Economic Stimulus Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
001602104 |
TxDOT District |
Austin |
County Name |
Hays |
Funding Status |
Funded |
| Highway |
IH 35 |
Project Length |
.777 Miles |
Project Type |
Economic Stimulus |
Bid Date |
2009-Aug |
| Work From |
2250 FT N OF MAIN ST |
Low Bid Amount |
$9,393,526.51 |
| Work To |
2000 FT S OF MAIN ST |
| Description |
CONSTRUCT BRIDGE |
| Project Note |
This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources. |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Walter Barfield, P.E. |
Phone: |
(512) 832-7136 |
| Construction Company |
FIDELITY AND DEPOSIT COMPANY OF MARYLAND |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
07/2008 |
10/2008 |
01/2009 |
|
05/2009 |
|
|
05/2009 |
| Actual Date |
07/2008 |
10/2008 |
01/2009 |
|
05/2009 |
|
|
05/2009 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 10/09/2009 |
11/02/2009 |
603 |
644 |
106.80 % |
101.26 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$474,393.28 |
$51,538.22 |
| Construction |
$14,231,376.42 |
$11,644,999.32 |
Construction Engineering |
$387,259.81 |
$1,346,197.84 |
Contingency
 |
$629,297.20 |
|
Indirect
 |
$580,889.72 |
|
| Total Cost |
$16,303,216.43 |
$13,042,735.38 |
|
 |