Proposition 14 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
224301009 |
TxDOT District |
Pharr |
County Name |
Cameron |
Funding Status |
Funded |
| Highway |
FM 106 |
Project Length |
11.440 Miles |
Project Type |
Proposition 14 |
District Est. Bid Date |
2014-Aug |
| Work From |
FM 1847 ON GEN BRANT RD, E & S |
|
|
| Work To |
FM 510 |
| Description |
REBUILD ROADWAY |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Homero Bazan, P.E. |
Phone: |
(956) 702-6214 |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
05/2005 |
01/2006 |
01/2007 |
09/2008 |
04/2035 |
04/2035 |
04/2035 |
04/2035 |
| Actual Date |
05/2005 |
01/2006 |
04/2013 |
|
|
|
|
|
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$696,922.05 |
$625,698.80 |
| Construction |
$14,222,898.88 |
$0.00 |
Construction Engineering |
$696,922.05 |
$0.00 |
Contingency
 |
$7,111.45 |
|
Indirect
 |
$732,479.29 |
|
| Total Cost |
$16,356,333.72 |
$625,698.80 |
|
 |