Proposition 14 Project Detail

Data updated on: 7/01/2014 10:05AM Print This Page
Project Summary
Project ID 239801047 TxDOT District Abilene County Name Taylor Funding Status Funded
Highway LP 322 Project Length 2.254 Miles Project Type Proposition 14 Bid Date 2013-Sep
Work From LYTLE CREEK Low Bid Amount $4,222,065.12
Work To NEAR MAPLE STREET
Description CONSTRUCT FRONTAGE ROADS
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Blair Haynie, P.E. Phone: (325) 676-6810
Construction Company CONTRACT PAVING CO.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
10/17/2013 10/21/2013 137 106 77.37 % 62.10 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $206,881.19 $305,911.50
Construction $4,447,629.39 $2,757,719.05
Construction EngineeringConstruction Engineering Definition $269,367.75 $101,100.98
Contingency Contingency Definition $54,464.64
Indirect Indirect Definition $203,925.75
Total Cost $5,182,268.72 $3,164,731.53