Economic Stimulus Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
027107242 |
TxDOT District |
Houston |
County Name |
Harris |
Funding Status |
Funded |
| Highway |
IH 10 |
Project Length |
3.381 Miles |
Project Type |
Economic Stimulus |
Bid Date |
2010-Jan |
| Work From |
WASHINGTON AVE. |
Low Bid Amount |
$48,579,333.51 |
| Work To |
TAYLOR ST. |
| Description |
WIDEN ROADWAY |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Bill Brudnick, P.E. |
Phone: |
(713) 802-5617 |
| Construction Company |
BALFOUR BEATTY INFRASTRUCTURE, INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
08/2002 |
06/2006 |
12/2006 |
04/2009 |
08/2002 |
12/2009 |
12/2009 |
12/2009 |
| Actual Date |
08/2002 |
06/2006 |
12/2006 |
04/2009 |
08/2002 |
12/2009 |
12/2009 |
12/2009 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 03/26/2010 |
04/26/2010 |
777 |
764 |
79.50 % |
89.07 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$6,751,592.19 |
$7,671,672.32 |
| Construction |
$51,878,705.21 |
$45,864,589.09 |
Construction Engineering |
$2,086,263.99 |
$2,338,506.02 |
Contingency
 |
$4,125,239.73 |
|
Indirect
 |
$2,355,160.25 |
|
| Total Cost |
$67,196,961.37 |
$55,874,767.43 |
|
 |