Proposition 14 Project Detail

Data updated on: 4/02/2014 8:12 AM Print This Page
Project Summary
Project ID 362301001 TxDOT District Waco County Name Coryell Funding Status Funded
Highway SH 9 Project Length 3.176 Miles Project Type Proposition 14 Bid Date 2010-Dec
Work From US 190 Low Bid Amount $31,901,241.27
Work To FM 116
Description CONSTRUCT NEW ROAD
Show Project Location
Contact Information
TxDOT Contact Andy Petter, P.E. Phone: (254) 867-2740
Construction Company LEDCOR CMI INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
01/24/2011 02/14/2011 609 774 115.70 % 96.42 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $1,526,246.92 $2,034,572.73
Construction $31,298,144.79 $32,876,737.07
Construction EngineeringConstruction Engineering Definition $1,442,760.52 $1,234,926.71
Contingency Contingency Definition $2,885,521.04
Indirect Indirect Definition $1,740,931.03
Total Cost $38,893,604.30 $36,146,236.51