Economic Stimulus Project Detail

Data updated on: 10/01/2014 8:23 AM Print This Page
Project Summary
Project ID 027107242 TxDOT District Houston County Name Harris Funding Status Funded
Highway IH 10 Project Length 3.381 Miles Project Type Economic Stimulus Bid Date 2010-Jan
Work From WASHINGTON AVE. Low Bid Amount $48,579,333.51
Work To TAYLOR ST.
Description WIDEN ROADWAY
Show Project Location
Contact Information
TxDOT Contact Pamela Elmer, P.E. Phone: (713) 802-5646
Construction Company BALFOUR BEATTY INFRASTRUCTURE, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
03/26/2010 04/26/2010 777 888 92.40 % 101.79 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $6,751,592.19 $7,716,938.91
Construction $51,878,705.21 $55,363,981.27
Construction EngineeringConstruction Engineering Definition $2,086,263.99 $2,903,947.13
Contingency Contingency Definition $4,125,239.73
Indirect Indirect Definition $2,355,160.25
Total Cost $67,196,961.37 $65,984,867.31