |
$16,217,082.14 |
$15,066,141.50 |
|
 |