Proposition 14 Project Detail

Data updated on: 8/01/2014 2:38 PM Print This Page
Project Summary
Project ID 313802010 TxDOT District Bryan County Name Brazos Funding Status Funded
Highway SH 47 Project Length 1.630 Miles Project Type Proposition 14 Bid Date 2011-Dec
Work From AT HSC PARKWAY Low Bid Amount $9,732,289.59
Work To .
Description CONSTRUCT INTERCHANGE
Show Project Location
Contact Information
TxDOT Contact Bob Appleton, P.E. Phone: (979) 778-2165
Construction Company KNIFE RIVER CORPORATION - SOUTH
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
01/24/2012 02/09/2012 223 310 98.10 % 96.05 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $488,158.56 $350,586.26
Construction $9,962,419.53 $10,345,257.62
Construction EngineeringConstruction Engineering Definition $467,237.48 $453,623.92
Contingency Contingency Definition $297,876.34
Indirect Indirect Definition $684,418.22
Total Cost $11,900,110.13 $11,149,467.80