Proposition 14 Project Detail

Data updated on: 10/01/2014 8:23 AM Print This Page
Project Summary
Project ID 212104093 TxDOT District El Paso County Name El Paso Funding Status Funded
Highway IH 10 Project Length 1.399 Miles Project Type Proposition 14 Bid Date 2014-Aug
Work From IH 10 @ LP 375 Low Bid Amount $31,489,367.95
Work To .
Description CONSTRUCT INTERCHANGE
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Celia Salazar, P.E. Phone: (915)-790-4400
Construction Company HAYDON BUILDING CORP.
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 02/2014 03/2014 05/2014 06/2014 03/2014 06/2014
Actual Date 02/2014 03/2014 05/2014 06/2014 07/2014 07/2014
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $1,520,325.10 $1,123,506.88
Construction $34,486,586.80 $0.00
Construction EngineeringConstruction Engineering Definition $1,455,168.31 $1,231,005.21
Contingency Contingency Definition $927,708.58
Indirect Indirect Definition $1,498,606.17
Total Cost $39,888,394.96 $2,354,512.09