Economic Stimulus Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 027107094 TxDOT District Houston County Name Harris Funding Status Funded
Highway IH 10 Project Length 10.033 Miles Project Type Economic Stimulus Bid Date 2010-Jul
Work From EAST OF MEMORIAL BROOK Low Bid Amount $1,560,409.91
Work To WASHINGTON AVENUE IN SECTIONS
Description LANDSCAPE
Show Project Location
Contact Information
TxDOT Contact Bill Brudnick, P.E. Phone: (713) 802-5617
Construction Company BOYER, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
09/27/2010 10/13/2010 90 80 88.89 % 93.28 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $76,460.09 $37,785.79
Construction $1,951,976.68 $1,776,563.06
Construction EngineeringConstruction Engineering Definition $93,624.59 $130,280.83
Contingency Contingency Definition $109,228.69
Indirect Indirect Definition $79,268.82
Total Cost $2,310,558.87 $1,944,629.68