Economic Stimulus Project Detail

Data updated on: 11/10/2014 3:25 PM Print This Page
Project Summary
Project ID 050402022 TxDOT District Fort Worth County Name Tarrant Funding Status Funded
Highway SH 121 Project Length .100 Miles Project Type Economic Stimulus Bid Date 2009-Nov
Work From SOUTH OF ARBORLAWN DRIVE Low Bid Amount $116,646,468.87
Work To SOUTH OF OVERTON RIDGE BLVD
Description CONSTRUCT NEW TOLLROAD
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Scot D. Smith, P.E. Phone: (817) 370-6673
Construction Company W.W. WEBBER, LLC
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
02/01/2010 03/15/2010 896 1,384 154.46 % 96.15 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $5,715,676.97 $272,006.58
Construction $135,456,050.43 $115,777,448.49
Construction EngineeringConstruction Engineering Definition $5,249,091.10 $5,879,247.14
Contingency Contingency Definition $8,165,252.82
Indirect Indirect Definition $7,337,062.89
Total Cost $161,923,134.21 $121,928,702.21