Proposition 14 Project Detail

Data updated on: 4/02/2014 8:12 AM Print This Page
Project Summary
Project ID 239901060 TxDOT District Bryan County Name Brazos Funding Status Funded
Highway FM 2818 Project Length 1.293 Miles Project Type Proposition 14 Bid Date 2011-Aug
Work From AT THE INTERSECTION OF FM 2818 Low Bid Amount $14,139,148.97
Work To AND FM 1179
Description CONSTRUCT INTERCHANGE
Show Project Location
Contact Information
TxDOT Contact Bob Appleton, P.E. Phone: (979) 778-2165
Construction Company KNIFE RIVER CORPORATION - SOUTH
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
10/21/2011 02/20/2012 316 316 95.76 % 70.53 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $692,818.30 $728,097.43
Construction $13,222,814.92 $10,131,405.36
Construction EngineeringConstruction Engineering Definition $636,261.70 $424,508.59
Contingency Contingency Definition $919,044.68
Indirect Indirect Definition $845,521.11
Total Cost $16,316,460.71 $11,284,011.38