Economic Stimulus Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 019402087 TxDOT District Wichita Falls County Name Cooke Funding Status Funded
Highway IH 35 Project Length 3.137 Miles Project Type Economic Stimulus Bid Date 2010-Sep
Work From NEAR FM 1202 Low Bid Amount $14,049,261.79
Work To NEAR US 82
Description REBUILD ROADWAY
Show Project Location
Contact Information
TxDOT Contact Danny Brown, P.E. Phone: (940) 720-7740
Construction Company ED BELL CONSTRUCTION COMPANY
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
11/04/2010 02/14/2011 600 558 93.00 % 97.72 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $647,021.61 $121,242.15
Construction $12,980,958.02 $14,111,628.04
Construction EngineeringConstruction Engineering Definition $638,629.95 $705,193.89
Contingency Contingency Definition $922,465.48
Indirect Indirect Definition $1,178,733.08
Total Cost $16,367,808.14 $14,938,064.08