Economic Stimulus Project Detail

Data updated on: 6/03/2013 7:32 AM Print This Page
Project Summary
Project ID 005503023 TxDOT District Waco County Name Coryell Funding Status Funded
Highway US 84 Project Length 10.235 Miles Project Type Economic Stimulus Bid Date 2009-Apr
Work From FM 932 Low Bid Amount $8,735,023.00
Work To HAMILTON C/L
Description CONSTRUCT NEW ROADWAY LANES
Show Project Location
Contact Information
TxDOT Contact Andy Petter, P.E. Phone: (254) 867-2740
Construction Company JAY MILLS CONTRACTING, INCORPORATED
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
06/18/2009 06/24/2009 408 345 84.56 % 104.30 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $428,016.13 $202,048.00
Construction $12,429,750.50 $9,775,265.31
Construction EngineeringConstruction Engineering Definition $436,751.15 $331,604.48
Contingency Contingency Definition $611,451.61
Indirect Indirect Definition $376,479.49
Total Cost $14,282,448.88 $10,308,917.79