Proposition 14 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 362801001 TxDOT District El Paso County Name El Paso Funding Status Funded
Highway SS 1966 Project Length .650 Miles Project Type Proposition 14 Bid Date 2013-Feb
Work From US 85 (PAISANO DR) Low Bid Amount $30,958,882.33
Work To SCHUSTER AVE
Description CONSTRUCT NEW ROAD
Show Project Location
Contact Information
TxDOT Contact Celia Salazar, P.E. Phone: (915)-790-4400
Construction Company HAYDON BUILDING CORP.
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 03/2012 03/2013 12/2013 06/2014 04/2013 05/2014 05/2014 06/2014
Actual Date 02/2012 11/2012 11/2012 11/2012 01/2013 01/2013 01/2013 01/2013
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $1,433,719.29 $1,795,791.51
Construction $37,489,472.12 $4,334.99
Construction EngineeringConstruction Engineering Definition $1,433,719.29 $5,961.87
Contingency Contingency Definition $365,744.72
Indirect Indirect Definition $2,430,272.27
Total Cost $43,152,927.69 $1,806,088.37