Economic Stimulus Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
042205004 |
TxDOT District |
Fort Worth |
County Name |
Johnson |
Funding Status |
Funded |
| Highway |
US 67 |
Project Length |
4.168 Miles |
Project Type |
Economic Stimulus |
Bid Date |
2010-Mar |
| Work From |
BU 67M |
Low Bid Amount |
$17,490,460.34 |
| Work To |
0.6 MILES EAST OF FM 4 |
| Description |
CONSTRUCT NEW ROADWAY LANES |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Scot D. Smith, P.E. |
Phone: |
(817) 370-6673 |
| Construction Company |
APAC-TEXAS, INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
05/1999 |
11/1999 |
02/2001 |
05/2009 |
05/2003 |
05/2009 |
05/2009 |
05/2009 |
| Actual Date |
05/1999 |
11/1999 |
02/2001 |
05/2009 |
05/2003 |
05/2009 |
05/2009 |
05/2009 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 05/13/2010 |
05/21/2010 |
384 |
659 |
171.61 % |
96.23 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$857,032.56 |
$203,475.19 |
| Construction |
$18,208,644.58 |
$17,996,927.98 |
Construction Engineering |
$787,070.72 |
$1,167,950.69 |
Contingency
 |
$1,136,879.92 |
|
Indirect
 |
$1,100,149.96 |
|
| Total Cost |
$22,089,777.74 |
$19,368,353.86 |
|
 |