Economic Stimulus Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 003904080 TxDOT District Pharr County Name Hidalgo Funding Status Funded
Highway BU 83-S Project Length 1.727 Miles Project Type Economic Stimulus Bid Date 2010-Mar
Work From FM 1015 IN WESLACO Low Bid Amount $4,813,173.28
Work To 0.7 MI E SP 31 IN MERCEDES
Description CONSTRUCT NEW ROADWAY LANES
Show Project Location
Contact Information
TxDOT Contact Homero Bazan, P.E. Phone: (956) 702-6214
Construction Company FOREMOST PAVING, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
05/11/2010 06/01/2010 125 242 100.00 % 100.02 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $149,208.37 $597,167.31
Construction $4,896,711.42 $5,359,391.22
Construction EngineeringConstruction Engineering Definition $240,658.66 $324,001.40
Contingency Contingency Definition $312,856.26
Indirect Indirect Definition $311,412.31
Total Cost $5,910,847.02 $6,280,559.93