Economic Stimulus Project Detail

Data updated on: 4/02/2014 8:12 AM Print This Page
Project Summary
Project ID 002811195 TxDOT District Beaumont County Name Orange Funding Status Funded
Highway IH 10 Project Length .589 Miles Project Type Economic Stimulus Bid Date 2010-Feb
Work From SH 62, EAST Low Bid Amount $38,315,248.30
Work To UP RR
Description REBUILD ROADWAY
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Phillip Lujan, P.E. Phone: (409) 898-5740
Construction Company WILLIAMS BROTHERS CONSTRUCTION CO., INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
04/22/2010 05/17/2010 744 792 105.60 % 96.56 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $1,722,390.94 $149,223.63
Construction $34,241,631.50 $41,849,885.33
Construction EngineeringConstruction Engineering Definition $1,581,787.60 $1,892,926.57
Contingency Contingency Definition $3,163,575.19
Indirect Indirect Definition $2,070,384.20
Total Cost $42,779,769.43 $43,892,035.53