Economic Stimulus Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 001602104 TxDOT District Austin County Name Hays Funding Status Funded
Highway IH 35 Project Length .777 Miles Project Type Economic Stimulus Bid Date 2009-Aug
Work From 2250 FT N OF MAIN ST Low Bid Amount $9,393,526.51
Work To 2000 FT S OF MAIN ST
Description CONSTRUCT BRIDGE
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Walter Barfield, P.E. Phone: (512) 832-7136
Construction Company FIDELITY AND DEPOSIT COMPANY OF MARYLAND
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
10/09/2009 11/02/2009 603 644 106.80 % 101.26 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $474,393.28 $51,538.22
Construction $14,231,376.42 $11,644,999.32
Construction EngineeringConstruction Engineering Definition $387,259.81 $1,346,197.84
Contingency Contingency Definition $629,297.20
Indirect Indirect Definition $580,889.72
Total Cost $16,303,216.43 $13,042,735.38