Project ID 222401085 TxDOT District Odessa County Name Ector Funding Status Funded
Highway LP 338 Project Length 5.500 Miles Project Type Proposition 14 District Est. Bid Date 2014-Mar
Work From YUKON ROAD
Work To 0.5 MI W OF US 385
Description WIDEN AND REHABILITATE ROADWAY
Show Project Location
Contact Information
TxDOT Contact Gary J. Law, P.E. Phone: (432) 332-0501
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 12/2012 02/2013 04/2013 06/2013 06/2013 03/2013 05/2013 06/2013
Actual Date 02/2013
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $307,653.77 $25,142.62
Construction $6,278,648.46 $0.00
Construction EngineeringConstruction Engineering Definition $311,420.96 $0.00
Contingency Contingency Definition $124,945.10
Indirect Indirect Definition $524,267.15
Total Cost $7,546,935.44 $25,142.62