Economic Stimulus Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 042205004 TxDOT District Fort Worth County Name Johnson Funding Status Funded
Highway US 67 Project Length 4.168 Miles Project Type Economic Stimulus Bid Date 2010-Mar
Work From BU 67M Low Bid Amount $17,490,460.34
Work To 0.6 MILES EAST OF FM 4
Description CONSTRUCT NEW ROADWAY LANES
Show Project Location
Contact Information
TxDOT Contact Scot D. Smith, P.E. Phone: (817) 370-6673
Construction Company APAC-TEXAS, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
05/13/2010 05/21/2010 384 659 171.61 % 96.23 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $857,032.56 $203,475.19
Construction $18,208,644.58 $17,996,927.98
Construction EngineeringConstruction Engineering Definition $787,070.72 $1,167,950.69
Contingency Contingency Definition $1,136,879.92
Indirect Indirect Definition $1,100,149.96
Total Cost $22,089,777.74 $19,368,353.86